01 31 13 - Project Coordination.pdf

PDF 475 KB Posted

Attached to
West Pump Station Replacement Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

This is a Project Coordination specification document prepared by Herbert, Rowland & Grubic, Inc. for the West Pump Station Replacement Project, a construction initiative by the Northwestern Chester County Municipal Authority in Pennsylvania. The project encompasses construction of a new suction lift style pump station with building and site improvements to replace the existing West Pump Station, including demolition of the existing below-grade package pump station, construction of sanitary sewer piping and associated manholes, installation of new pumps, construction of force main piping, and general site improvements such as fencing, gates, pavement, and electrical connections. The project is divided into three separate contracts: WPS-1 for General Construction, WPS-2 for Electrical Construction, and WPS-3 for Mechanical Construction, with bids due on a lump sum basis by Wednesday, May 20, 2026 at 10:00 AM local time. Bidding documents are available through the designated website at https://pennbid.bonfirehub.com/, where prospective bidders are encouraged to register as plan holders.

The specification establishes coordination requirements for the contractor, including the preparation of coordination drawings, scheduling of submittals and work sequencing, verification of utility compatibility, and coordination meetings with personnel and subcontractors. The contractor is required to maintain all necessary utility services to the public throughout construction and manage operations in existing occupied areas with minimal disruption, performing work only after written approval from the Owner and the Engineer. The contractor bears full responsibility for costs associated with any damage to existing facilities, repairs, or alternate facilities required to maintain operations beyond the planned schedule. Alteration procedures require skilled installers, proper surface preparation, removal of unsuitable materials, daily cleaning of occupied areas, and careful restoration work to match existing products and finishes with neat transitions between new and existing work.

View the file

Other files

File Type Posted
40 05 53 - Identification For Process Piping.pdf PDF
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 31 13 – PROJECT COORDINATION

Herbert, Rowland & Grubic, Inc. 01 31 13 - 1 000483.0450

SECTION 01 31 13 – PROJECT COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes

1. Coordination and Project conditions.

B. Related Sections

1. Section 01 12 00 – Multiple Contract Summary: description of the division of work among separate contracts and responsibility for coordination activities not in this Section.

2. Section 01 32 16 – Construction Progress Schedule: preparing and submitting Contractor's construction schedule.

3. Section 01 73 00 – Execution Requirements: procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

4. Section 01 77 00 – Closeout Procedures: coordinating closeout of the Contract.

1.2 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of various Sections of Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.

B. Verify that utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate Work of various Sections having interdependent responsibilities for installing, connecting to, and placing operating equipment in service.

C. Coordinate space requirements, supports, and installation of mechanical and electrical Work indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit as closely as practical; place runs parallel with lines of building. Use spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

1. Coordination Drawings: Prepare as required to coordinate all portions of Work.

Show relationship and integration of different construction elements that require coordination during fabrication or installation to fit in space provided or to function as intended. Indicate locations where space is limited for installation and access and where sequencing and coordination of installations are important.

D. Coordination Meetings: In addition to other meetings specified in this Section, hold coordination meetings with personnel and Subcontractors to ensure coordination of Work.

E. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within construction. Coordinate locations of fixtures and outlets with finish elements.

Herbert, Rowland & Grubic, Inc. 01 31 13 - 2 000483.0450

F. Coordinate completion and clean-up of Work of separate Sections in preparation for Substantial Completion and for portions of Work designated for Owner’s occupancy.

G. After Owner's occupancy of premises, coordinate access to Site for correction of defective Work and Work not complying with Contract Documents, to minimize disruption of Owner's activities.

1.3 COORDINATION AND MAINTENANCE OF SERVICE DURING CONSTRUCTION

A. The Contractor(s) will, at all times throughout the Work, cooperate fully with the Owner in maintaining all necessary utility services to the public.

B. The Work involves modifications to and the demolition of existing facilities and structures which must be completed in sequence with one another due to the physical requirements of the Work or the need to maintain operations of existing facility.

C. Should the Contractor's operations damage any existing facilities and render them unavailable for continued use prior to the scheduled time for their removal, the Contractor will take immediate action to furnish, install, and place into operation alternate equivalent facilities. Should only minor repairs be required to the existing facilities, the Contractor shall immediately make such necessary repairs and restore the existing facilities to full service. All costs for such repairs or additional costs for operation of alternate facilities for a period of time longer than planned will be paid for by the Contractor.

D. The nature, location, capacity, and type of facilities proposed for maintaining continuity of Owner operations will at all times are subject to the approval of the Engineer.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION

3.1 ALTERATION PROCEDURES

A. Designated areas of existing facilities will be occupied for normal operations during progress of construction. Cooperate with Owner in scheduling operations to minimize conflict and to permit continuous usage.

1. Perform Work not to interfere with operations of occupied areas.

2. Keep utility and service outages to a minimum and perform only after written approval of Owner.

3. Clean Owner-occupied areas daily. Clean spillage, overspray, and heavy collection of dust in Owner-occupied areas immediately.

B. Materials: As specified in product Sections; match existing products with new and salvaged products for patching and extending Work.

C. Employ skilled and experienced installer to perform alteration and renovation Work.

Herbert, Rowland & Grubic, Inc. 01 31 13 - 3 000483.0450

D. Cut, move, or remove items as necessary for access to alterations and renovation Work.

Replace and restore at completion. Comply with Section 01 73 00 – Execution Requirements

E. Remove unsuitable material not marked for salvage, including rotted wood, corroded metals, and deteriorated masonry and concrete. Replace materials as specified for finished Work.

F. Remove debris and abandoned items from area and from concealed spaces.

G. Prepare surface and remove surface finishes to permit installation of new Work and finishes.

H. Close openings in exterior surfaces to protect existing Work from weather and extremes of temperature and humidity.

I. Remove, cut, and patch Work to minimize damage and to permit restoring products and finishes to specified condition.

J. Refinish existing visible surfaces to remain in renovated rooms and spaces, to specified condition for each material, with neat transition to adjacent finishes.

K. Where new Work abuts or aligns with existing Work, provide smooth and even transition.

Patch Work to match existing adjacent Work in texture and appearance.

L. When finished surfaces are cut so that smooth transition with new Work is not possible, terminate existing surface along straight line at natural line of division and submit recommendation to Engineer for review.

M. Where change of plane of 1/4 inch or more occurs, submit recommendation for providing smooth transition to Engineer for review.

N. Trim existing doors to clear new floor finish. Refinish trim to specified condition.

O. Patch or replace portions of existing surfaces that are damaged, lifted, discolored, or showing other imperfections.

P. Finish surfaces as specified in individual product Sections.

END OF SECTION 01 31 13