3819P22114A06_c1v1_FY26_TGI.pdf
PDF 107 KB Posted
- Solicitation number
- N6264925RA059-0008
About this file
This Task Group Instruction (TGI) details maintenance work for the USS Blue Ridge's 1A Boiler Forced Draft Blower (FDB) Shutters. The document specifies cleaning and adjusting two FDB shutters manufactured by Bath Iron Works Corporation, each measuring 23.25-Inch LG X 30.00-Inch WD and conforming to MIL-S-18525 specifications. The work is scheduled for contractor execution from July 21, 2026 to November 21, 2027, in response to a Boiler Inspection and Repair Management Information System (BIRMIS) report dated October 17, 2024.
The maintenance procedure involves disconnecting and reconnecting spring hanger assemblies, removing and reinstalling FDB shutters, cleaning exposed parts, and installing new gaskets. SRF-JRMC will provide government-furnished materials and supporting services including crane and rigging, utility services (electrical, air, water, steam), and safety and quality assurance inspections. The task requires multiple work groups including boiler room, welding, painting, and insulation personnel, with potential asbestos and lead hazards noted. The material list includes items such as silicone grease, packing, adhesive, insulation sleeves, and cement.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
05-MAR-2025 1104
20.14.15.2.9020 (September 2024) ICN: 3819P22114 KeyOp: A06
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1A BLR FDB SHTR AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *(D71-01) F/O - CLEAN AND ADJUST EACH 1A BOILER FORCED DRAFT BLOWER SHUTTER
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 5
EM02L194
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
NAKAMURA, KOUKI 232 3152430090 21-FEB-2025
APPROVED BY: CODE: PHONE: DATE:
KINOSHITA, TAKAHIRO 232 3152432491 05-MAR-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EM02-L194
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
221A1114
1. SCOPE/PURPOSE:
1.1 Title: Each 1A Boiler Forced Draft Blower (FDB) Shutter; clean and adjust
1.2 Location of Work:
1.2.1 Fire Room (8-76-0-E)
1.3 Identification:
1.3.1 Quantity (One EA), 1A Boiler 1A1 FDB Shutter
Mfr: Bath Iron Works Corporation Specification: MIL-S-18525 or Equal Size: 23.25-Inch LG X 30.00-Inch WD
APL: 400270037
1.3.2 Quantity (One EA), 1A Boiler 1A2 FDB Shutter
TGI Short Form
05-MAR-2025 1104
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A06
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1A BLR FDB SHTR AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *(D71-01) F/O - CLEAN AND ADJUST EACH 1A BOILER FORCED DRAFT BLOWER SHUTTER
FOUO Pg 2 of 5
CU PHASE DESCRIPTION (Cont.)
Mfr: Bath Iron Works Corporation Specification: MIL-S-18525 or Equal Size: 23.25-Inch LG X 30.00-Inch WD
APL: 400270037
1.3.3 Quantity (One AY), Spring Hanger Assembly for FDB Duct
Hanger Ident No.: F-S-1 Remarks: See Sheet 3 (KEY PLAN-STBD SIDE) and Sheet 6 of Ref. No. 3 for details.
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Asbestos Hazard.
1.5.2 Potential Lead Hazard.
1.6 Contractor work start date: 7/21/2026
1.7 Contractor work completion date: 11/21/2027
2. PROCEDURE:
2.1 Disconnect mechanically and reconnect each spring hanger assembly listed in 1.3.3 for supporting clean and adjustment of FDB shutter, using Ref. No. 3 for guidance.
2.2 Remove each FDB shutter listed in 1.3.1 and 1.3.2, using Ref. No. 4 and Ref. No. 5 for guidance.
2.3 Adjust each FDB shutter listed in 1.3.1 and 1.3.2 in accordance with ASSEMBLY AND BALANCING PRECEDURE of Ref.
No. 6.
2.3.1 Disassemble and assemble each FDB shutter in accordance with Ref. No. 6 and Ref. No. 7.
2.3.2 Clean each exposed part free of foreign matter, leaving no residue or injurious effects.
2.4 Install each FDB shutter listed in 1.3.1 and 1.3.2, using Ref. No. 4 and Ref. No. 5 for guidance.
2.4.1 Remove existing and install new gasket, conforming to HH-P-31.
2.5 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.
2.6 Notes:
2.6.1 Planner: Code 232 K. Nakamura, 070-7787-1977
Planner: Code 234 H. Takemoto, 070-7787-2055 Planner: Code 234 D. Ogawa, 080-9345-4110
2.6.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
05-MAR-2025 1104
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A06
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1A BLR FDB SHTR AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *(D71-01) F/O - CLEAN AND ADJUST EACH 1A BOILER FORCED DRAFT BLOWER SHUTTER
FOUO Pg 3 of 5
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
2.6.3 This TGI is response to Boiler Inspection and Repair Management Information System (BIRMIS) for 1A Boiler report dated 17 OCT 2024, Line item D71-01.
2.6.4 JCN EM02-L194 is related to this TGI.
2.7 SRF-JRMC will provide GFM listed in the Material List.
2.8 SRF-JRMC will provide the following service work: (TGI No. 3819P22114S07)
2.8.1 [C740] Crane and crane rigging service.
2.8.2 [X99E] Utility service, electrical.
2.8.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.8.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.8.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.8.6 [C133] QA inspection for (G) Symbol(s).
05-MAR-2025 1104
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A06
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1A BLR FDB SHTR AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *(D71-01) F/O - CLEAN AND ADJUST EACH 1A BOILER FORCED DRAFT BLOWER SHUTTER
FOUO Pg 4 of 5
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N 3 DWG 204-2492048 FDB Ducts, LWR Uptakes, Smoke IND & Trash BNR Piping - Supports
C Y 3,6
4 DWG 204-2492045 Forced Draft System - DIAG E N 5 DWG 204-2492046 F.D Blower Ducts - DETS C N 6 DWG 204-2492754 30" W. x 23 1/4 H. Auto SHTRS for FDB, ASSY
A Y ALL
7 DWG 204-2492756 30" W. x 23 1/4" H. Auto SHTRS for FDB, DET & L/M
B Y ALL
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 BLRM HRs, RGRS HRs 22/KE PC N
2.2 BLRM HRs, INSL HRs, RGRS HRs 22/KE PC N
2.3 IMCH HRs 22/KE PC N
2.4 BLRM HRs, WELD HRs, QA HRs, INSL HRs, PNTR HRs, RGRS HRs
22/KE PC N
2.5 PNTR HRs, QA HRs 22/KE PC N
Machinery Work CFM for Misc (plastic sheets/bags and other consumable).
22/MQ CS N
Boiler Work CFM for paint and other consumable. 22/MQ CS N
Lagging Work CFM for asbestos sampler and analysis cost, paints, covering material, and MISC such as other consumable material.
22/MQ CS N
Process Funding Document. 10/CT OM N
Version-01: Revise Paragraph 1.3.3.
Code 232 T. Kinoshita, 03/05/2025, -/-/N
/ V-01 N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 M GREASE,SILICONE INS, ORIG:
C232 K. NAKAMURA, 070-7787-
ORDERED FOR KTR
MIL-L-15719
9B HOLD 010809652 NA 4 Y 50385041 2/CA
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P22114 KEY OP: A06
05-MAR-2025 1104
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A06
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1A BLR FDB SHTR AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *(D71-01) F/O - CLEAN AND ADJUST EACH 1A BOILER FORCED DRAFT BLOWER SHUTTER
FOUO Pg 5 of 5
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
400 M PACKING, C-234 H.TAKEMOTO
243-4479
ORDERED FOR KTR
WE REQUIRED 1 LENGTH (100
FT)
9B 5330 012100534 NA 4 N 50425089 100/FT
403 M ADHESIVE, ORDERED FOR
KTR
C234 H.TAKEMOTO 243-4479
9B 8040 002738708 NA 4 Y 50425135 1/GL
404 M INSULATION SLEEVING,
SILICA PIPE COVER, 4"IPS X
3-1/2"THK X 3 FT LONG PER
EACH,
C234 H.TAKEMOTO 243-4479
ORDERED FOR KTR
9Q 5640 002012583 NA 4 N 50425010 4/EA
405 M CLOTH,PLAIN WEAVE, H/W
GLASS CLOTH, COLOR IS
NATURAL
ORDERED FOR KTR
C234 H.TAKEMOTO 243-4479
9B 8305 001487364 NA 4 N 50425107 1/RO
406 M CEMENT,INSULATION,H, C234
H.TAKMEOTO 243-4479
ORDERED FOR KTR
9Q 5640 002264540 NA 4 Y 50425013 1/BG
407 M INSULATION SLEEVING,
ORDERED FOR KTR
C234 H.TAKEMOTO 243-4479
9Q 5640 005513476 NA 4 N 50625108 3/EA
407 M INSULATION SLEEVING,
ORDERED FOR KTR
C234 H.TAKEMOTO 243-4479
9Q 5640 005513476 NA 4 N 50425009 2/EA
File details come from the government source that posted it. Updated .