This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge, detailing the removal and installation of a Deaerating Feed Tank (DFT) Steam Pressure Relief Valve. The specific task involves removing and installing one 4.00-inch IPS relief valve (Valve No. V57) located in the Fire Room (8-76-0-E), with work to be conducted between July 21, 2026, and November 21, 2027. The instruction includes detailed procedural steps for valve removal, surface restoration, and reinstallation, with guidance from referenced documents and support from SRF-JRMC, which will provide government-furnished materials, crane services, utility services, safety inspections, and quality assurance inspections. The task is in response to a Boiler Inspection and Repair Management Information System (BIRMIS) report for the 1A Boiler, and involves potential asbestos hazard considerations.

View the file

Other files

File Type Posted
N6264925RA059-0009.pdf PDF
N6264925RA059-0002.pdf PDF
N6264925RA059-0001.pdf PDF
3819P25001T04_c0v0_TGI.pdf PDF
3819P25001T01_c0v0_TGI.pdf PDF
TGI_3819P22115T01_c0v0.pdf PDF
TGI_3819P22114T06_c0v0.pdf PDF
TGI_3819P123AGT11_c0v0.pdf PDF
TGI_3819P123AGT01_c0v0.pdf PDF
Attachment VI Quality Assurance Surveillance Plan (QASP).pdf PDF
Attachment V Contract Data Sheet.pdf PDF
3819P65416A01_c1v2_FY26_TGI.pdf PDF
3819P26001A01_c0v0_FY26_TGI.pdf PDF
3819P25201A01_c0v0_FY26_TGI.pdf PDF
3819P22115A12_c0v0_FY26_TGI.pdf PDF
3819P22115A06_c0v0_FY26_TGI.pdf PDF
3819P22115A05_c0v0_FY26_TGI.pdf PDF
3819P22115A01_c1v1_FY26_TGI.pdf PDF
3819P22114A17_c0v0_FY26_TGI.pdf PDF
3819P22114A13_c0v1_FY26_TGI.pdf PDF
3819P22114A10_c0v0_FY26_TGI.pdf PDF
3819P43701T01_c0v0_TGI.pdf PDF
3819P25001T02_c0v0_TGI.pdf PDF
TGI_3819P22115T02_c0v0.pdf PDF
TGI_3819P22114T05_c0v0.pdf PDF
TGI_3819P22114T03_c0v0.pdf PDF
TGI_3819P123AGT12_c0v0.pdf PDF
TGI_3819P123AGT04_c0v0.pdf PDF
TGI_3819P123AGT02_c0v0_TT_rev.pdf PDF
Attachment VII Warranty Tracking Information.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL)_R1.pdf PDF
3819P25514A01_c0v0_FY26_TGI.pdf PDF
3819P25001A01_c1v0_FY26_TGI.pdf PDF
3819P22124A01_c0v0_FY26_TGI.pdf PDF
3819P22115A11_c0v0_FY26_TGI.pdf PDF
3819P22115A10_c0v0_FY26_TGI.pdf PDF
3819P22115A08_c0v0_FY26_TGI.pdf PDF
3819P22115A02_c1v1_FY26_TGI.pdf PDF
3819P22114A15_c0v0_FY26_TGI.pdf PDF
3819P22114A11_c1v2_FY26_TGI.pdf PDF
3819P22114A05_c0v0_FY26_TGI.pdf PDF
3819P22114A04_c1v1_FY26_TGI.pdf PDF
3819P22114A02_c0v0_FY26_TGI.pdf PDF
3819P22114A01_c0v0_FY26_TGI.pdf PDF
N6264925RA059-0003.pdf PDF
3819P43701T02_c0v0_TGI.pdf PDF
3819P25606T01_c0v0_TGI.pdf PDF
3819P25001T03_c0v0_TGI.pdf PDF
TGI_3819P22115T05_c0v0.pdf PDF
TGI_3819P22114T04_c0v0.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

09-JUL-2025 1510

20.14.15.2.9020 (September 2024) ICN: 3819P22114 KeyOp: A12

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #1 DFT AUX EXH RLF V- A 0 0/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 25571

CU PHASE TITLE: (N14-03) F/O – REMOVE AND INSTALL DFT RLF V IN 8-76-0-E

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 4

EM02L194

PREPARING ACTIVITY: STATUS: APP WORKING STATUS: PKG

PREPARED BY: CODE: PHONE: DATE:

IKEDA, KOUTARO 232 3152430958 24-FEB-2025

APPROVED BY: CODE: PHONE: DATE:

OZAWA, AKIHITO 232 3152432493 09-JUL-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EM02-L194

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

TAKAHASHI, YASUHIKO 8-76-0-E U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

221A1114

1. SCOPE/PURPOSE:

1.1 Title: No. One Deaerating Feed Tank (DFT) Steam Pressure Relief Valve; remove and install

1.2 Location of Work:

1.2.1 Fire Room (8-76-0-E)

1.3 Identification:

1.3.1 Quantity (One EA), No. One DFT Steam Pressure Relief Valve Type: Relief Valve Size: 4.00-Inch IPS Valve No: V57 of Ref. No. 3

1.4 Security Classification: None.

TGI Short Form

09-JUL-2025 1510

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A12

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #1 DFT AUX EXH RLF V- A 0 0/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 25571

CU PHASE TITLE: (N14-03) F/O – REMOVE AND INSTALL DFT RLF V IN 8-76-0-E

FOUO Pg 2 of 4

CU PHASE DESCRIPTION (Cont.)

1.5 Initial Condition:

1.5.1 Potential Asbestos Hazard

1.6 Contractor work start date: 7/21/2026

1.7 Contractor work completion date: 11/21/2027

2. PROCEDURE:

2.1 Remove each valve listed in 1.3.1 for SRF-JRMS test work, using Ref. No. 3 and Ref. No. 4 for guidance.

2.1.1 Restore each mating surface exposed by removal.

2.1.1.1 Remove each high spot, burr, abrasion, nick, corrosion, and foreign matter from each exposed flange and mating surface.

2.1.1.2 Chase and tap each exposed threaded area.

2.2 Install each valve listed in 1.3.1 after completion of SRF-JRMC test work, using Ref. No. 3 and Ref. No. 4 for guidance.

2.2.1 Remove existing and install new each steam piping joint gasket, conforming to MIL-G-24716.

2.3 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.

2.4 Notes:

2.4.1 Planner: Code 232 K. Ikeda, 243-0958

Planner: Code 231B N. Kurokawa, 243-0108 Planner: Code 234 Y. Yajima, 243-0977

2.4.2 Zone Manager (ZM): Code 333 T. Yaginuma, 080-5419-0598

2.4.3 This TGI is response to Boiler Inspection and Repair Management Information System (BIRMIS) for 1A Boiler report dated 17 OCT 2024, Line Item N14-03.

2.4.4 Shop test work for each relief valve listed in 1.3.1 will be accomplished by SRF-JRMC TGI No. 3819P22114-H01.

2.4.5 JCN EM02-L194 is related to this TGI.

2.5 Government Furnished Material (GFM):

2.5.1 SRF-JRMC will provide GFM listed in Material List.

2.6 SRF-JRMC will provide following service work: (TGI No. 3819P22114-S15)

2.6.1 [C740] Crane and crane rigging service.

2.6.2 [X99E] Utility service, electrical.

09-JUL-2025 1510

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A12

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #1 DFT AUX EXH RLF V- A 0 0/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 25571

CU PHASE TITLE: (N14-03) F/O – REMOVE AND INSTALL DFT RLF V IN 8-76-0-E

FOUO Pg 3 of 4

CU PHASE DESCRIPTION (Cont.)

2.6.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.6.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.6.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.6.6 [C133] QA inspection for (G) Symbol(s).

09-JUL-2025 1510

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A12

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #1 DFT AUX EXH RLF V- A 0 0/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 25571

CU PHASE TITLE: (N14-03) F/O – REMOVE AND INSTALL DFT RLF V IN 8-76-0-E

FOUO Pg 4 of 4

OTHER SPECIAL REQUIREMENTS:

CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL II

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N 3 DWG 514-2492510 AGC19 AUX EXH & Escape -

DIAG

C Y ALL

4 DWG NMP-162 4" Model "L-2210-C" Bronze Navy Relief Valve Type A-1 Class C

D Y ALL

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

2.1 OMCH, RGRS, INSL:

2.2 OMCH, RGRS, INSL:

2.3 PNTR, QA

Outside Machinist Work CFM: fasteners and misc.

Insulation Work CFM: all paints, thinners, asbestos sampling/analysis cost, insulation, cap, adhesive, insulation tape, tyvex suit, masking tape, plastic bag, and MISC such as other consumable.

Lagging Work (for lagging pad) CFM: asbestos sampler and analysis cost, covering material, hook, tyvek suit, and MISC such as other consumable material.

Process Funding Document.

Version-01: change COPY REQD to “Y” for Ref. No. 3, and No. 4. C232 A. Ozawa, 07/09/2025, -/Y/N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

001 M GASKET,S, ORIG: C232, K.

IKEDA, 243-0958

ORDERED FOR KTR

9B 5330 013387835 NA 4 N 50555193 2/EA

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P22114 KEY OP: A12