01 61 00 - Product Requirements.pdf

PDF 478 KB Posted

Attached to
West Pump Station Replacement Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

This is a Product Requirements specification document prepared by Herbert, Rowland & Grubic, Inc. for the West Pump Station Replacement Project, a construction project for the Northwestern Chester County Municipal Authority in Pennsylvania. The specification establishes requirements for all products and materials to be incorporated into the Work, including named products, new products, or approved equal products. Products must comply with specified requirements and reference standards, be furnished by qualified manufacturers suitable for intended use, and be delivered in manufacturer's original sealed containers with complete labels and instructions. All products must be new at the time of installation unless specifically permitted otherwise. Delivery must follow manufacturer's instructions and be coordinated to minimize on-site storage. The specification addresses three separate bid contracts: WPS-1 for General Construction, WPS-2 for Electrical Construction, and WPS-3 for Mechanical Construction, with bids due online by Wednesday, May 20, 2026 at 10:00 AM local time.

Product storage and handling requirements mandate that all materials be stored according to manufacturer's instructions with seals and labels intact and legible. Sensitive products require weathertight, climate-controlled storage, while exterior fabricated products must be placed on sloped supports above ground. Loose granular materials must be stored on solid flat surfaces in well-drained areas to prevent contamination. The specification reserves the Engineer's right to limit product selection to those with warranties not in conflict with Contract Documents. Where specifications name a single manufacturer or product, that named product must be provided; where multiple manufacturers are listed, the Contractor may select one compliant option. The project generally includes construction of a new suction lift pump station with building and site improvements, demolition of the existing pump station, sanitary and force main piping construction, pump installation, and site improvements including fencing, pavement, and electrical connections. Bidding documents are available through https://pennbid.bonfirehub.com/.

View the file

Other files

File Type Posted
40 05 53 - Identification For Process Piping.pdf PDF
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 61 00 – PRODUCT REQUIREMENTS

Herbert, Rowland & Grubic, Inc. 01 61 00 - 1 000483.0450

SECTION 01 61 00 – PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Products.

B. Product delivery requirements.

C. Product storage and handling requirements.

D. Product options.

E. Equipment electrical characteristics and components.

1.2 DEFINITIONS

A. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents.

2. New Products: Items that have not previously been incorporated into another project or facility. Products salvaged or recycled from other projects are not considered new products.

3. “Or Equal” Product: Product that is demonstrated and approved through submittal process to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

B. Basis of Design Product: The Project was designed generally around the first or singularly named manufacturers. Where a specific manufacturer's product is named, including make or model number or other designation, it is to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics. If the Contractor chooses to furnish an alternately named manufacturer or product, a substitution request must be made in accordance with paragraph 7.05 of the General Conditions.

1.3 PRODUCTS

A. At minimum, comply with specified requirements and reference standards.

B. Specified products define standard of quality, type, function, dimension, appearance, and performance required.

Herbert, Rowland & Grubic, Inc. 01 61 00 - 2 000483.0450

C. Furnish products of qualified manufacturers that are suitable for intended use. Furnish products of each type by single manufacturer unless specified otherwise. Confirm that manufacturer's production capacity can provide sufficient product, on time, to meet Project requirements.

D. Do not use materials and equipment removed from existing premises except as specifically permitted by Contract Documents.

E. Furnish interchangeable components from same manufacturer for components being replaced.

1.4 PRODUCT DELIVERY REQUIREMENTS

A. Comply with delivery requirements in Section 01 74 19 – Construction Waste Management and Disposal.

B. Transport and handle products according to manufacturer's instructions.

C. Deliver products in manufacturer's original sealed container or packaging, complete with labels/instructions for storing, handling, unpacking, protecting, and installing.

D. Promptly inspect shipments to ensure products comply with requirements, quantities are correct, and products are undamaged.

E. Provide equipment and personnel to handle products; use methods to prevent soiling, disfigurement, or damage.

F. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.

1. Coordinate delivery with installation to ensure minimum storage for items that are hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

1.5 PRODUCT STORAGE AND HANDLING REQUIREMENTS

A. Store and protect products according to manufacturer's instructions.

B. Store products with seals and labels intact and legible.

C. Store sensitive products in weathertight, climate-controlled enclosures in an environment suitable to product.

D. For exterior storage of fabricated products, place products on sloped supports aboveground.

E. Provide off-Site storage and protection when Site does not permit on-Site storage or protection.

Herbert, Rowland & Grubic, Inc. 01 61 00 - 3 000483.0450

F. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.

G. Store loose granular materials on solid flat surfaces in well-drained area. Prevent mixing with foreign matter.

H. Provide equipment and personnel to store products; use methods to prevent soiling, disfigurement, or damage.

I. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.

PART 2 - PRODUCTS

2.1 PRODUCT SELECTION PROCEDURES

A. General Product Requirements: Provide products that comply with the Contract Documents, that are undamaged and that are new at time of installation.

1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.

2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.

3. Engineer reserves the right to limit selection to products with warranties not in conflict with requirements of the Contract Documents.

B. Product Selection Procedures:

1. Product: Where Specifications name a single product and manufacturer, provide the named product. Where Specifications include a list of names of both products and manufacturers, provide one of the products listed that complies with requirements.

2. Manufacturer/Source: Where Specifications name a single manufacturer or source, provide a product by the named manufacturer or equal source that complies with requirements. Where Specifications include a list of manufacturers' names, provide a product by one of the manufacturers listed that complies with requirements.

3. Basis-of-Design Product: Where Specifications name a product and manufacturer, provide the specified product. Where Contract Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named provide named product.

4. Visual Selection Specification: Where Specifications include the phrase "as selected from manufacturer's colors, patterns, textures" or a similar phrase, select a product that complies with other specified requirements.

a. Standard Range: Where Specifications include the phrase "standard range of colors, patterns, textures" or similar phrase, Owner and Engineer will select color, pattern, density, or texture from manufacturer's product line that does not include premium items.

b. Full Range: Where Specifications include the phrase "full range of colors, patterns, textures" or similar phrase, Owner and Engineer will select

Herbert, Rowland & Grubic, Inc. 01 61 00 - 4 000483.0450 color, pattern, density, or texture from manufacturer's product line that includes both standard and premium items.

PART 3 - EXECUTION - Not Used

END OF SECTION 01 61 00