3819P22114A12_c0v1_FY26_TGI.pdf
PDF 162 KB Posted
- Solicitation number
- N6264925RA059-0008
About this file
This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge, detailing the removal and installation of a Deaerating Feed Tank (DFT) Steam Pressure Relief Valve. The specific task involves removing and installing one 4.00-inch IPS relief valve (Valve No. V57) located in the Fire Room (8-76-0-E), with work to be conducted between July 21, 2026, and November 21, 2027. The instruction includes detailed procedural steps for valve removal, surface restoration, and reinstallation, with guidance from referenced documents and support from SRF-JRMC, which will provide government-furnished materials, crane services, utility services, safety inspections, and quality assurance inspections. The task is in response to a Boiler Inspection and Repair Management Information System (BIRMIS) report for the 1A Boiler, and involves potential asbestos hazard considerations.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
09-JUL-2025 1510
20.14.15.2.9020 (September 2024) ICN: 3819P22114 KeyOp: A12
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #1 DFT AUX EXH RLF V- A 0 0/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25571
CU PHASE TITLE: (N14-03) F/O – REMOVE AND INSTALL DFT RLF V IN 8-76-0-E
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 4
EM02L194
PREPARING ACTIVITY: STATUS: APP WORKING STATUS: PKG
PREPARED BY: CODE: PHONE: DATE:
IKEDA, KOUTARO 232 3152430958 24-FEB-2025
APPROVED BY: CODE: PHONE: DATE:
OZAWA, AKIHITO 232 3152432493 09-JUL-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EM02-L194
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
TAKAHASHI, YASUHIKO 8-76-0-E U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
221A1114
1. SCOPE/PURPOSE:
1.1 Title: No. One Deaerating Feed Tank (DFT) Steam Pressure Relief Valve; remove and install
1.2 Location of Work:
1.2.1 Fire Room (8-76-0-E)
1.3 Identification:
1.3.1 Quantity (One EA), No. One DFT Steam Pressure Relief Valve Type: Relief Valve Size: 4.00-Inch IPS Valve No: V57 of Ref. No. 3
1.4 Security Classification: None.
TGI Short Form
09-JUL-2025 1510
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A12
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #1 DFT AUX EXH RLF V- A 0 0/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25571
CU PHASE TITLE: (N14-03) F/O – REMOVE AND INSTALL DFT RLF V IN 8-76-0-E
FOUO Pg 2 of 4
CU PHASE DESCRIPTION (Cont.)
1.5 Initial Condition:
1.5.1 Potential Asbestos Hazard
1.6 Contractor work start date: 7/21/2026
1.7 Contractor work completion date: 11/21/2027
2. PROCEDURE:
2.1 Remove each valve listed in 1.3.1 for SRF-JRMS test work, using Ref. No. 3 and Ref. No. 4 for guidance.
2.1.1 Restore each mating surface exposed by removal.
2.1.1.1 Remove each high spot, burr, abrasion, nick, corrosion, and foreign matter from each exposed flange and mating surface.
2.1.1.2 Chase and tap each exposed threaded area.
2.2 Install each valve listed in 1.3.1 after completion of SRF-JRMC test work, using Ref. No. 3 and Ref. No. 4 for guidance.
2.2.1 Remove existing and install new each steam piping joint gasket, conforming to MIL-G-24716.
2.3 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.
2.4 Notes:
2.4.1 Planner: Code 232 K. Ikeda, 243-0958
Planner: Code 231B N. Kurokawa, 243-0108 Planner: Code 234 Y. Yajima, 243-0977
2.4.2 Zone Manager (ZM): Code 333 T. Yaginuma, 080-5419-0598
2.4.3 This TGI is response to Boiler Inspection and Repair Management Information System (BIRMIS) for 1A Boiler report dated 17 OCT 2024, Line Item N14-03.
2.4.4 Shop test work for each relief valve listed in 1.3.1 will be accomplished by SRF-JRMC TGI No. 3819P22114-H01.
2.4.5 JCN EM02-L194 is related to this TGI.
2.5 Government Furnished Material (GFM):
2.5.1 SRF-JRMC will provide GFM listed in Material List.
2.6 SRF-JRMC will provide following service work: (TGI No. 3819P22114-S15)
2.6.1 [C740] Crane and crane rigging service.
2.6.2 [X99E] Utility service, electrical.
09-JUL-2025 1510
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A12
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #1 DFT AUX EXH RLF V- A 0 0/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25571
CU PHASE TITLE: (N14-03) F/O – REMOVE AND INSTALL DFT RLF V IN 8-76-0-E
FOUO Pg 3 of 4
CU PHASE DESCRIPTION (Cont.)
2.6.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.6.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.6.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.6.6 [C133] QA inspection for (G) Symbol(s).
09-JUL-2025 1510
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A12
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #1 DFT AUX EXH RLF V- A 0 0/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25571
CU PHASE TITLE: (N14-03) F/O – REMOVE AND INSTALL DFT RLF V IN 8-76-0-E
FOUO Pg 4 of 4
OTHER SPECIAL REQUIREMENTS:
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL II
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N 3 DWG 514-2492510 AGC19 AUX EXH & Escape -
DIAG
C Y ALL
4 DWG NMP-162 4" Model "L-2210-C" Bronze Navy Relief Valve Type A-1 Class C
D Y ALL
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 OMCH, RGRS, INSL:
2.2 OMCH, RGRS, INSL:
2.3 PNTR, QA
Outside Machinist Work CFM: fasteners and misc.
Insulation Work CFM: all paints, thinners, asbestos sampling/analysis cost, insulation, cap, adhesive, insulation tape, tyvex suit, masking tape, plastic bag, and MISC such as other consumable.
Lagging Work (for lagging pad) CFM: asbestos sampler and analysis cost, covering material, hook, tyvek suit, and MISC such as other consumable material.
Process Funding Document.
Version-01: change COPY REQD to “Y” for Ref. No. 3, and No. 4. C232 A. Ozawa, 07/09/2025, -/Y/N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 M GASKET,S, ORIG: C232, K.
IKEDA, 243-0958
ORDERED FOR KTR
9B 5330 013387835 NA 4 N 50555193 2/EA
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P22114 KEY OP: A12