01 25 00 - Substitution Procedures.pdf

PDF 478 KB Posted

Attached to
West Pump Station Replacement Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

This is a substitution procedures specification document for the West Pump Station Replacement Project, a construction initiative by the Northwestern Chester County Municipal Authority in Pennsylvania. The specification establishes guidelines for product substitutions during the project, which includes construction of a new suction lift style pump station with building and site improvements, demolition of existing equipment, installation of sanitary sewer piping and force main piping, grinder pump and wet well installation, and general site improvements. The project is divided into three separate contracts: WPS-1 (General Construction), WPS-2 (Electrical Construction), and WPS-3 (Mechanical Construction), with bids due by Wednesday, May 20, 2026 at 10:00 AM local time. Contractors may request product substitutions only within 30 days after the Notice to Proceed date, and all substitution requests must be submitted in writing with complete supporting documentation for Engineer approval.

The specification requires that substitution requests demonstrate substantial advantages to the Owner in cost, time, energy conservation, or other considerations while accounting for additional responsibilities the Owner must assume, including Engineer compensation for redesign and evaluation services. Contractors must reimburse the Owner and Engineer for all costs associated with evaluating proposed substitutions and making any resulting changes to the Contract Documents. Substitution requests must include detailed documentation such as manufacturer information, point-by-point product comparisons, cost analyses, test data, references to similar installations, and certification of compliance with Contract Documents. The Engineer will return requests that do not satisfy specified conditions without action, except to document noncompliance. Additionally, substitutions cannot be considered if they are implied on shop drawings or product data submittals without separate written requests, or if acceptance would require revisions to the Contract Documents.

View the file

Other files

File Type Posted
40 05 53 - Identification For Process Piping.pdf PDF
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 25 00 – SUBSTITUTION PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 25 00 - 1 000483.0450

SECTION 01 25 00 – SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Quality assurance.

B. Product options.

C. Product substitution procedures.

1.2 QUALITY ASSURANCE

A. Contracts are based on products and standards established in Contract Documents without consideration of proposed substitutions.

B. Products specified define standard of quality, type, function, dimension, appearance, and performance required.

C. Substitution Proposals: Permitted for specified products except where specified otherwise. Do not substitute products unless substitution has been accepted and approved in writing by Owner.

1.3 PRODUCT OPTIONS

A. See Section 01 61 00 – Product Requirements.

1.4 PRODUCT SUBSTITUTION PROCEDURES

A. Engineer will consider requests for substitutions only within 30 days after date established in Notice to Proceed.

B. Substitutions may be considered when a product becomes unavailable through no fault of Contractor.

C. Costs:

1. Engineer’s Cost Reimbursement: Engineer will record costs in evaluating a substitute proposed or submitted by Contractor pursuant to this Section and the General Conditions. Whether or not Engineer approves a substitute item submitted by Contractor, Contractor shall reimburse Owner for the charges of Engineer for evaluating each such proposed substitute. Contractor shall also reimburse Owner for the charges of Engineer for making changes in the Contract Documents (or in the provisions of any other direct contract with Owner) resulting from the acceptance of each proposed substitute.

2. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or “or equal” at Contractor’s expense.

Herbert, Rowland & Grubic, Inc. 01 25 00 - 2 000483.0450

D. Conditions: Engineer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Engineer will return requests without action, except to record noncompliance with these requirements:

1. Request is submitted in accordance with this Section and the requirements of the

General Conditions.

2. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities include compensation to Engineer for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.

3. Requested substitution does not require extensive revisions to the Contract Documents.

4. Requested substitution is consistent with the Contract Documents and will produce indicated results.

5. Substitution request is fully documented and properly submitted.

6. Requested substitution will not adversely affect Contractor's Construction

Schedule.

7. Requested substitution has received necessary approvals of authorities having jurisdiction.

8. Requested substitution is compatible and coordinated with other portions of the

Work.

9. Requested substitution provides specified warranty.

10. If requested substitution involves other Contracts, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved. All costs of other contracts for substitution will be made by Contractor making request.

E. Document each request with complete data, substantiating compliance of proposed substitution with Contract Documents, including:

1. Manufacturer's name and address, product, trade name, model, or catalog number, performance and test data, and reference standards.

2. Itemized point-by-point comparison of proposed substitution with specified product, listing variations in quality, performance, and other pertinent characteristics.

3. Reference to Article and Paragraph numbers in Specification Section.

4. Cost data comparing proposed substitution with specified product and amount of net change to Contract Sum.

5. Changes required in other Work.

6. Availability of maintenance service and source of replacement parts as applicable.

7. Certified test data to show compliance with performance characteristics specified.

8. Samples when applicable or requested.

9. Other information as necessary to assist Engineer's evaluation.

10. List of similar installations for completed projects with project names and addresses and names and addresses of engineers and owners.

Herbert, Rowland & Grubic, Inc. 01 25 00 - 3 000483.0450

11. Certification that proposed substitution complies with requirements in the Contract Documents and is appropriate for applications indicated.

12. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

F. A request constitutes a representation that Contractor]:

1. Has investigated proposed product and determined that it meets or exceeds quality level of specified product.

2. Will provide same warranty for substitution as for specified product.

3. Will coordinate installation and make changes to other Work that may be required for the Work to be complete with no additional cost to Owner.

4. Waives claims for additional costs or time extension that may subsequently become apparent.

5. Will coordinate installation of the accepted substitute, making such changes as may be required for the Work to be complete in all respects.

6. Will reimburse Owner and Engineer for review or redesign services associated with reapproval by authorities having jurisdiction.

G. Substitutions will not be considered when they are indicated or implied on Shop Drawing or Product Data submittals without separate written request or when acceptance will require revision to Contract Documents.

1.5 INSTALLER SUBSTITUTION PROCEDURES

A. Document 00 21 13 – Instructions to Bidders specifies time restrictions for submitting requests for substitutions during Bidding period.

B. Document each request with:

1. Installer's qualifications.

2. Installer's experience in work similar to that specified.

3. Other information as necessary to assist Architect/Engineer's evaluation.

C. Substitution Submittal Procedure:

1. Submit electronic files to Project website of Request for Substitution for consideration. Limit each request to one proposed substitution.

2. Engineer will notify Contractor in writing of decision to accept or reject request.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

END OF SECTION 01 25 00