This is a Task Group Instruction (TGI) document for cleaning chain lockers and replacing manhole assemblies on the USS RALPH JOHNSON (DDG-114). The work includes cleaning of Chain Locker (3-6-1-Q), Chain Locker (3-6-2-Q), and Chain Locker Sump (3-12-0-W), along with replacement of manhole assemblies in these spaces. The scope involves installing new 15" x 23" flush deck, water-tight manhole assemblies, cleaning multiple spaces including the Anchor Holding Equipment Storeroom, Windlass Machinery Room, Sonar Equipment Room No. 3, and Forepeak Tank.
The work is scheduled for execution between July 14, 2025, and August 21, 2025, with a material cost of $2,201.20 and requires 1,107 total man hours. The TGI specifies requirements for manhole cover plates and bolting rings made of steel, with quality assurance requirements including local air hose testing of new welds with zero allowable leakage. The document notes this work affects fire zone boundaries and requires fabrication of non-flammable closures. SRF-JRMC will provide various support services including crane operations, utilities, safety inspections, and quality assurance inspections.
View the file
Other files
Show 40 more
Latest 50 of 73 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: CHAIN LOCKER & SUMP AY A 0 0
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
DDG-114 USS RALPH JOHNSON K52
CU PHASE TITLE:
F/O - CLN CHAIN LKR & CHAIN LKR SUMP 3-6-1-Q, 3-6-2-Q, & 3-12-0-W & REPL MH AY
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
YUUTA KISHI 231A 315-243-6411 13-SEP-2024
APPROVED BY: CODE PHONE DATE
YUUJI NAKAMURA 231A 315-243-6041 13-SEP-2024
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
CHANGE INSTRUCTIONS:
SPECIAL REQUIREMENTS:
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: CHAIN LOCKER & SUMP AY A 0
FOUO
SHIP: DDG-114 CHG/VER: 0/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-5 J1-2 M1
1. SCOPE/PURPOSE
1.1 Title: Cleaning of Chain Locker (3-6-1-Q), Chain Locker (3-6-2-Q) and Chain Locker Sump (3-12-0-W) and Replacement of Manhole Assembly; accomplish
1.2 Location of Work:
1.2.1 Chain Locker (3-6-1-Q)
1.2.2 Chain Locker (3-6-2-Q)
1.2.3 Chain Locker Sump (3-12-0-W)
1.2.4 Anchor Holding Equipment Storeroom (0 1/2-W-0-A)
1.2.5 Windlass Machinery Room (0 1/2-2-0-Q)
1.2.6 Sonar Equipment Room No. 3 (3-18-0-Q)
1.2.7 Forepeak Tank (4-P-0-W)
1.3 Identification:
1.3.1 Quantity (One EA), Chain Locker
Space No.: 3-6-1-Q
1.3.2 Quantity (One EA), Chain Locker
Space No.: 3-6-2-Q
1.3.3 Quantity (One EA), Chain Locker Sump
Space No.: 3-12-0-W
1.3.4 Quantity (One AY), Manhole Assembly for 3-6-1-Q [Existing] Manhole No. : 0.5-8-1 Manhole Size: 15 Inches x 23 Inches Type: Flush Deck, Water-Tight
1.3.5 Quantity (One AY), Manhole Assembly for 3-6-2-Q [Existing] Manhole No. : 0.5-8-2 Manhole Size: 15 Inches x 23 Inches Type: Flush Deck, Water-Tight
1.3.6 Quantity (One AY), Manhole Assembly for 3-6-1-Q [New]
Manhole No. : 0.5-8-1 Manhole Size: 15 Inches x 23 Inches Type: Flush Deck, Water-Tight Remarks: See Assy No. 7 of 2.4 for details.
FOUO
SHIP: DDG-114 CHG/VER: 0/0
1.3.7 Quantity (One AY), Manhole Assembly for 3-6-2-Q [New]
Manhole No. : 0.5-8-2 Manhole Size: 15 Inches x 23 Inches Type: Flush Deck, Water-Tight Remarks: See Assy No. 7 of 2.4 for details.
1.3.8 Quantity (4 EA), Manhole Cover Plate
1.3.8.1 Quantity (One EA), Manhole Cover Plate for 3-6-1-Q
Manhole No.: 0 1/2-8-1 Size: 15 Inches x 23 Inches Material: Steel
1.3.8.2 Quantity (One EA), Manhole Cover Plate for 3-6-2-Q
Manhole No.: 0 1/2-8-2 Size: 15 Inches x 23 Inches Material: Steel
1.3.8.3 Quantity (2 EA), Manhole Cover Plate for 3-12-0-W
Manhole No.: 3-18-1 and 3-18-2 Size: 15 Inches x 23 Inches Material: Steel
1.3.9 Quantity (4 EA), Bolting Ring for Manhole Cover Plate
1.3.9.1 Quantity (One EA), Bolting Ring for Manhole Cover Plate for 3-6-1-Q Manhole No.: 0 1/2-8-1 Material: Steel
1.3.9.2 Quantity (One EA), Bolting Ring for Manhole Cover Plate for 3-6-2-Q Manhole No.: 0 1/2-8-2 Material: Steel
1.3.9.3 Quantity (2 EA), Bolting Ring for Manhole Cover Plate for 3-12-0-W Manhole No.: 3-18-1 and 3-18-2 Material: Steel
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor work start date:
1.7 Contractor work completion date:
2. REFERENCES:
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-25 NAVSEA Standard Items - 1 N 2 LI FY-25 Local Standard Items - ORG N
3 TM S9086-
CJ-STM-
010/CH--075
Fasteners 7 N
Masato.Endo.ja Typewritten Text
14 JUL 2025
Masato.Endo.ja Typewritten Text
21 AUG 2025
FOUO
SHIP: DDG-114 CHG/VER: 0/0
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
4 DWG 8100-
1254-0085
FLUSH DK. W.T. & OIL TIGHT
BOLTED PLATE MANHOLE 15" x 36", 15" x 18" & 15" x 23"
AA Y AL
L
5 DWG 167-
7062372
MANHOLE LIST SHIP WIDE - Y 7H
9A
6 DWG 100-
7060366
UNIT STRL ARR DWG ASSY UNIT
C Y 3
3. APPENDICES:
3.1. Appendix “J” TGI Job Summary Information Sheet
3.2. Appendix "M" TGI Material List
3.3. Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1. This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.
5. PROCEDURE:
5.1 Accomplish the requirements of 099-902YO of 2.2 for each space listed in 1.3.1 through 1.3.3.
5.1.1 Install each manhole cover for each space listed in 1.3.1 through 1.3.3 in accordance with figures 075-4-1 of 2.3.
5.2 Remove each existing manhole assembly listed in 1.3.4 and 1.3.5, and install each new manhole assembly listed in 1.3.6 and 1.3.7 in accordance with 2.4 and 2.5, using 2.6 for guidance.
5.2.1 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) A, Lines One through 7.
5.2.2 Accomplish the requirements of 009-25 of 2.1 for a local air hose test of each new weld of each manhole assembly. Allowable leakage: None.
5.3 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 24, for chain locker and chain locker sump side surface, and Table 3, Line(s) 25, for windlass machinery room and sonar equipment room side surface of each cover plate listed in 1.3.8.
5.4 Accomplish the requirements of 009-32 of 2.1 for each bolting ring listed in 1.3.9.
5.5 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
5.6 Notes:
5.6.1 Planner: Code 231A Y. Kishi, 243-6411
5.6.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
5.6.3 Opening, cleaning, and closing of each tank listed in 1.2.7 will be covered by TGI No. 38K5212345A01 (KTR
TGI).
Masato.Endo.ja Typewritten Text
12/21/2024 C-1209 M. ENDO 11030028
Masato.Endo.ja Cross-Out
FOUO
SHIP: DDG-114 CHG/VER: 0/0
5.6.4 Removal and installation of bow anchor and anchor chains will be covered by TGI No. 38K5258101A01 (KTR
TGI).
5.6.5 This TGI meets the intent of DDG CSWT File No. 123-133.
5.6.6 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.
5.6.7 JCNs ER01-ZA83, ER01-ZA84, and EB14-ZA85 are related to this TGI.
5.7 Government Furnished Material (GFM):
5.7.1 SRF-JRMC will provide GFM listed in Appendix “M”.
5.8 SRF-JRMC will provide the following service work: (TGI No. 38K5212348S02)
5.8.1 [C740] Crane and crane rigging service.
5.8.2 [X99E] Utility service, electrical.
5.8.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
5.8.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.8.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.8.6 [C133] QA inspection for (G) symbol(s).
FOUO
J-1
SHIP: DDG-114 CHG/VER: 0/0
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
CHAIN LOCKER & SUMP AY A 0 0
CU PHASE TITLE:
F/O - CLN CHAIN LKR & CHAIN LKR SUMP 3-6-1-Q, 3-6-2-Q, & 3-12-0-W & REPL MH AY
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
MANHOLE 0.5-8-1 HA MANHOLE 3-18-2 HA VOID 3-6-1-Q VD MANHOLE 0.5-8-2 HA
MANHOLE 3-18-1 HA VOID 3-6-2-Q VD VOID 3-12-0-W VD
ATTACHMENT LIST:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA ,TAKEHIDE
JO: KO: TOTAL MAN HRS: TOTAL MAT’L COST TOTAL DURATION: PLANNING ACCEPTANCE:
38K5212348 A01 1107 $2,201.20 1
CU PHASE DESCRIPTION:
The purpose of this TGI is to clean Chain Locker (3-6-1-Q), Chain Locker (3-6-2-Q) and Chain Locker Sump (3-12- 0-W) and replace manhole assembly.
Location of Work:
Chain Locker (3-6-1-Q) Chain Locker (3-6-2-Q) Chain Locker Sump (3-12-0-W) Anchor Holding Equipment Storeroom (0 1/2-W-0-A) Windlass Machinery Room (0 1/2-2-0-Q) Sonar Equipment Room No. 3 (3-18-0-Q) Forepeak Tank (4-P-0-W)
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
FOUO
J-2
SHIP: DDG-114 CHG/VER: 0/0
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
FOUO
M-1
SHIP: DDG-114 CHG/VER: 0/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
CHAIN LOCKER & SUMP AY A 0 0
CU PHASE TITLE:
F/O - CLN CHAIN LKR & CHAIN LKR SUMP 3-6-1-Q, 3-6-2-Q, & 3-12-0-W & REPL MH AY
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
JOB ORDER: KEY OP:
38K5212348 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 M MANHOLE, 15" X 23", , STEEL,
15" X 23", DH-36,0-15
PSI,FLUSH DECK, W.T & O.T,
BOLTED,REFERENCE
DRAWING: BIW DWG: 8100-
1254-0085 REV-AA, ASSY NO
OREDER FOR KTR
ORIG: C231A Y. KISHI, 243-
9B 2040 LL4639459 NA 4 N 42567554 2/EA
NOTES:
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-114 CHAIN LOCKER & SUMP AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
38K5212348 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-114 CHAIN LOCKER & SUMP AY A 0