3819P22115A02_c1v1_FY26_TGI.pdf

PDF 75 KB Posted

Attached to
USS BLUE RIDGE 5C1 DSRA TYCOM 7 (YOKOSUKA, JAPAN)
Solicitation number
N6264925RA059-0008
Issued by

About this file

This Task Group Instruction (TGI) details maintenance procedures for the USS Blue Ridge's 1B Boiler Forced Draft Blower (FDB) Shutters. The document specifies cleaning and adjustment work for two FDB shutters manufactured by Bath Iron Works Corporation, each measuring 23.25-inches long by 30.00-inches wide. The maintenance is scheduled for contractor work between 7/21/2026 and 11/21/2027, with the task originating from a Boiler Inspection and Repair Management Information System (BIRMIS) report dated 17 OCT 2024.

The procedure involves disconnecting and reconnecting spring hanger assemblies, removing and reinstalling FDB shutters, cleaning components, and performing adjustments per specified assembly and balancing procedures. SRF-JRMC will provide government-furnished materials and support services, including crane and rigging, utility services, safety inspections, and quality assurance inspections. The work requires multiple trades, including boiler room hours, welding, painting, and installation personnel. Potential hazards include asbestos and lead, and the material list includes items such as silicone grease, insulation sleeves, packing, adhesives, and insulation cement.

View the file

Other files

File Type Posted
N6264925RA059-0009.pdf PDF
3819P43701T01_c0v0_TGI.pdf PDF
3819P25001T02_c0v0_TGI.pdf PDF
TGI_3819P22115T02_c0v0.pdf PDF
TGI_3819P22114T05_c0v0.pdf PDF
TGI_3819P22114T03_c0v0.pdf PDF
TGI_3819P123AGT12_c0v0.pdf PDF
TGI_3819P123AGT04_c0v0.pdf PDF
TGI_3819P123AGT02_c0v0_TT_rev.pdf PDF
Attachment VII Warranty Tracking Information.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL)_R1.pdf PDF
3819P25514A01_c0v0_FY26_TGI.pdf PDF
3819P25001A01_c1v0_FY26_TGI.pdf PDF
3819P22124A01_c0v0_FY26_TGI.pdf PDF
3819P22115A11_c0v0_FY26_TGI.pdf PDF
3819P22115A10_c0v0_FY26_TGI.pdf PDF
3819P22115A08_c0v0_FY26_TGI.pdf PDF
3819P22114A15_c0v0_FY26_TGI.pdf PDF
3819P22114A11_c1v2_FY26_TGI.pdf PDF
3819P22114A05_c0v0_FY26_TGI.pdf PDF
3819P22114A04_c1v1_FY26_TGI.pdf PDF
3819P22114A02_c0v0_FY26_TGI.pdf PDF
3819P22114A01_c0v0_FY26_TGI.pdf PDF
N6264925RA059-0002.pdf PDF
N6264925RA059-0001.pdf PDF
3819P25001T04_c0v0_TGI.pdf PDF
3819P25001T01_c0v0_TGI.pdf PDF
TGI_3819P22115T01_c0v0.pdf PDF
TGI_3819P22114T06_c0v0.pdf PDF
TGI_3819P123AGT11_c0v0.pdf PDF
TGI_3819P123AGT01_c0v0.pdf PDF
Attachment VI Quality Assurance Surveillance Plan (QASP).pdf PDF
Attachment V Contract Data Sheet.pdf PDF
3819P65416A01_c1v2_FY26_TGI.pdf PDF
3819P26001A01_c0v0_FY26_TGI.pdf PDF
3819P25201A01_c0v0_FY26_TGI.pdf PDF
3819P22115A12_c0v0_FY26_TGI.pdf PDF
3819P22115A06_c0v0_FY26_TGI.pdf PDF
3819P22115A05_c0v0_FY26_TGI.pdf PDF
3819P22115A01_c1v1_FY26_TGI.pdf PDF
3819P22114A17_c0v0_FY26_TGI.pdf PDF
3819P22114A13_c0v1_FY26_TGI.pdf PDF
3819P22114A12_c0v1_FY26_TGI.pdf PDF
3819P22114A10_c0v0_FY26_TGI.pdf PDF
N6264925RA059-0003.pdf PDF
3819P43701T02_c0v0_TGI.pdf PDF
3819P25606T01_c0v0_TGI.pdf PDF
3819P25001T03_c0v0_TGI.pdf PDF
TGI_3819P22115T05_c0v0.pdf PDF
TGI_3819P22114T04_c0v0.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

05-MAR-2025 1329

20.14.15.2.9020 (September 2024) ICN: 3819P22115 KeyOp: A02

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1B BLR FDB SHTR AY A 0 1/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *(D71-01) F/O - CLEAN AND ADJUST EACH 1B BOILER FORCED DRAFT BLOWER SHUTTER

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 5

EM02L192

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

NAKAMURA, KOUKI 232 3152430090 21-FEB-2025

APPROVED BY: CODE: PHONE: DATE:

KINOSHITA, TAKAHIRO 232 3152432491 05-MAR-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EM02-L192

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

221A1115

1. SCOPE/PURPOSE:

1.1 Title: Each 1B Boiler Forced Draft Blower (FDB) Shutter; clean and adjust

1.2 Location of Work:

1.2.1 Fire Room (8-76-0-E)

1.3 Identification:

1.3.1 Quantity (One EA), 1B Boiler 1B1 FDB Shutter

Mfr: Bath Iron Works Corporation Specification: MIL-S-18525 or Equal Size: 23.25-Inch LG X 30.00-Inch WD

APL: 400270037

1.3.2 Quantity (One EA), 1B Boiler 1B2 FDB Shutter

TGI Short Form

05-MAR-2025 1329

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22115 KeyOp: A02

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1B BLR FDB SHTR AY A 0 1/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *(D71-01) F/O - CLEAN AND ADJUST EACH 1B BOILER FORCED DRAFT BLOWER SHUTTER

FOUO Pg 2 of 5

CU PHASE DESCRIPTION (Cont.)

Mfr: Bath Iron Works Corporation Specification: MIL-S-18525 or Equal Size: 23.25-Inch LG X 30.00-Inch WD

APL: 400270037

1.3.3 Quantity (One AY), Spring Hanger Assembly for FDB Duct

Hanger No.: F-S-2 Remarks: See Sheet 3 (KEY PLAN-PORT SIDE) and Sheet 5 of Ref. No. 3 for details.

1.4 Security Classification: None.

1.5 Initial Condition:

1.5.1 Potential Asbestos Hazard.

1.5.2 Potential Lead Hazard.

1.6 Contractor work start date: 7/21/2026

1.7 Contractor work completion date: 11/21/2027

2. PROCEDURE:

2.1 Disconnect mechanically and reconnect each spring hanger assembly listed in 1.3.3 for supporting clean and adjustment of FDB shutter, using Ref. No. 3 for guidance.

2.2 Remove each FDB shutter listed in 1.3.1 and 1.3.2, using Ref. No. 4 and Ref. No. 5 for guidance.

2.3 Adjust each FDB shutter listed in 1.3.1 and 1.3.2 in accordance with ASSEMBLY AND BALANCING PRECEDURE of Ref.

No. 6.

2.3.1 Disassemble and assemble each FDB shutter in accordance with Ref. No. 6 and Ref. No. 7.

2.3.2 Clean each exposed part free of foreign matter, leaving no residue or injurious effects.

2.4 Install each FDB shutter listed in 1.3.1 and 1.3.2, using Ref. No. 4 and Ref. No. 5 for guidance.

2.4.1 Remove existing and install new gasket, conforming to HH-P-31.

2.5 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.

2.6 Notes:

2.6.1 Planner: Code 232 K. Nakamura, 070-7787-1977

Planner: Code 234 H. Takemoto, 070-7787-2055 Planner: Code 234 D. Ogawa, 080-9345-4110

2.6.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

05-MAR-2025 1329

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22115 KeyOp: A02

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1B BLR FDB SHTR AY A 0 1/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *(D71-01) F/O - CLEAN AND ADJUST EACH 1B BOILER FORCED DRAFT BLOWER SHUTTER

FOUO Pg 3 of 5

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

2.6.3 This TGI is response to Boiler Inspection and Repair Management Information System (BIRMIS) for 1B Boiler report dated 17 OCT 2024, Line item D71-01.

2.6.4 JCN EM02-L192 is related to this TGI.

2.7 SRF-JRMC will provide GFM listed in the Material List.

2.8 SRF-JRMC will provide the following service work: (TGI No. 3819P22115S03)

2.8.1 [C740] Crane and crane rigging service.

2.8.2 [X99E] Utility service, electrical.

2.8.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.8.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.8.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.8.6 [C133] QA inspection for (G) Symbol(s).

05-MAR-2025 1329

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22115 KeyOp: A02

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1B BLR FDB SHTR AY A 0 1/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *(D71-01) F/O - CLEAN AND ADJUST EACH 1B BOILER FORCED DRAFT BLOWER SHUTTER

FOUO Pg 4 of 5

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N 3 DWG 204-2492048 FDB Ducts, LWR Uptakes, Smoke IND & Trash BNR Piping - Supports

C Y 3,5

4 DWG 204-2492045 Forced Draft System - DIAG E N 5 DWG 204-2492046 F.D Blower Ducts - DETS C N 6 DWG 204-2492754 30" W. x 23 1/4 H. Auto SHTRS for FDB, ASSY

A Y ALL

7 DWG 204-2492756 30" W. x 23 1/4" H. Auto SHTRS for FDB, DET & L/M

B Y ALL

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

2.1 BLRM HRs, RGRS HRs 22/KE PC N

2.2 BLRM HRs, INSL HRs, RGRS HRs 22/KE PC N

2.3 IMCH HRs 22/KE PC N

2.4 BLRM HRs, WELD HRs, QA HRs, INSL HRs, PNTR HRs, RGRS HRs

22/KE PC N

2.5 PNTR HRs, QA HRs 22/KE PC N

Machinery Work CFM for Misc (plastic sheets/bags and other consumable).

22/MQ CS N

Boiler Work CFM for paint and other consumable. 22/MQ CS N

Lagging Work CFM for asbestos sampler and analysis cost, paints, covering material, and MISC such as other consumable material.

22/MQ CS N

Process Funding Document. 10/CT OM N

Version-01: Revise Paragraph 1.3.3.

Code 232 T. Kinoshita, 03/05/2025, -/-/N

/ V-01 N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

001 M GREASE,SILICONE INS, ORIG:

C232 K. NAKAMURA, 070-7787-

ORDERED FOR KTR

MIL-L-15719

9B HOLD 010809652 NA 4 Y 50385039 2/CA

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P22115 KEY OP: A02

05-MAR-2025 1329

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22115 KeyOp: A02

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1B BLR FDB SHTR AY A 0 1/1

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *(D71-01) F/O - CLEAN AND ADJUST EACH 1B BOILER FORCED DRAFT BLOWER SHUTTER

FOUO Pg 5 of 5

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

400 M INSULATION SLEEVING,

ORDERED FOR KTR

C234 H.TAKEMOTO 243-4479

9Q 5640 005513476 NA 4 N 50625109 3/EA

400 M INSULATION SLEEVING,

ORDERED FOR KTR

C234 H.TAKEMOTO 243-4479

9Q 5640 005513476 NA 4 N 50425008 2/EA

401 M PACKING, C-234 H.TAKEMOTO

243-4479

ORDERED FOR KTR

WE REQUIRED 1 LENGTH (100

FT)

9B 5330 012100534 NA 4 N 50425087 100/FT

402 M ADHESIVE, ORDERED FOR

KTR

C234 H.TAKEMOTO 243-4479

9B 8040 002738708 NA 4 Y 50425134 1/GL

403 M INSULATION SLEEVING,

SILICA PIPE COVER, 4"IPS X

3-1/2"THK X 3 FT LONG PER

EACH,

C234 H.TAKEMOTO 243-4479

ORDERED FOR KTR

9Q 5640 002012583 NA 4 N 50425007 4/EA

404 M CLOTH,PLAIN WEAVE, H/W

GLASS CLOTH, COLOR IS

NATURAL

ORDERED FOR KTR

C234 H.TAKEMOTO 243-4479

9B 8305 001487364 NA 4 N 50425105 1/RO

405 M CEMENT,INSULATION,H, C234

H.TAKMEOTO 243-4479

ORDERED FOR KTR

9Q 5640 002264540 NA 4 Y 50425014 1/BG

File details come from the government source that posted it. Updated .