This Task Group Instruction (TGI) details work requirements for cleaning and maintaining fuel tanks on the USS RALPH JOHNSON (DDG-114) at Yokosuka Naval Base. The work focuses on Fuel Tank Group-4 (5-220-4-F) with a capacity of 17,328 gallons, along with associated work on seven other tanks in Groups 3 and 4 with a total combined capacity of 117,151 gallons. The scope includes opening and cleaning tanks, installing manhole covers, surface preparation, and painting of cover plates and bolting rings.

The work is to be performed between July 14, 2025, and December 11, 2025. The contractor must follow specific cleaning procedures to Level III standards and comply with various NAVSEA Standard Items. Government-furnished services include crane operations, utility services (electrical, air, water, steam), safety inspections, gas-free inspections, and QA inspections. This TGI (38K5212354-A01) is part of a larger ship repair availability package being solicited under contract N6264925RA025, with offers due by March 11, 2025, at 10:00 AM Japan Standard Time.

View the file

Other files

File Type Posted
2.03 Amendment 0003 25RA025.pdf PDF
2.03 Amendment 0002 25RA025.pdf PDF
2.03 Amendment 0001 25RA025.pdf PDF
TGI_38K5263408A01_c0v0.pdf PDF
TGI_38K5212351A01_c3v1.rev1.pdf PDF
2.02 Attachment V Contract Data Sheet 25RA025.pdf PDF
TGI_38K5259310A01_c0v0.pdf PDF
TGI_38K5212347A01_c0v0.rev1.pdf PDF
TGI_38K5212352A01_c0v0.rev1.pdf PDF
TGI_38K5212346A01_c0v0.rev1.pdf PDF
TGI_38K5212389A01_c0v0.pdf PDF
TGI_38K5213001A01_c1v1.pdf PDF
TGI_38K5212317_A01_c2v2.rev1.pdf PDF
TGI_38K5212314_A01_c0v0.rev1.pdf PDF
TGI_38K5212315_A01_c0v0.rev1.pdf PDF
TGI_38K5212382A01_c0v0.pdf PDF
TGI_38K5212365A01_c0v0.pdf PDF
TGI_38K5213102A01_c1v1.pdf PDF
TGI_38K5215401A01_c0v0.pdf PDF
TGI_38K5212329_A01_c1v1.rev1.pdf PDF
TGI_38K5212363T01_c0v0.pdf PDF
TGI_38K5212321A01_c2v0.rev1.pdf PDF
TGI_38K5212342A01_c0v0.rev1.pdf PDF
TGI_38K5212364A01_c0v0.pdf PDF
TGI_38K5216702_A01_c0v0.pdf PDF
TGI_38K5212325_A01_c0v0.rev1.pdf PDF
TGI_38K5212377A01_c1v1.pdf PDF
TGI_38K5212312_A01_c0v0.rev1.pdf PDF
TGI_38K5212340A01_c0v0.rev1.pdf PDF
TGI_38K5212313_A01_c0v1.rev1.pdf PDF
TGI_38K5212323_A01_c0v0.rev1.pdf PDF
TGI_38K5212309_A01_c0v0.rev1.pdf PDF
TGI_38K5212392A01_c1v1.pdf PDF
2.02 Attachment IV N6264925RA025 Request for Information Form.doc DOC document
TGI_38K5216704_A01_c0v0.pdf PDF
TGI_38K5212356A01_c0v0.rev1.pdf PDF
TGI_38K5212391A01_c0v0.pdf PDF
2.02 Attachment II Price Proposal Form N6264925RA025.xlsx XLSX spreadsheet
TGI_38K5212336_A01_c0v0.pdf PDF
TGI_38K5212320_A01_c1v1.rev1.pdf PDF
TGI_38K5212328_A01_c0v0.rev1.pdf PDF
TGI_38K5212319_A01_c2v1.rev1.pdf PDF
TGI_38K5216705_A01_c0v1.pdf PDF
TGI_38K5212390A01_c0v0.pdf PDF
TGI_38K5212330_A01_c0v0.rev1.pdf PDF
TGI_38K5212327_A01_c1v2.rev1.pdf PDF
TGI_38K5212355A01_c0v0.rev1.pdf PDF
2.02 Attachment III N6264925RA025 Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
TGI_38K5212348A01_c0v0.pdf PDF
TGI_38K5216703_A01_c0v0.pdf PDF
Show 40 more

Latest 50 of 73 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

06-DEC-2024 1500

20.14.15.2.9020 (September 2024) ICN: 38K5212354 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: FOCT 5-220-4-F AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-114 USS RALPH JOHNSON K52

CU PHASE TITLE: F/O - OPEN AND CLEAN FUEL TANK GROUP-4 (5-220-4-F)

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 5

ER01ZA93

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

KISHI, YUUTA 231A 3152436411 07-SEP-2024

APPROVED BY: CODE: PHONE: DATE:

NAKAMURA, YUUJI 231A 3152436041 09-SEP-2024

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

ER01-ZA93

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

123A1154

1. SCOPE/PURPOSE:

1.1 Title: Fuel Tank Group-4 (5-220-4-F); open and clean

1.2 Location of Work:

1.2.1 Fuel Tank Group-4 (5-220-4-F)

1.2.2 Engine Room No. One (4-174-0-E)

1.2.3 Auxiliary Machinery Room No. 2 (4-220-0-E)

1.2.4 Engine Room No. 2 (4-254-0-E)

1.3 Identification:

1.3.1 Quantity (One EA), Fuel Tank Group-4

TGI Short Form

06-DEC-2024 1500

20.14.15.2.9020 (September 2024) (Continued) ICN: 38K5212354 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: FOCT 5-220-4-F AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-114 USS RALPH JOHNSON K52

CU PHASE TITLE: F/O - OPEN AND CLEAN FUEL TANK GROUP-4 (5-220-4-F)

FOUO Pg 2 of 5

CU PHASE DESCRIPTION (Cont.)

Tank No.: 5-220-4-F Capacity: 17,328 Gallons

1.3.2 Quantity (One Lot/ 8 Tanks), Fuel Tank Group-3 and Group-4 Total Capacity: 117,151 Gallons Required amount of water to dewater: 100,952 Gallons

1.3.2.1 Fuel Receiving Tank Group-3

Tank No.: 4-174-1-F Capacity: 23,007 Gallons

1.3.2.2 Fuel Tank Group-3

Tank No.: 5-220-3-F Capacity: 17,120 Gallons

1.3.2.3 Fuel Tank Group-3

Tank No.: 5-254-3-F Capacity: 20,698 Gallons

1.3.2.4 Fuel Expansion Seawater Overflow Tank Group-3

Tank No.: 5-254-1-F Capacity: 2,096 Gallons

1.3.2.5 Fuel Tank Group-4

Tank No.: 5-220-4-F Capacity: 17,328 Gallons

1.3.2.6 Reserve Fuel Tank Group-4

Tank No.: 4-272-2-F Capacity: 21,685 Gallons

1.3.2.7 Fuel Tank Group-4

Tank No.: 5-264-2-F Capacity: 13,000 Gallons

1.3.2.8 Fuel Expansion Seawater Overflow Tank Group-4

Tank No.: 5-254-2-F Capacity: 2,217 Gallons

1.3.3 Quantity (One EA), Manhole Cover Plate for 5-220-4-F

Manhole No.: 4-226-2 Size: 15 Inches x 23 Inches Material: Steel

1.3.4 Quantity (One EA), Air Vent Hose Connection (AVHC) Cover Plate for 5-220-4-F AVHC No.: 4-241-2 Size: 10 Inches Diameter Material: Steel

06-DEC-2024 1500

20.14.15.2.9020 (September 2024) (Continued) ICN: 38K5212354 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: FOCT 5-220-4-F AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-114 USS RALPH JOHNSON K52

CU PHASE TITLE: F/O - OPEN AND CLEAN FUEL TANK GROUP-4 (5-220-4-F)

FOUO Pg 3 of 5

CU PHASE DESCRIPTION (Cont.)

1.3.5 Quantity (2 EA), Bolting Ring for Manhole Cover Plate and AVHC Cover Plate for 5-220-4-F

Manhole No.: 4-226-2 AVHC No.: 4-241-2 Material: Steel

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor work start date: 14 JUL 2025

1.7 Contractor work completion date: 11 DEC 2025

2. PROCEDURE:

2.1 Accomplish the requirements of 099-902YO of Ref. No. 2 for each tank listed in 1.3.1.

2.1.1 Accomplish the requirements of 099-909YO of Ref. No. 2 for each tank listed in 1.3.2.

2.1.1.1 Accomplish the requirements of 009-09 of Ref. No. One.

2.1.2 Accomplish the requirements of 009-107 of Ref. No. One for each tank listed in 1.3.1.

2.1.2.1 Ensure General Cleaning must be Level III.

2.1.3 Install each manhole cover for each tank listed in 1.3.1 in accordance with figures 075-4-1 of Ref. No. 3.

2.2 Accomplish the requirements of 009-32 of Ref. No. One, including Table 4, Line(s) 11, for tank side surface, and Table 3, Line(s) 12, for machinery side surface of each cover plate listed in 1.3.3 and 1.3.4.

2.3 Accomplish the requirements of 009-32 of Ref. No. One for each bolting ring listed in 1.3.5.

2.4 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.

2.5 Notes:

2.5.1 Planner: Code 231A Y. Kishi, 243-6411

2.5.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.5.3 This TGI meets the intent of DDG CSWT File No. 123-133.

2.5.4 JCN ER01-ZA93 is related to this TGI.

2.6 Government Furnished Material (GFM): None.

2.7 SRF-JRMC will provide the following service work: (TGI No. 38K5212354S02)

2.7.1 [C740] Crane and crane rigging service.

06-DEC-2024 1500

20.14.15.2.9020 (September 2024) (Continued) ICN: 38K5212354 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: FOCT 5-220-4-F AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-114 USS RALPH JOHNSON K52

CU PHASE TITLE: F/O - OPEN AND CLEAN FUEL TANK GROUP-4 (5-220-4-F)

FOUO Pg 4 of 5

CU PHASE DESCRIPTION (Cont.)

2.7.2 [X99E] Utility service, electrical.

2.7.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.7.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.7.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.7.6 [C133] QA inspection for (G) symbol(s).

06-DEC-2024 1500

20.14.15.2.9020 (September 2024) (Continued) ICN: 38K5212354 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: FOCT 5-220-4-F AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-114 USS RALPH JOHNSON K52

CU PHASE TITLE: F/O - OPEN AND CLEAN FUEL TANK GROUP-4 (5-220-4-F)

FOUO Pg 5 of 5

OTHER SPECIAL REQUIREMENTS:

CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - 1 N 2 LI FY-25 Local Standard Items - ORG N

3 TM S9086-CJ-STM-

010/CH--075

Fasteners 7 N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38K5212354 KEY OP: A01