TGI_38K5212336_A01_c0v0.pdf
PDF 128 KB Posted
- Solicitation number
- N6264925RA025
About this file
This is a Task Group Instruction (TGI) document detailing maintenance work requirements for fuel tanks on the USS RALPH JOHNSON (DDG-114) to be performed in Yokosuka, Japan. The work involves opening and cleaning two Fuel Tank Group-4 tanks (4-272-2-F with 21,685 gallon capacity and 5-264-2-F with 13,000 gallon capacity), including associated manhole cover plates and bolting rings. The work requires Level III cleanliness standards and includes painting/coating requirements for tank surfaces and hardware.
The work is part of a larger ship repair availability package scheduled for July 14, 2025 through February 23, 2026. SRF-JRMC will provide support services including crane operations, utility services, safety inspections, gas free inspections, and QA inspections. The work falls under solicitation N6264925RA025, which is restricted to contractors authorized to operate in Japan. Contractor proposals are due by March 11, 2025 at 10:00 AM Japan Standard Time.
View the file
Other files
Show 40 more
Latest 50 of 73 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: 4-272-2-F&5-264-2-F AY A 0 0
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
DDG-114 USS RALPH JOHNSON K52
CU PHASE TITLE:
F/O - OPEN AND CLEAN FUEL TANK GP-4 (4-272-2-F) AND FUEL TANK GP-4 (5-264-2-F)
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
YUUTA KISHI 231A 315-243-6411 12-SEP-2024
APPROVED BY: CODE PHONE DATE
YUUJI NAKAMURA 231A 315-243-6041 12-SEP-2024
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
CHANGE INSTRUCTIONS:
SPECIAL REQUIREMENTS:
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: 4-272-2-F&5-264-2-F AY A 0
FOUO
SHIP: DDG-114 CHG/VER: 0/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-4 J-1 M-1
1. SCOPE/PURPOSE
1.1 Title: Fuel Tank Group-4 (4-272-2-F) and Fuel Tank Group-4 (5-264-2-F); open and clean
1.2 Location of Work:
1.2.1 Fuel Tank Group-4 (4-272-2-F)
1.2.2 Fuel Tank Group-4 (5-264-2-F)
1.2.3 Engine Room No. One (4-174-0-E)
1.2.4 Auxiliary Machinery Room No. 2 (4-220-0-E)
1.2.5 Engine Room No. 2 (4-254-0-E)
1.3 Identification:
1.3.1 Quantity (2 EA), Fuel Tank
1.3.1.1 Quantity (One EA), Fuel Tank Group-4
Tank No.: 4-272-2-F Capacity: 21,685 Gallons
1.3.1.2 Quantity (One EA), Fuel Tank Group-4
Tank No.: 5-264-2-F Capacity: 13,000 Gallons
1.3.2 Quantity (One Lot/ 8 Tanks), Fuel Tank Group-3 and Group-4 Total Capacity: 117,151 Gallons Required amount of water to dewater: 104,898 Gallons
1.3.2.1 Fuel Receiving Tank Group-3
Tank No.: 4-174-1-F Capacity: 23,007 Gallons
1.3.2.2 Fuel Tank Group-3
Tank No.: 5-220-3-F Capacity: 17,120 Gallons
1.3.2.3 Fuel Tank Group-3
Tank No.: 5-254-3-F Capacity: 20,698 Gallons
1.3.2.4 Fuel Expansion Seawater Overflow Tank Group-3
Tank No.: 5-254-1-F Capacity: 2,096 Gallons
FOUO
SHIP: DDG-114 CHG/VER: 0/0
1.3.2.5 Fuel Tank Group-4
Tank No.: 5-220-4-F Capacity: 17,328 Gallons
1.3.2.6 Fuel Tank Group-4
Tank No.: 4-272-2-F Capacity: 21,685 Gallons
1.3.2.7 Fuel Tank Group-4
Tank No.: 5-264-2-F Capacity: 13,000 Gallons
1.3.2.8 Fuel Expansion Seawater Overflow Tank Group-4
Tank No.: 5-254-2-F Capacity: 2,217 Gallons
1.3.3 Quantity (2 EA), Manhole Cover Plate for 4-272-2-F
Manhole No.: 3 1/2-279-2 and 3 1/2-294-2 Size: 15 Inches x 23 Inches Material: Steel
1.3.4 Quantity (2 EA), Manhole Cover Plate for 5-264-2-F
Manhole No.: 4-273-2 and 4-290-2 Size: 15 Inches x 23 Inches Material: Steel
1.3.5 Quantity (2 EA), Bolting Ring for Manhole Cover Plate for 4-272-2-F Manhole No.: 3 1/2-279-2 and 3 1/2-294-2 Material: Steel
1.3.6 Quantity (2 EA), Bolting Ring for Manhole Cover Plate for 5-264-2-F Manhole No.: 4-273-2 and 4-290-2 Material: Steel
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor work start date:
1.7 Contractor work completion date:
2. REFERENCES:
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-25 NAVSEA Standard Items - 1 N 2 LI FY-25 Local Standard Items - ORG N
3 TM S9086-
CJ-STM-
010/CH--075
Fasteners 7 N
3. APPENDICES:
Masato.Endo.ja Typewritten Text
14 JUL 2025
Masato.Endo.ja Typewritten Text
21 AUG 2025
FOUO
SHIP: DDG-114 CHG/VER: 0/0
3.1. Appendix “J” TGI Job Summary Information Sheet
3.2. Appendix "M" TGI Material List
3.3. Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1. Not Applicable.
5. PROCEDURE:
5.1 Accomplish the requirements of 099-902YO of 2.2 for each tank listed in 1.3.1.
5.1.1 Accomplish the requirements of 099-909YO of 2.2 for each tank listed in 1.3.2.
5.1.1.1 Accomplish the requirements of 009-09 of 2.1.
5.1.2 Accomplish the requirements of 009-107 of 2.1 for each tank listed in 1.3.1.
5.1.2.1 Ensure General Cleaning must be Level III.
5.1.3 Install each manhole cover for each tank listed in 1.3.1 in accordance with figures 075-4-1 of 2.3.
5.2 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 11, for tank side surface, and Table 3, Line(s) 12, for machinery side surface of each cover plate listed in 1.3.3 and 1.3.4.
5.3 Accomplish the requirements of 009-32 of 2.1 for each bolting ring listed in 1.3.5 and 1.3.6.
5.4 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
5.5 Notes:
5.5.1 Planner: Code 231A Y. Kishi, 243-6411
5.5.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
5.5.3 This TGI meets the intent of DDG CSWT File No. 123-133.
5.5.4 JCNs ER01-ZA92 and EB14-ZAN9 are related to this TGI.
5.6 Government Furnished Material (GFM): None.
5.7 SRF-JRMC will provide the following service work: (TGI No. 38K5212336S02)
5.7.1 [C740] Crane and crane rigging service.
5.7.2 [X99E] Utility service, electrical.
5.7.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
5.7.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.7.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.7.6 [C133] QA inspection for (G) symbol(s).
Masato.Endo.ja Cross-Out
Masato.Endo.ja Typewritten Text
12/17/2024 C-1209 M. ENDO 11030028
FOUO
J-1
SHIP: DDG-114 CHG/VER: 0/0
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
4-272-2-F&5-264-2-F AY A 0 0
CU PHASE TITLE:
F/O - OPEN AND CLEAN FUEL TANK GP-4 (4-272-2-F) AND FUEL TANK GP-4 (5-264-2-F)
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
FOCT 4-272-2-F TKMANHOLE 3.5-279-2 HA MANHOLE 3.5-294-2 HA FOCT 5-264-2-F TK
MANHOLE 4-273-2 HA MANHOLE 4-290-2 HA FOCT 4-174-1-F TKFOCT 5-220-3-F TK
FOCT 5-254-3-F TKFOCT 5-254-1-F TKFOCT 5-220-4-F TKFOCT 5-254-2-F TK
ATTACHMENT LIST:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA ,TAKEHIDE
JO: KO: TOTAL MAN HRS: TOTAL MAT’L COST TOTAL DURATION: PLANNING ACCEPTANCE:
38K5212336 A01 995 $0.00 1
CU PHASE DESCRIPTION:
The purpose of this TGI is to open and clean Fuel Tank Group-4 (4-272-2-F) and Fuel Tank Group-4 (5-264-2-F)
Location of Work:
Fuel Tank Group-4 (4-272-2-F) Fuel Tank Group-4 (5-264-2-F) Engine Room No. One (4-174-0-E) Auxiliary Machinery Room No. 2 (4-220-0-E) Engine Room No. 2 (4-254-0-E)
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
FOUO
M-1
SHIP: DDG-114 CHG/VER: 0/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
4-272-2-F&5-264-2-F AY A 0 0
CU PHASE TITLE:
F/O - OPEN AND CLEAN FUEL TANK GP-4 (4-272-2-F) AND FUEL TANK GP-4 (5-264-2-F)
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
JOB ORDER: KEY OP:
38K5212336 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
NOTES:
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-114 4-272-2-F&5-264-2-F AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
38K5212336 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-114 4-272-2-F&5-264-2-F AY A 0
File details come from the government source that posted it. Updated .