TGI_3819P22114T01_c0v0.pdf
PDF 24 KB Posted
- Solicitation number
- N6264925RA059-0008
About this file
This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge, dated 01-MAY-2025, focusing on the Auxiliary Steam System Tightness and Operational Test. The TGI is specifically for component 53411-3-300KTR, with project number 19P and system 53411. The task involves three primary work categories: (V) Contractor work, (G) Quality Assurance work, and (S) Ship/Force work, all of which are required to accomplish and document the tightness and operational test in accordance with the reference technical procedure TP 53411-3-300KTR. The document includes preparation details by Nishimura Kazuhiro and approval by Ohta Jason Y., with Takahashi Yasuhiko listed as the Zone Manager, and the work is to be conducted in various compartments.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
01-MAY-2025 0848
20.14.15.2.9020 (September 2024) ICN: 3819P22114 KeyOp: T01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 53411-3-300KTR TT T 3 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 53411
CU PHASE TITLE: AUX STEAM SYS (T & OP) - KTR
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 2
EM02L194
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
NISHIMURA, KAZUHIRO 246.2 3152433479 17-APR-2025
APPROVED BY: CODE: PHONE: DATE:
OHTA, JASON Y. 246.2 3152435901 29-APR-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EM02-L194
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
TAKAHASHI, YASUHIKO VARIOUS U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
221A1114
Tightness & Operational Test for Aux Steam System - KTR.
TGI Short Form
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
01-MAY-2025 0848
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: T01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 53411-3-300KTR TT T 3 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 53411
CU PHASE TITLE: AUX STEAM SYS (T & OP) - KTR
FOUO Pg 2 of 2
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 TP 53411-3-300KTR AUX STEAM SYS (T & OP) -
KTR
LAT Y
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
(V) Contractor work:
Accomplish/document the tightness & operational test in accordance with reference, TP 53411-3-300KTR.
22/KE PC N
(G) QA work:
Accomplish/document the tightness & operational test in accordance with reference, TP 53411-3-300KTR.
33/G1 QA N
(S) S/F work:
Accomplish/document the tightness & operational test in accordance with reference, TP 53411-3-300KTR.
/ EM02 N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P22114 KEY OP: T01
File details come from the government source that posted it. Updated .