TGI_3819P123AGT10_c0v0.pdf

PDF 24 KB Posted

Attached to
USS BLUE RIDGE 5C1 DSRA TYCOM 7 (YOKOSUKA, JAPAN)
Solicitation number
N6264925RA059-0008
Issued by

About this file

This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge (LCC-19), dated 02-MAY-2025, focusing on a Low Pressure Air Tightness and Operational Test for a Contractor (KTR). The specific task (JCN: EM01-L261) involves three work segments: (1) Contractor work to accomplish and document the tightness & operational test, (2) Quality Assurance (QA) work to document the test, and (3) Support/Functional (S/F) work to document the test, all referencing technical procedure TP 55121-3-300KTR for Low and Medium Pressure Air testing. The document is marked FOUO (For Official Use Only) and includes administrative details such as preparation by Harada Kazuya and approval by Ohta Jason Y. on 22-APR-2025 and 02-MAY-2025 respectively, with a zone manager of Yaginuma Takehide.

View the file

Other files

File Type Posted
N6264925RA059-0009.pdf PDF
N6264925RA059-0002.pdf PDF
N6264925RA059-0001.pdf PDF
3819P25001T04_c0v0_TGI.pdf PDF
3819P25001T01_c0v0_TGI.pdf PDF
TGI_3819P22115T01_c0v0.pdf PDF
TGI_3819P22114T06_c0v0.pdf PDF
TGI_3819P123AGT11_c0v0.pdf PDF
TGI_3819P123AGT01_c0v0.pdf PDF
Attachment VI Quality Assurance Surveillance Plan (QASP).pdf PDF
Attachment V Contract Data Sheet.pdf PDF
3819P65416A01_c1v2_FY26_TGI.pdf PDF
3819P26001A01_c0v0_FY26_TGI.pdf PDF
3819P25201A01_c0v0_FY26_TGI.pdf PDF
3819P22115A12_c0v0_FY26_TGI.pdf PDF
3819P22115A06_c0v0_FY26_TGI.pdf PDF
3819P22115A05_c0v0_FY26_TGI.pdf PDF
3819P22115A01_c1v1_FY26_TGI.pdf PDF
3819P22114A17_c0v0_FY26_TGI.pdf PDF
3819P22114A13_c0v1_FY26_TGI.pdf PDF
3819P22114A12_c0v1_FY26_TGI.pdf PDF
3819P22114A10_c0v0_FY26_TGI.pdf PDF
3819P43701T01_c0v0_TGI.pdf PDF
3819P25001T02_c0v0_TGI.pdf PDF
TGI_3819P22115T02_c0v0.pdf PDF
TGI_3819P22114T05_c0v0.pdf PDF
TGI_3819P22114T03_c0v0.pdf PDF
TGI_3819P123AGT12_c0v0.pdf PDF
TGI_3819P123AGT04_c0v0.pdf PDF
TGI_3819P123AGT02_c0v0_TT_rev.pdf PDF
Attachment VII Warranty Tracking Information.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL)_R1.pdf PDF
3819P25514A01_c0v0_FY26_TGI.pdf PDF
3819P25001A01_c1v0_FY26_TGI.pdf PDF
3819P22124A01_c0v0_FY26_TGI.pdf PDF
3819P22115A11_c0v0_FY26_TGI.pdf PDF
3819P22115A10_c0v0_FY26_TGI.pdf PDF
3819P22115A08_c0v0_FY26_TGI.pdf PDF
3819P22115A02_c1v1_FY26_TGI.pdf PDF
3819P22114A15_c0v0_FY26_TGI.pdf PDF
3819P22114A11_c1v2_FY26_TGI.pdf PDF
3819P22114A05_c0v0_FY26_TGI.pdf PDF
3819P22114A04_c1v1_FY26_TGI.pdf PDF
3819P22114A02_c0v0_FY26_TGI.pdf PDF
3819P22114A01_c0v0_FY26_TGI.pdf PDF
N6264925RA059-0003.pdf PDF
3819P43701T02_c0v0_TGI.pdf PDF
3819P25606T01_c0v0_TGI.pdf PDF
3819P25001T03_c0v0_TGI.pdf PDF
TGI_3819P22115T05_c0v0.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

02-MAY-2025 1705

20.14.15.2.9020 (September 2024) ICN: 3819P123AG KeyOp: T10

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 55121-3-300KTR TT T 8 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 55121

CU PHASE TITLE: LOW PRESSURE AIR (T & OP) - KTR

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 2

EM01L261

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

HARADA, KAZUYA 246.2 3152432048 22-APR-2025

APPROVED BY: CODE: PHONE: DATE:

OHTA, JASON Y. 246.2 3152435901 02-MAY-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EM01-L261

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

123A41AG

Tightness & Operational Test for Low Pressure Air System - KTR.

TGI Short Form

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

02-MAY-2025 1705

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P123AG KeyOp: T10

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 55121-3-300KTR TT T 8 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 55121

CU PHASE TITLE: LOW PRESSURE AIR (T & OP) - KTR

FOUO Pg 2 of 2

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 TP 55121-3-300KTR LOW AND MEDIUM

PRESSURE AIR (T & OP) -

KTR

LAT Y

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

(V) Contractor work:

Accomplish/document the tightness & operational test in accordance with reference, TP 55121-3-300KTR.

22/KE PC N

(G) QA work:

Accomplish/document the tightness & operational test in accordance with reference, TP 55121-3-300KTR.

33/G1 QA N

(S) S/F work:

Accomplish/document the tightness & operational test in accordance with reference, TP 55121-3-300KTR.

/ EM01 N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P123AG KEY OP: T10

File details come from the government source that posted it. Updated .