This is a Contract Modification Procedures document for the West Pump Station Replacement Project managed by Northwestern Chester County Municipal Authority in Pennsylvania. The document outlines the procedural framework for handling changes to the construction contract, including processes for requests for interpretation (RFI), minor changes, proposal requests, change orders, and work change directives. The project involves three separate contracts: WPS-1 (General Construction), WPS-2 (Electrical Construction), and WPS-3 (Mechanical Construction), all to be bid on a lump sum basis. Bids are due online by Wednesday, May 20, 2026 at 10:00 AM local time, with public opening and reading of bids to follow immediately. The project scope includes construction of a new suction lift style pump station with building and site improvements, demolition of the existing below-grade package pump station, construction of sanitary sewer piping and associated appurtenances, installation of new pumps, force main piping, and general site improvements including fencing, gates, pavement, and electrical connections. Bidding documents are available through the designated website at https://pennbid.bonfirehub.com/, and prospective bidders are required to register as plan holders on the designated website for access to all official notifications, addenda, and project information.
The modification procedures document establishes that the contractor must designate an authorized individual to receive change documents and maintain liaison with the engineer. Contractors are required to submit proposal requests within 10 days of issuance, including detailed cost breakdowns with quantities, unit costs, applicable taxes, delivery charges, equipment rental, labor and equipment costs directly attributable to changes, and updated construction schedules reflecting the impact of proposed modifications. Change orders require approval by the owner and execution by both owner and contractor, and can be structured as stipulated price change orders or unit price change orders. The document requires contractors to maintain detailed records of work performed on a time and material basis and promptly revise all contract documents, including the Schedule of Values, Applications for Payment, and Progress Schedules, to reflect authorized changes and adjustments to contract price and time.
View the file
Other files
Show 40 more
Latest 50 of 171 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 26 00 – CONTRACT MODIFICATION PROCEDURES
Herbert, Rowland & Grubic, Inc. 01 26 00 - 1 000483.0450
SECTION 01 26 00 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes
1. Change procedures.
B. Related Sections
1. Document 00 60 00 – Project Forms
2. Document 00 63 13 – RFI Form
3. Document 00 63 49 – Work Change Directive Form
4. Document 00 63 63 – Change Order Form
5. Section 01 26 13 – Request for Interpretation
1.2 CHANGE PROCEDURES
A. Submittals: Submit name of individual who is authorized to receive change documents and is responsible for informing others in Contractor's employ or Subcontractors of changes to the Work.
B. Carefully study and compare Contract Documents before proceeding with fabrication and installation of Work. Promptly advise Engineer of any error, inconsistency, omission, or apparent discrepancy.
C. Requests for Interpretation (RFI) and Clarifications: Allot time in construction scheduling for liaison with Engineer; establish procedures for handling queries and clarifications.
1. Refer to Section 01 26 13 – Request for Interpretation.
2. Engineer may respond with a direct answer on the Request for Interpretation form, Field Order, or Proposal Request.
1.3 MINOR CHANGES IN THE WORK
A. Engineer will advise of minor changes in the Work not involving adjustment to Contract Price or Contract Time by issuing supplemental instructions on Field Order.
1.4 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Engineer may issue Proposal Request including a detailed description of proposed change with supplementary or revised Drawings and Specifications
1. Proposal Requests issued by Engineer are not instructions either to stop work in progress or to execute the proposed change.
2. Contractor will prepare and submit estimate within 10 days.
a. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.
Herbert, Rowland & Grubic, Inc. 01 26 00 - 2 000483.0450
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and equipment directly attributable to the change.
d. Include an updated Construction Schedule that indicates the effect of the change.
B. Contractor may propose changes by submitting a Change Proposal to Engineer, describing proposed change and its full effect on the Work. Include a statement describing reason for the change and the effect on Contract Price and Contract Time with full documentation and a statement describing effect on the Work by separate or other Contractors.
1. Notice: Comply with General Conditions where latent or changed conditions require modifications to the Contract.
2. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and equipment directly attributable to the change.
5. Include an updated Construction Schedule that indicates the effect of the change.
C. Document requested substitutions according to Section 01 25 00 – Substitution Procedures.
1.5 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Proposal Request, Engineer will issue a Change Order for execution by Owner and Contractor.
1. Change Order Forms: Document 00 63 63 – Change Order Form.
B. Stipulated Price Change Order: Based on Proposal Request and Contractor's price quotation or Contractor's request for Change Order as approved by Engineer.
C. Unit Price Change Order: For Contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of that which are not predetermined, execute Work under Work Directive Change.
D. Correlation of Contractor Submittals:
1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as separate line item and adjust Contract Price.
2. Promptly revise Progress Schedules to reflect change in Contract Time, adjust times for other items of Work affected by the change, and resubmit.
3. Promptly enter changes in Record Documents.
1.6 WORK CHANGE DIRECTIVE
A. Engineer may issue directive, on Work Change Directive signed by Owner, instructing Contractor to proceed with change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work and designate method of determining any change in Contract Price or Contract Time. Promptly execute change.
Herbert, Rowland & Grubic, Inc. 01 26 00 - 3 000483.0450
B. Maintain detailed records of Work done on time and material basis. Provide full information required for evaluation of proposed changes and to substantiate costs for changes in the Work.
PART 2 - PRODUCTS - Not Used
PART 3 - EXECUTION - Not Used
END OF SECTION 01 26 00