This WebAIM Short Form Task Group Instruction (TGI) details a tightness and operational test for the 1B Boiler on the USS Blue Ridge (LCC-19), scheduled for 06-MAY-2025. The document identifies three primary work tasks to be accomplished by different groups: a Contractor (22/KE), Quality Assurance (33/G1), and Support/Facility work team (EM02), all of whom are required to accomplish and document the tightness and operational test in accordance with reference document TP 22111-3-300KTR. The instruction is part of Project 19P, System 22111, and was prepared by Oosaka, Tesshin and approved by Ohta, Jason Y. on 02-MAY-2025, with a TGI number of 22111-3-300KTR and a KeyOp code of T01.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
06-MAY-2025 1440
20.14.15.2.9020 (September 2024) ICN: 3819P22115 KeyOp: T01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 22111-3-300KTR TT T 5 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 22111
CU PHASE TITLE: 1B BOILER (T & OP) - KTR
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 2
EM02L192
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
OOSAKA, TESSHIN 246.2 3152434109 17-APR-2025
APPROVED BY: CODE: PHONE: DATE:
OHTA, JASON Y. 246.2 3152435901 02-MAY-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EM02-L192
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
TAKAHASHI, YASUHIKO U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
221A1115
Tightness & Operational Test for 1B BOILER - KTR.
TGI Short Form
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
06-MAY-2025 1440
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22115 KeyOp: T01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 22111-3-300KTR TT T 5 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 22111
CU PHASE TITLE: 1B BOILER (T & OP) - KTR
FOUO Pg 2 of 2
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 TP 22111-3-300KTR BOILER (T & OP) - KTR LAT Y
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
(V) Contractor work:
Accomplish/document the tightness & operational test in accordance with reference, TP 22111-3-300KTR.
22/KE PC N
(G) QA work:
Accomplish/document the tightness & operational test in accordance with reference, TP 22111-3-300KTR.
33/G1 QA N
(S) S/F work:
Accomplish/document the tightness & operational test in accordance with reference, TP 22111-3-300KTR.
/ EM02 N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P22115 KEY OP: T01