TGI_38K5216702_A01_c0v0.pdf

PDF 140 KB Posted

Attached to
USS RALPH JOHNSON DDG114 FY25 SRA 5C1 Bundle 2 (YOKOSUKA, JAPAN)
Solicitation number
N6264925RA025
Issued by

About this file

This is a Task Group Instruction (TGI) document for overhauling a watertight hatch (1-444-2) on the USS RALPH JOHNSON (DDG-114). The work involves removing and reinstalling the hatch panel, replacing gaskets and label plates, conducting surface preparation and painting, and performing operational and leak tests. The hatch is located on the Main Deck Weather at Frame 444 Port side, providing access to an Access Trunk (2-442-4-T) and Passage (2-442-2-L).

The work is scheduled to be performed between July 14, 2025, and November 26, 2025, with a total estimated cost of $3,278.15 and 233 man-hours. The TGI includes detailed material requirements for parts like machine screws, helical springs, shoulder pins, cotter pins, sleeve bushings, and bearings. Special requirements note that the work affects a fire zone boundary and requires fabrication/staging of a non-flammable closure. The document specifies quality assurance checkpoints, including chalk tests and air hose tests with zero allowable leakage, and requires coordination with various support services including crane operations, utilities, safety inspections, and gas-free inspections.

View the file

Other files

File Type Posted
2.03 Amendment 0003 25RA025.pdf PDF
2.03 Amendment 0002 25RA025.pdf PDF
2.03 Amendment 0001 25RA025.pdf PDF
TGI_38K5263408A01_c0v0.pdf PDF
TGI_38K5212351A01_c3v1.rev1.pdf PDF
2.02 Attachment V Contract Data Sheet 25RA025.pdf PDF
TGI_38K5259310A01_c0v0.pdf PDF
TGI_38K5212347A01_c0v0.rev1.pdf PDF
TGI_38K5212352A01_c0v0.rev1.pdf PDF
TGI_38K5212346A01_c0v0.rev1.pdf PDF
TGI_38K5212389A01_c0v0.pdf PDF
TGI_38K5213001A01_c1v1.pdf PDF
TGI_38K5212317_A01_c2v2.rev1.pdf PDF
TGI_38K5212314_A01_c0v0.rev1.pdf PDF
TGI_38K5212315_A01_c0v0.rev1.pdf PDF
TGI_38K5212382A01_c0v0.pdf PDF
TGI_38K5212365A01_c0v0.pdf PDF
TGI_38K5213102A01_c1v1.pdf PDF
TGI_38K5215401A01_c0v0.pdf PDF
TGI_38K5212329_A01_c1v1.rev1.pdf PDF
TGI_38K5212363T01_c0v0.pdf PDF
TGI_38K5212321A01_c2v0.rev1.pdf PDF
TGI_38K5212342A01_c0v0.rev1.pdf PDF
TGI_38K5212364A01_c0v0.pdf PDF
TGI_38K5212325_A01_c0v0.rev1.pdf PDF
TGI_38K5212377A01_c1v1.pdf PDF
TGI_38K5212312_A01_c0v0.rev1.pdf PDF
TGI_38K5212340A01_c0v0.rev1.pdf PDF
TGI_38K5212313_A01_c0v1.rev1.pdf PDF
TGI_38K5212323_A01_c0v0.rev1.pdf PDF
TGI_38K5212309_A01_c0v0.rev1.pdf PDF
TGI_38K5212392A01_c1v1.pdf PDF
2.02 Attachment IV N6264925RA025 Request for Information Form.doc DOC document
TGI_38K5216704_A01_c0v0.pdf PDF
TGI_38K5212356A01_c0v0.rev1.pdf PDF
TGI_38K5212391A01_c0v0.pdf PDF
2.02 Attachment II Price Proposal Form N6264925RA025.xlsx XLSX spreadsheet
TGI_38K5212336_A01_c0v0.pdf PDF
TGI_38K5212320_A01_c1v1.rev1.pdf PDF
TGI_38K5212328_A01_c0v0.rev1.pdf PDF
TGI_38K5212319_A01_c2v1.rev1.pdf PDF
TGI_38K5216705_A01_c0v1.pdf PDF
TGI_38K5212390A01_c0v0.pdf PDF
TGI_38K5212330_A01_c0v0.rev1.pdf PDF
TGI_38K5212327_A01_c1v2.rev1.pdf PDF
TGI_38K5212355A01_c0v0.rev1.pdf PDF
2.02 Attachment III N6264925RA025 Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
TGI_38K5212348A01_c0v0.pdf PDF
TGI_38K5216703_A01_c0v0.pdf PDF
TGI_38K5212311A01_c1v0.rev1.pdf PDF
Show 40 more

Latest 50 of 73 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

FOUO: Public availability to be determined under 5 USC 552

TASK GROUP INSTRUCTION

AIM REV 20.11.4.0 (OCTOBER 2020)

TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:

NO.: HATCH 1-444-2 AY A 0 0

SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:

DDG-114 USS RALPH JOHNSON K52

CU PHASE TITLE:

*F/O - OVERHAUL WATERTIGHT HATCH 1-444-2

PREPARING ACTIVITY:

PREPARED BY: CODE PHONE DATE

TSUBASA KOSUGE 231A 315-243-4371 06-NOV-2024

APPROVED BY: CODE PHONE DATE

YUUJI NAKMARA 231A 315-243-6041 06-NOV-2024

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

REASON FOR WORK/NEED FOR CHANGE:

CHANGE INSTRUCTIONS:

SPECIAL REQUIREMENTS:

This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.

WORK CERTIFICATION SIGNATURES

COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

ACCEPTANCE OF COMPLETED WORK

PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:

REQUIRED:☐YES ☒NO

RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

TGI NO.: HATCH 1-444-2 AY A 0

FOUO

SHIP: DDG-114 CHG/VER: 0/0

LIST OF EFFECTIVE PAGES

SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.

1-5 J1-2 M1-2

1. SCOPE/PURPOSE

1.1 Title: Watertight Hatch 1-444-2; overhaul

1.2 Location of Work:

1.2.1 Main Deck Weather, Frame 444, Port

1.2.2 Access Trunk (2-442-4-T)

1.2.3 Passage (2-442-2-L)

1.3 Identification:

1.3.1 Quantity (One Lot), Longitudinal No.7(P) in 2-442-4-T, Frames between 442 and 444 Port

Base Material: HTS, MIL-S-22698 GR-AH36, 8 Inches x 5-1/2 Inches x 13 LBs T Remarks: See Sheets 3-12 and 4-12 of 2.3 for details

1.3.2 Quantity (One EA), Hatch, Watertight

Hatch No. : 1-444-2 Size: 30 Inches x x30 Inches Material: Steel Type: Raised Low Profile Quick Acting, 6 Dogs, Spring Balanced

1.3.3 Quantity (4 EA), Label Plate, Watertight Hatch

1.3.3.1 Quantity (One EA), Label Plate, Exterior

Material: CRES, Type-II of 2.8 Inscription: 1st. Line: 1-444-2

2nd. Line: ACCESS TRUNK 3rd. Line: 1-442-4-T

1.3.3.2 Quantity (One EA), Label Plate, Damage Control Closure Classification, Exterior

Material: CRES, Type-II of 2.8 Remarks: Figure-D of 2.8

1.3.3.3 Quantity (One EA), Label Plate, Interior

Material: Aluminum Alloy, Type-I of 2.8 Inscription: 1st. Line: 1-444-2

2nd. Line: WEATHER

1.3.3.4 Quantity (One EA), Label Plate, Damage Control Closure Classification, Interior

FOUO

SHIP: DDG-114 CHG/VER: 0/0

Material: Aluminum Alloy, Type-I of 2.8 Remarks: Figure-D of 2.8

1.4 Security Classification: None.

1.5 Initial Condition:

1.5.1 Potential Asbestos Hazard.

1.6 Contractor work start date:

1.7 Contractor work completion date:

2. REFERENCES:

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

1 NSI FY-25 NAVSEA Standard Items - 1 N 2 LI FY-25 Local Standard Items - ORG N

3 DWG 100-

7063224

UNIT STRUCTURAL ARR DWG

ASSY UNIT 3440

- Y 3- 12, 4-

4 DWG 167-

7062377

HATCH AND SCUTTLE LIST SHIP

WIDE

- Y 7F

5 DWG 8100-

1252-0235

Hatches Structural (Steel) Arrangement

K N

6 DWG 8100-

1252-0236

Hatches, Structural (Steel) Assemblies & Details

AH N

7 TM

SYSTEMS &

SPECIFICAT

IONS

SSPC Painting Manual Volume 2 - N

8 PDD 602-

ELM-150531

SRF-JRMC STD ELM LABEL

PLATE FOR CLOSURE

A Y AL

L

3. APPENDICES:

3.1. Appendix “J” TGI Job Summary Information Sheet

3.2. Appendix "M" TGI Material List

3.3. Appendix “D” Deficiency Form

4. GENERAL REQUIREMENTS:

4.1 Not Applicable.

5. PROCEDURE:

5.1 Drill maximum 3/4 inch or greater minimum 5/8 inch diameter hole on longitudinal listed in 1.3.1 for removal of hinge shaft for hatch panel, using for 2.3 for guidance.

5.1.1 Template location details from onboard ship for removal.

5.2 Remove existing hatch panel of each hatch listed in 1.3.2, using 2.4 through 2.6 for guidance.

5.2.1 Disassemble dog assembly.

Masato.Endo.ja Typewritten Text

14 JUL 2025

Masato.Endo.ja Typewritten Text

26 NOV 2025

Masato.Endo.ja Cross-Out

Masato.Endo.ja Typewritten Text

1/11/2025 C-1209 M. ENDO 11030028

FOUO

SHIP: DDG-114 CHG/VER: 0/0

5.2.1.1 Clean each part free of dirt, grease and foreign matter.

5.2.2 Remove existing gasket and label plate(s) of each hatch.

5.3 Accomplish the requirements of 009-32 of 2.1, including Table 2, Line(s) 9, for exterior surfaces and Table 3, Line(s) 25, for interior surfaces of hatch panel of each hatch listed in 1.3.2.

5.3.1 Near-white blast clean for each hatch panel. Accomplish each requirement of Surface Preparation Specification SSPC-SP 10 of 2.7.

5.4 Prepare and align hatch panel of each hatch listed in 1.3.2 for reinstallation, using 2.4 through 2.6 for guidance.

5.4.1 Fabricate and install new gasket conforming to A-A-59588 Class 3B Grade 30.

5.5 Reinstall hatch panel of each hatch listed in 1.3.2, using 2.4 through 2.6 for guidance.

5.5.1 Reassemble dog assembly.

5.5.1.1 Lubricate each dogging mechanisms.

5.5.2 Adjust each dogging mechanism for unobstructed operation and to obtain 100 percent centered contact with the imprint of chalk in the center three-fifths of the gasket.

5.6 Accomplish the requirements of 009-25 of 2.1 for a chalk test of each hatch listed in 1.3.2.

5.7 Accomplish the requirements of 009-25 of 2.1 for a local air hose test of hatch panel gasket and knife edge mating area of each hatch listed in 1.3.2. Allowable leakage: None.

5.8 Accomplish an operational test of each hatch listed in 1.3.2 to assure unobstructed operation. Allowable sticking or binding: None.

(V)(G) “OPERATION TEST”

5.9 Fabricate and install new each label plate listed in 1.3.3 in accordance with 2.8.

5.9.1 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) D, Lines One through 7.

5.10 Accomplish build up weld of remaining hole on each existing longitudinal listed in 1.3.1.

5.10.1 Accomplish the requirement of 009-12 of 2.1, including Table 2, Column(s) A, Lines One through 7.

5.10.2 Accomplish the requirements of 009-25 of 2.1 for a local air hose test of new weld of existing longitudinal listed in 1.3.1. Allowable leakage: None.

5.11 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.

5.12 Notes:

5.12.1 Planner: Code 231A T. Kosuge, 243-4371

Engineer: Code 250 M. Kunugi, 243-7885

5.12.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

5.12.3 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard

FOUO

SHIP: DDG-114 CHG/VER: 0/0

fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.

5.12.4 JCN ER09-L025 is related to this TGI.

5.13 Government Furnished Material (GFM):

5.13.1 SRF-JRMC will provide GFM listed in Appendix “M”.

5.14 SRF-JRMC will provide the following service work: (TGI No. 38K5216702S02).

5.14.1 [C740] Crane and crane rigging service.

5.14.2 [X99E] Utility service, electrical.

5.14.3 [X99M] Utilities service, including low pressure air supply, water supply, and steam supply.

5.14.4 [C106.1] Safety inspection for SRF-JRMC employees.

5.14.5 [C106.2] Gas free inspection for SRF-JRMC employees.

5.14.6 [C133] QA Inspection for (G) symbol(s).

FOUO

J-1

SHIP: DDG-114 CHG/VER: 0/0

APPENDIX "J"

TGI JOB SUMMARY INFORMATION SHEET

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

HATCH 1-444-2 AY A 0 0

CU PHASE TITLE:

*F/O - OVERHAUL WATERTIGHT HATCH 1-444-2

PRIMARY COMPONENT:

COMPONENT UNIT LIST (FOR ASSEMBLIES):

HATCH 1-444-2 HA CMPT 2-442-2-L MS TRUNK 2-442-4-T MS

ATTACHMENT LIST:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA ,TAKEHIDE

JO: KO: TOTAL MAN HRS: TOTAL MAT’L COST TOTAL DURATION: PLANNING ACCEPTANCE:

38K5216702 A01 233 $3,278.15 1

CU PHASE DESCRIPTION:

The purpose of this TGI is to overhaul watertight hatch 1-444-2.

Location of Work:

Main Deck Weather, Frame 444, Port Access Trunk (2-442-4-T) Passage (2-442-2-L)

TASK NAME

SHOP TSD/WC TS CREW# MHRS

HIGH RAD

HOURS

RC

GRID#

FOUO

J-2

SHIP: DDG-114 CHG/VER: 0/0

TASK NAME

SHOP TSD/WC TS CREW# MHRS

HIGH RAD

HOURS

RC

GRID#

FOUO

M-1

SHIP: DDG-114 CHG/VER: 0/0

APPENDIX “M”

TGI MATERIAL LIST

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

HATCH 1-444-2 AY A 0 0

CU PHASE TITLE:

*F/O - OVERHAUL WATERTIGHT HATCH 1-444-2

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV

JOB ORDER: KEY OP:

38K5216702 A01

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

001 M SCREW,MACHINE, ORGI:

C231A T. KOSUGE

243-4371

ORDERED FOR KTR

9B 5305 016133097 NA 4 N 43115013 6/EA

002 M SPRING, HELICAIL, ORIG:

C231A T. KOSUGE

243-4371

ORDERED FOR KTR

9B 5360 014209907 NA 4 N 43115014 6/EA

003 M PIN,SHOULDER,HEADLE,

ORIG: C231A T. KOSUGE

243-4371

ORDERED FOR KTR

9B 5315 014200098 NA 4 N 43115018 8/EA

004 M PIN,COTTER, ORIG: C231A T.

KOSUGE

243-4371

ORDERED FOR KTR

9B 5315 014198257 NA 4 N 43115024 3/EA

005 M BUSHING,SLEEVE, ORIG:

C231A T. KOSUGE

243-4371

ORDERED FOR KTR

9B 3120 010892602 NA 4 N 43115026 1/EA

006 M BEARING,SLEEVE, ORIG:

C231A T. KOSUGE

243-4371

ORDERED FOR KTR

9B 3120 009577910 NA 4 N 43115035 1/EA

NOTES:

FOUO

M-2

SHIP: DDG-114 CHG/VER: 0/0

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

007 M BOLT, MACHINE, ORIG: C231A

T. KOSUGE

243-4371

ORDERED FOR KTR

BOLT, MACHINE, 1/2"-13UNC-

2AX1-1/4"L, CRES, RIGHT

HAND

LL4946519 NA 4 N 2/EA

008 M NUT, HEXHEAD, ORIG: C231A

T. KOSUGE

243-4371

ORDERED FOR KTR

9B 5310 015098658 NA 4 N 43115037 2/EA

009 M RUBBER , ORIG: C231A T.

KOSUGE

243-4371

ORDERED FOR KTR

9B 5330 013717183 NA 4 N 43115039 20/FT

010 M INSULATI, ORGI: C231A T.

KOSUGE

243-4371

ORDERED FOR KTR

9Q 5640 013713263 NA 4 N 43115041 1/SH

011 M INSULATI, ORIG: C231A T.

KOSUGE

243-4371

ORDERED FOR KTR

9Q 5640 013713262 NA 4 N 43115043 1/SH

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR APPENDIX "D"

DEFICIENCY FORM

☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One)

2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

DDG-114 HATCH 1-444-2 AY A 0

4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:

38K5216702 A01

7. DESCRIPTION:

8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

9. CORRECTIVE ACTION:

10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

FOR NON-NUCLEAR USE ONLY

11. RFD/RFW REQ’D ☐ LAR REQ'D ☐

ILS MOD REQ’D ☐

SRD/PLAN REV REQ'D ☐

DWG NO.: _____________________ S/A NO.: ___________________

12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:

SATISFACTORY:

13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

YES ☐ NO ☐

14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE:

15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

_________:YES ☐ NO ☐

16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE (DR ONLY)

DL’s ISSUED

(DR ONLY)

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

DDG-114 HATCH 1-444-2 AY A 0

File details come from the government source that posted it. Updated .