This is a Photographic Documentation specification prepared by Herbert, Rowland & Grubic, Inc. for the West Pump Station Replacement Project managed by Northwestern Chester County Municipal Authority in Pennsylvania. The specification establishes requirements for comprehensive photographic documentation throughout the construction process, including preconstruction photographs covering the entire construction limits and surrounding areas such as driveways, sidewalks, utilities, landscaping, and building exteriors; bi-weekly periodic construction photographs timed to coincide with payment application cutoff dates; and final completion photographs after substantial completion. All photographs must be submitted in digital format within three days of capture using cameras with minimum 8-megapixel sensor resolution, formatted as JPG files with minimum 3200 by 2400 pixel dimensions, unaltered and date/time stamped. Each image must include comprehensive metadata identification containing project name, photographer contact information, engineer and contractor names, photograph date, detailed vantage point description with compass direction and elevation, and a unique sequential identifier keyed to an accompanying key plan.

The specification requires that all photographs be taken with maximum depth of field and in sharp focus, with unacceptable photographs rejected if they contain blurry or out-of-focus areas. A key plan of the project site and building must be submitted identifying all vantage points with notation of location and direction. All copyright usage rights and unlimited reproduction rights must be transferred to the Owner. The preconstruction photography must document drainage patterns, retaining walls, headwalls, fences, visible utilities, and all structures within zones of influence. This photographic documentation will serve as project record documents required at closeout as referenced in Section 01 77 00 of the specifications.

View the file

Other files

File Type Posted
40 05 53 - Identification For Process Piping.pdf PDF
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 32 33 – PHOTOGRAPHIC DOCUMENTATION

Herbert, Rowland & Grubic, Inc. 01 32 33 - 1 000483.0450

SECTION 01 32 33 – PHOTOGRAPHIC DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Preconstruction photographs.

2. Periodic construction photographs.

3. Final completion construction photographs.

B. Related Sections:

1. Section 01 33 00 – Submittals Procedures: Procedures for submitting photographic documentation.

2. Section 01 77 00 – Closeout Procedures: Procedures for submitting photographic documentation as project record documents at Project closeout.

1.2 SUBMITTALS

A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each photograph. Indicate elevation or story of construction. Include same information as corresponding photographic documentation.

B. Digital Photographs: Submit image files within three days of taking photographs.

1. Digital Camera: Minimum sensor resolution of 8 megapixels.

2. Format: JPG with minimum 3200 by 2400 pixels, in unaltered original files, with same aspect ratio as the sensor, uncropped, date and time stamped, in folder named by date of photograph, accompanied by key plan file.

3. Identification: Provide the following information with each image description in file metadata tag:

a. Name of Project.

b. Name and contact information for photographer.

c. Name of Engineer.

d. Name of Contractor.

e. Date photograph was taken.

f. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.

g. Unique sequential identifier keyed to accompanying key plan.

1.3 USAGE RIGHTS

A. Transfer copyright usage rights to Owner for unlimited use and reproduction of photographic documentation.

01 32 33 – PHOTOGRAPHIC DOCUMENTATION

Herbert, Rowland & Grubic, Inc. 01 32 33 - 2 000483.0450

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION

3.1 GENERAL

A. Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted.

1. Maintain key plan with each set of construction photographs that identifies each photographic location.

3.2 PRECONSTRUCTION PHOTOGRAPHS

A. Photographic documentation is required prior to the start of any construction. Coverage shall include everything within the construction limits as identified on the Contract Drawings.

B. Include coverage driveways, sidewalks, curbs, ditches (to show drainage patterns), street (as full width as possible), landscaping, trees, shrubs, culverts, catch basins, retaining walls, headwalls, fences, visible utilities, and building exteriors within the zones of influence. Buildings should be identified visibly when possible.

C. Properly identify all photographs by number, date, locations and project name.

3.3 PERIODIC CONSTRUCTION PHOTOGRAPHS

A. Take photographs bi-weekly, with timing each month adjusted to coincide with the cutoff date associated with each Application for Payment. Select vantage points to show status of construction and progress since last photographs were taken.

3.4 FINAL COMPLETION CONSTRUCTION PHOTOGRAPHS

A. Take color photographs after date of Substantial Completion for submission as project record documents. Select vantage points to show status of construction and progress since last photographs were taken.

END OF SECTION 01 32 33