This is a Task Group Instruction (TGI) document detailing work requirements for cleaning, assessing, repairing, and preserving an oily waste holding tank (5-220-2-F) aboard the USS RALPH JOHNSON (DDG-114) in Yokosuka, Japan. The work scope includes cleaning to Level III cleanliness, conducting structural and coating assessments, repairing approximately 11 square feet of plate defects in the tank bottom, preserving 52 square feet of defective painted surfaces, and addressing manhole cover plates and bolting rings.

The work is scheduled to begin July 14, 2025, and complete by December 11, 2025. The TGI specifies detailed procedures for welding repairs, surface preparation, and preservation requirements. Government-furnished crane services, utilities, safety inspections, and quality assurance support will be provided by SRF-JRMC. The work is part of a larger ship repair availability package being solicited under contract N6264925RA025, with proposals due March 11, 2025. The total estimated labor hours for this specific tank work is 388 hours.

View the file

Other files

File Type Posted
2.03 Amendment 0003 25RA025.pdf PDF
2.03 Amendment 0002 25RA025.pdf PDF
2.03 Amendment 0001 25RA025.pdf PDF
TGI_38K5263408A01_c0v0.pdf PDF
TGI_38K5212351A01_c3v1.rev1.pdf PDF
2.02 Attachment V Contract Data Sheet 25RA025.pdf PDF
TGI_38K5259310A01_c0v0.pdf PDF
TGI_38K5212347A01_c0v0.rev1.pdf PDF
TGI_38K5212352A01_c0v0.rev1.pdf PDF
TGI_38K5212346A01_c0v0.rev1.pdf PDF
TGI_38K5212389A01_c0v0.pdf PDF
TGI_38K5213001A01_c1v1.pdf PDF
TGI_38K5212317_A01_c2v2.rev1.pdf PDF
TGI_38K5212314_A01_c0v0.rev1.pdf PDF
TGI_38K5212315_A01_c0v0.rev1.pdf PDF
TGI_38K5212382A01_c0v0.pdf PDF
TGI_38K5212365A01_c0v0.pdf PDF
TGI_38K5213102A01_c1v1.pdf PDF
TGI_38K5215401A01_c0v0.pdf PDF
TGI_38K5212329_A01_c1v1.rev1.pdf PDF
TGI_38K5212363T01_c0v0.pdf PDF
TGI_38K5212321A01_c2v0.rev1.pdf PDF
TGI_38K5212342A01_c0v0.rev1.pdf PDF
TGI_38K5212364A01_c0v0.pdf PDF
TGI_38K5216702_A01_c0v0.pdf PDF
TGI_38K5212325_A01_c0v0.rev1.pdf PDF
TGI_38K5212377A01_c1v1.pdf PDF
TGI_38K5212312_A01_c0v0.rev1.pdf PDF
TGI_38K5212340A01_c0v0.rev1.pdf PDF
TGI_38K5212313_A01_c0v1.rev1.pdf PDF
TGI_38K5212323_A01_c0v0.rev1.pdf PDF
TGI_38K5212309_A01_c0v0.rev1.pdf PDF
TGI_38K5212392A01_c1v1.pdf PDF
2.02 Attachment IV N6264925RA025 Request for Information Form.doc DOC document
TGI_38K5216704_A01_c0v0.pdf PDF
TGI_38K5212356A01_c0v0.rev1.pdf PDF
TGI_38K5212391A01_c0v0.pdf PDF
2.02 Attachment II Price Proposal Form N6264925RA025.xlsx XLSX spreadsheet
TGI_38K5212336_A01_c0v0.pdf PDF
TGI_38K5212320_A01_c1v1.rev1.pdf PDF
TGI_38K5212328_A01_c0v0.rev1.pdf PDF
TGI_38K5212319_A01_c2v1.rev1.pdf PDF
TGI_38K5216705_A01_c0v1.pdf PDF
TGI_38K5212390A01_c0v0.pdf PDF
TGI_38K5212330_A01_c0v0.rev1.pdf PDF
TGI_38K5212355A01_c0v0.rev1.pdf PDF
2.02 Attachment III N6264925RA025 Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
TGI_38K5212348A01_c0v0.pdf PDF
TGI_38K5216703_A01_c0v0.pdf PDF
TGI_38K5212311A01_c1v0.rev1.pdf PDF
Show 40 more

Latest 50 of 73 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

FOUO: Public availability to be determined under 5 USC 552

TASK GROUP INSTRUCTION

AIM REV 20.11.4.0 (OCTOBER 2020)

TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:

NO.: WASTE TK 5-220-2-F AY A 0 1

SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:

DDG-114 USS RALPH JOHNSON K52

CU PHASE TITLE:

F/O - CLEAN, ASSESS, REPAIR, AND PRESERVE OILY WASTE HOLDING TANK (5-220-2-F)

PREPARING ACTIVITY:

PREPARED BY: CODE PHONE DATE

DAISUKE TAMURA 231A 315-243-9526 21-SEP-2024

APPROVED BY: CODE PHONE DATE

NAKAMURA YUUJI 231A 315-243-6041 21-SEP-2024

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

REASON FOR WORK/NEED FOR CHANGE:

Paragraph 5.2.3 was unrequired.

CHANGE INSTRUCTIONS:

CH-1: Delete paragraph 5.2.3. (10/15/2024)

SPECIAL REQUIREMENTS:

SURFMEPP

CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III.

WORK CERTIFICATION SIGNATURES

COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

ACCEPTANCE OF COMPLETED WORK

PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:

REQUIRED:☐YES ☒NO

RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

TGI NO.: WASTE TK 5-220-2-F AY A 0

FOUO

SHIP: DDG-114 CHG/VER: 1/2

LIST OF EFFECTIVE PAGES

SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.

1-5 J-1 M-1

1. SCOPE/PURPOSE

1.1 Title: Oily Waste Holding Tank (5-220-2-F); clean, assess, repair, and preserve

1.2 Location of Work:

1.2.1 Oily Waste Holding Tank (5-220-2-F)

1.2.2 Auxiliary Machinery Room No. 2 (4-220-0-E)

1.3 Identification:

1.3.1 Quantity (One EA), Oily Waste Holding Tank

Tank No. 5-220-2-F Capacity: 2,868 Gallons

1.3.2 Quantity (2 EA), Manhole Cover Plate and Air Vent Hose Connection (AVHC) Cover Plate for 5-220-2-F

Manhole No(s).: 4-225-2 Size: 15 Inches x 23 Inches AVHC No(s).: 4-222-2 Size: 10 Inches Diameter Material: Steel

1.3.3 Quantity (2 EA), Bolting Ring for Manhole Cover Plate and AVHC Cover Plate for 5-220-2-F

Manhole No(s).: 4-225-2 AVHC No(s).: 4-222-2 Material: Steel

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor work start date:

1.7 Contractor work completion date:

2. REFERENCES:

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

1 NSI FY-25 NAVSEA Standard Items - 1 N 2 LI FY-25 Local Standard Items - ORG N

Masato.Endo.ja Typewritten Text

14 JUL 2025

Masato.Endo.ja Typewritten Text

11 DEC 2025

FOUO

SHIP: DDG-114 CHG/VER: 1/2

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

3 TM T-9630-

AB-MMD-

Corrosion Control Assessment and Maintenance Manual (CCAMM)

- 3 N

4 TM NAVSEA

4790/14

Tank and Void Structural and Coating Condition Survey (MRC G1N5)

- N

5 DWG 633-

7284201

OILY WASTE TANK ZINC

INSTLLATION & ML

A Y 12, 17, 6 DWG 100-

7060394

UNIT STRL ARR DWG ASSY UNIT

C Y SE

E N

OT

E

7 TM S9086-

CJ-STM-

010/CH-075

Fasteners 7 N

3. APPENDICES:

3.1 Appendix “J” TGI Job Summary Information Sheet

3.2 Appendix “M” TGI Material List

3.3 Appendix “D” Deficiency Form

4. GENERAL REQUIREMENTS:

4.1 Not Applicable.

5. PROCEDURE:

5.1 Accomplish the requirements of 099-902YO of 2.2 for each tank listed in 1.3.1.

5.1.1 Accomplish an assessment of each tank listed in 1.3.1 for existing preservation coating, structural integrity, deterioration, pitting, cracks, and areas of damage or distortion, including sounding tubes, tank/void vents, overflows, piping and associated material, structural members, ladders, anodes, desiccant, tank level indicator (TLI), radar TLI, and their electric cables, stud, and tank top cable penetration, and manhole covers in accordance with 2.3 and 2.4, using 2.5 and 2.6 for guidance. Document the assessment on 2.4.

(I) "CCIMS ASSESSMENT"

5.1.1.1 Mark each corroded, damaged and/or deteriorated coating area in each tank.

5.1.1.2 Submit one legible copy, in hard copy or approved transferrable media, of completed assessment form 2.4 to the SUPERVISOR.

5.1.2 Accomplish the requirements of 009-107 of 2.1.

5.1.2.1 Ensure General Cleaning must be Level III.

5.1.3 Install each manhole cover for each tank listed in 1.3.1 in accordance with Figure 075-4-1 of 2.7.

5.2 Repair each tank listed in 1.3.1, based on 5.1.1.2 as designated by the SUPERVISOR, using 2.5 and 2.6 for guidance. See 5.7.5 and 5.7.6.

5.2.1 Base metal weld buildup a total of 11 square inches of each plate defect in the tank bottom.

Masato.Endo.ja Cross-Out

Masato.Endo.ja Typewritten Text

1/14/2025 C-1209 M. ENDO 11030028

FOUO

SHIP: DDG-114 CHG/VER: 1/2

5.2.1.1 For bidding purposes the base metal weld buildup must be one quarter inch thick.

5.2.1.2 Surface must be ground to sound metal prior to base metal weld buildup.

5.2.1.3 Fill each local pit and groove with weld material prior to application of each principal buildup layer.

5.2.1.4 Grind each surface of completed base metal weld buildup smooth if greater than 1/8 inch above plate surface.

5.2.2 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) A Lines One through 7.

5.2.2.1 Accomplish nondestructive testing in accordance with Line 11.

5.3 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 11, for tank side surface, and Table 3, Line(s) 12, for machinery space side surface of each cover plate listed in 1.3.2.

5.4 Accomplish the requirements of 009-32 of 2.1 for each bolting ring listed in 1.3.3.

5.5 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 11, for a total of 52 square feet of defective painted surfaces, for each tank listed in 1.3.1, as designated by the SUPERVISOR.

5.5.1 The preservation area must not exceed 10 square feet per one area.

5.6 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.

5.7 Notes:

5.7.1 Planner: Code 231A D. Tamura, 243-9526

5.7.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5149-0598

5.7.3 2.4 is available on P:\C200\C225\Enclosures\C231\Tank and Void Structural and Coating Condition Survey

(MRC G1N5).

5.7.4 This TGI meets the intent of DDG CSWT File Nos. 123-127, 123-129, and 123-133.

5.7.5 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.

5.7.6 Materials for structure members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.

5.7.7 WPC will copy the following pages in reference.

REF. 2.6: Pages 3, 4, 4A, 4B, 5-9, and 9-5.

5.7.8 JCNs EB14-ZAI9, EB14-ZAK1, EB14-ZAL3, and EB14-ZAM4 are related to this TGI.

5.8 Government Furnished Material (GFM): None.

5.9 SRF-JRMC will provide the following service work: (TGI No. 38K5212327S02)

5.9.1 [C740] Crane and crane rigging service.

FOUO

SHIP: DDG-114 CHG/VER: 1/2

5.9.2 [X99E] Utility service, electrical.

5.9.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

5.9.4 [C106.1] Safety inspection for SRF-JRMC employees.

5.9.5 [C106.2] Gas free inspection for SRF-JRMC employees.

5.9.6 [C133] QA inspection for (G) symbol(s) and Surface Corrosion Control Information Management System (CCIMS) entry.

5.9.7 [C135] QA inspection for (G) symbol(s).

5.9.8 [C250] Technical support and process of the tank/void assessment results.

FOUO

J-1

SHIP: DDG-114 CHG/VER: 1/2

APPENDIX "J"

TGI JOB SUMMARY INFORMATION SHEET

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

WASTE TK 5-220-2-F AY A 0 2

CU PHASE TITLE:

F/O - CLEAN, ASSESS, REPAIR, AND PRESERVE OILY WASTE HOLDING TANK (5-220-2-F)

PRIMARY COMPONENT:

COMPONENT UNIT LIST (FOR ASSEMBLIES):

AVHC CV 4-222-2 HA MANHOLE 4-225-2 HA OWHT 5-220-2-F TK

ATTACHMENT LIST:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE

JO: KO: TOTAL MAN HRS: TOTAL MAT’L COST TOTAL DURATION: PLANNING ACCEPTANCE:

38K5212327 A01 388 $0.00 0

CU PHASE DESCRIPTION:

The purpose of this TGI is to clean, assess, repair, and preserve oily waste holding tank, 5-220-2-F.

Location of Work:

Oily Waste Holding Tank (5-220-2-F) Auxiliary Machinery Room No. 2 (4-220-0-E)

TASK NAME

SHOP TSD/WC TS CREW# MHRS

HIGH RAD

HOURS

RC

GRID#

Version-1: re-sequence reference.C231A Y, Nakamura 09/21/2024 -/-/N

V-01 0 0 0

Version-2: revise special requirements and correct man-hours for 5.2, 5.5, and CFM for preservation work. C231A Y. Nakamura, 10/16/2024, Y/Y/N

V-02 0 0 0

FOUO

M-1

SHIP: DDG-114 CHG/VER: 1/2

APPENDIX “M”

TGI MATERIAL LIST

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

WASTE TK 5-220-2-F AY A 0 2

CU PHASE TITLE:

F/O - CLEAN, ASSESS, REPAIR, AND PRESERVE OILY WASTE HOLDING TANK (5-220-2-F)

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV

JOB ORDER: KEY OP:

38K5212327 A01

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

NOTES:

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR APPENDIX "D"

DEFICIENCY FORM

☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One)

2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

DDG-114 WASTE TK 5-220-2-F AY A 0

4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:

38K5212327 A01

7. DESCRIPTION:

8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

9. CORRECTIVE ACTION:

10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

FOR NON-NUCLEAR USE ONLY

11. RFD/RFW REQ’D ☐ LAR REQ'D ☐

ILS MOD REQ’D ☐

SRD/PLAN REV REQ'D ☐

DWG NO.: _____________________ S/A NO.: ___________________

12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:

SATISFACTORY:

13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

YES ☐ NO ☐

14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE:

15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

_________:YES ☐ NO ☐

16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE (DR ONLY)

DL’s ISSUED

(DR ONLY)

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

DDG-114 WASTE TK 5-220-2-F AY A 0

File details come from the government source that posted it. Updated .