This Task Group Instruction (TGI) details an electrical installation task for the USS Blue Ridge, specifically the installation of a Main Engine Lube Oil Temperature Switch. The project is scheduled to begin on 7/21/2026 and complete by 11/21/2027, located in the Engine Room. SRF-JRMC will provide government-furnished materials and services including crane rigging, utility services (electrical, air, water, steam), and quality assurance inspections.

The material list includes 14 specific components to be ordered, such as a blank panel, junction box cover, terminal board, toggle switch, various screws, nuts, washers, O-rings, and a power cable. The work will involve multiple technical specialties including electrical, structural, painting, and welding, with tasks focused on electrical modifications, surface preparation, and switch installation. The task is identified with TGI No. SA88717D and has a potential lead hazard noted in the documentation.

View the file

Other files

File Type Posted
N6264925RA059-0009.pdf PDF
3819P43701T01_c0v0_TGI.pdf PDF
3819P25001T02_c0v0_TGI.pdf PDF
TGI_3819P22115T02_c0v0.pdf PDF
TGI_3819P22114T05_c0v0.pdf PDF
TGI_3819P22114T03_c0v0.pdf PDF
TGI_3819P123AGT12_c0v0.pdf PDF
TGI_3819P123AGT04_c0v0.pdf PDF
TGI_3819P123AGT02_c0v0_TT_rev.pdf PDF
Attachment VII Warranty Tracking Information.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL)_R1.pdf PDF
3819P25514A01_c0v0_FY26_TGI.pdf PDF
3819P25001A01_c1v0_FY26_TGI.pdf PDF
3819P22124A01_c0v0_FY26_TGI.pdf PDF
3819P22115A11_c0v0_FY26_TGI.pdf PDF
3819P22115A10_c0v0_FY26_TGI.pdf PDF
3819P22115A08_c0v0_FY26_TGI.pdf PDF
3819P22115A02_c1v1_FY26_TGI.pdf PDF
3819P22114A15_c0v0_FY26_TGI.pdf PDF
3819P22114A11_c1v2_FY26_TGI.pdf PDF
3819P22114A05_c0v0_FY26_TGI.pdf PDF
3819P22114A04_c1v1_FY26_TGI.pdf PDF
3819P22114A02_c0v0_FY26_TGI.pdf PDF
3819P22114A01_c0v0_FY26_TGI.pdf PDF
N6264925RA059-0002.pdf PDF
N6264925RA059-0001.pdf PDF
3819P25001T04_c0v0_TGI.pdf PDF
3819P25001T01_c0v0_TGI.pdf PDF
TGI_3819P22115T01_c0v0.pdf PDF
TGI_3819P22114T06_c0v0.pdf PDF
TGI_3819P123AGT11_c0v0.pdf PDF
TGI_3819P123AGT01_c0v0.pdf PDF
Attachment VI Quality Assurance Surveillance Plan (QASP).pdf PDF
Attachment V Contract Data Sheet.pdf PDF
3819P65416A01_c1v2_FY26_TGI.pdf PDF
3819P25201A01_c0v0_FY26_TGI.pdf PDF
3819P22115A12_c0v0_FY26_TGI.pdf PDF
3819P22115A06_c0v0_FY26_TGI.pdf PDF
3819P22115A05_c0v0_FY26_TGI.pdf PDF
3819P22115A01_c1v1_FY26_TGI.pdf PDF
3819P22114A17_c0v0_FY26_TGI.pdf PDF
3819P22114A13_c0v1_FY26_TGI.pdf PDF
3819P22114A12_c0v1_FY26_TGI.pdf PDF
3819P22114A10_c0v0_FY26_TGI.pdf PDF
2.01 N6264925RA059.pdf PDF
N6264925RA059-0008.pdf PDF
N6264925RA059-0007.pdf PDF
N6264925RA059-0006.pdf PDF
N6264925RA059-0005.pdf PDF
N6264925RA059-0004.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

18-MAR-2025 1305

20.14.15.2.9020 (September 2024) ICN: 3819P26001 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SA88717D ELEC INST AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *F/O - S/A 88717D, ACCOMPLISH MAIN ENGINE LUBE OIL TEMP SWITCH INSTALLATION

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 5

EXSAZBG2

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

SASANO, HIROAKI 233 8093501453 18-MAR-2025

APPROVED BY: CODE: PHONE: DATE:

HOSONO, MASAHIRO 233 8093501455 18-MAR-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EXSA-ZBG2

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

260A0001

1. SCOPE/PURPOSE:

1.1 Title: S/A 88717D, Installation of Main Engine Lube Oil Temperature Switch; accomplish

1.2 Location of Work:

1.2.1 Engine Room (8-86-0-E)

1.3 Identification:

1.3.1 Quantity (One EA), Power System

Remarks: See 2.3 for details.

1.4 Security Classification: None.

1.5 Initial Condition:

TGI Short Form

18-MAR-2025 1305

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P26001 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SA88717D ELEC INST AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *F/O - S/A 88717D, ACCOMPLISH MAIN ENGINE LUBE OIL TEMP SWITCH INSTALLATION

FOUO Pg 2 of 5

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1.5.1 Potential Lead Hazard.

1.6 Contractor work start date: 7/21/2026

1.7 Contractor work completion date: 11/21/2027

2. PROCEDURES:

2.1 Pump out, clean and dry the bilge area located in 1.2.1 free from oil, debris, and other foreign matter.

2.2 Accomplish electrical modifications and installations of the system listed in 1.3.1 in accordance with Ref. No. 3 through Ref.

No. 5.

2.2.1 Accomplish the requirements of 009-12 of Ref. No. One, including Table 2, Column(s) A, Lines One through 7.

2.3 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.

2.4 Notes.

2.4.1 Planner: Code 233 H. Sasano, 080-9350-1453

Planner: Code 231B T. Ando, 243-4372

2.4.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.4.3 Provision of oily/chemical water barge will be coordinated by Project Team.

2.4.4 JCN EXSA-ZBG2 is related to this TGI.

2.5 Government Furnished Material (GFM):

2.5.1 SRF-JRMC will provide GFM listed in the Material List.

2.6 SRF-JRMC will provide the following service work: (TGI No. 3819P26001S02)

2.6.1 [C740] Crane and crane rigging service.

2.6.2 [X99E] Utility service, electrical.

2.6.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.6.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.6.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.6.6 [C133] QA inspection for (G) symbol(s).

18-MAR-2025 1305

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P26001 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SA88717D ELEC INST AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *F/O - S/A 88717D, ACCOMPLISH MAIN ENGINE LUBE OIL TEMP SWITCH INSTALLATION

FOUO Pg 3 of 5

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY25 Standard Items - ORG N 2 LI FY25 Local Standard Items - ORG N 3 DWG 302-8683951 SCD 18717 Power System

Modifications Main Engine Lube Oil Temperature Switch Ins

A Y ALL

4 PDD 302-ELM-

250205

SUPPL INFO FOR SCD 18717

PWR SYS MODIFICATION

- Y ALL

5 LAR SRFY-0072-25 LOCATION ADJUSTMENT OF

THE NEW MELOT BIASING

SWITCH ENCLOSURE

- Y ALL

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

2.1 SFTR HRs, LBR HRs 22/KE PC N

2.2 ELEC HRs, SFTR HRs, WELD HRs, RGRS HRs PNTR HRs, QA HRs

22/KE PC N

2.3 PNTR HRs, QA HRs 22/KE PC N

Structure Work CFM for all paints, thinner, marine chemist, lead analysis cost, firewatch cost, fastener and misc such as electrode, temporary covering material, and other consumable.

22/MQ CS N

Electrical Work CFM for misc. 22/MQ CS N

Process Funding Document. 10/CT OM N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

001 1 1 M PANEL,BLANK, ORDER FOR

KTR

ORIG: C226 T. KATSUYA, 070-

7787-1996

9B 5975 009883493 NA 4 N 50445005 1/EA

002 2 1 M COVER,JUNCTION BOX,

ORDER FOR KTR

ORIG: C226 T. KATSUYA, 070-

7787-1996

9B 5975 015700822 NA 4 N 50445011 1/EA

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

1 302-8683951

ICN: 3819P26001 KEY OP: A01

18-MAR-2025 1305

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P26001 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SA88717D ELEC INST AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *F/O - S/A 88717D, ACCOMPLISH MAIN ENGINE LUBE OIL TEMP SWITCH INSTALLATION

FOUO Pg 4 of 5

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

003 3 1 M TERMINAL BOARD, TERMINAL

BOARD, MOUNTING HOLE

DIAMETER 0.175 INCHES,

DIELECTRIC WITHSTANDING

VOLTAGE IN VOLTS 1100.0,

BODY STYLE BARRIER TYPE,

TERMINAL ROW QUANTITY 2,

CENTER TO CENTER

DISTANCE BETWEEN

TERMINALS 0.438 INCHES,

DISTANCE BETWEEN

TERMINAL ROW CENTERS

0.422 INCHES, BOARD

CONSTRUCTION SOLID

CONSTRUCTION,

9B 5940 LL9307601 NA 4 N 50447504 1/EA

004 4 1 M SWITCH,TOGGLE, ORDER FOR

KTR

ORIG: C226 T. KATSUYA, 070-

7787-1996

9B 5930 008786734 NA 4 N 50445012 1/EA

005 6 1 M STUFFING, ORDER FOR KTR

ORIG: C226 T. KATSUYA, 070-

7787-1996

9B 5975 002964092 NA 4 N 50445021 1/EA

006 7 1 M PACKING ASSEMBLY, ORDER

FOR KTR

ORIG: C226 T. KATSUYA, 070-

7787-1996

9B 5330 002022580 NA 4 N 50445013 1/EA

007 8 1 M O-RING, ORDER FOR KTR

ORIG: C226 T. KATSUYA, 070-

7787-1996

9B 5331 001668403 NA 4 N 50445023 1/EA

008 9 1 M SCREW, HEX, CAP, 1/4,

SCREW, HEX, CAP,

SIZE: 1/4"-20 UNC-2A X 1"LG,

MATL: CRES 304 COLD

WORKED,

MIL-DTL-1222 TYPE I

ORDER FOR KTR

ORIG: C226 T. KATSUYA, 070-

7787-1996

9B 5305 LL9307612 NA 4 N 50447505 4/EA

009 10 1 M WASHER,F, ORDER FOR KTR

ORIG: C226 T. KATSUYA, 070-

7787-1996

9B 5310 005505054 NA 4 N 50445024 1/HD

010 11 1 M NUT,1/4"-20UNC-2B, 3, NUT,

HEX,

SIZE: 1/4-20 UNC-2B,

CRES GR-304 ANNEALED,

MIL-DTL-1222 TYPE-I

ORDER FOR KTR

ORIG: C226 T. KATSUYA, 070-

7787-199

9B 5310 LL9307600 NA 4 N 50447506 4/EA

011 12 1 M TERMINAL,LUG, ORDER FOR

KTR

ORIG: C226 T. KATSUYA, 070-

7787-1996

9B 5940 008130698 NA 4 N 50445014 1/HD

18-MAR-2025 1305

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P26001 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SA88717D ELEC INST AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE: *F/O - S/A 88717D, ACCOMPLISH MAIN ENGINE LUBE OIL TEMP SWITCH INSTALLATION

FOUO Pg 5 of 5

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

012 14 1 M CABLE,POWER,ELECTRI,

ORDER FOR KTR

ORIG: C226 T. KATSUYA, 070-

7787-1996

9B 6145 012027769 NA 4 N 50445016 30/FT

013 5 1 M BOOT,DUST AND MOIST,

ORDER FOR KTR

ORIG: C226 T. KATSUYA, 070-

7787-1996

9B 5930 011415368 NA 4 N 50445017 1/EA

014 M STANDOFF, ORDERED FOR

KTR

ORIG: C233 H.SASANO, 080-

9350-1453

9B 5340 002726544 NA 4 N 1/HD