Project 8_ Attachment 0012 Scopes_07 Apr 2026.pdf
PDF 185 KB Posted
- Solicitation number
- W51EW7-26-R-A007
About this file
This is a Statement of Work (SOW) for the repair and replacement of the overt/covert lighting system at McChord Airfield, located at Joint Base Lewis-McChord (JBLM).
The project scope encompasses replacing the entire failing overt/covert lighting system, the Sequence Flasher Lights (SFL) system, and providing training to JBLM Airfield Lighting technicians. Task 1 requires Logi Track Device Hardware Upgrade for Runways 16/34, specifically 48 Logi Track Remotes (P/N: T6540-03-01-00 CLD, 2XLAMP, ON/OFF PROGR 11768824), with 44 units to be installed and 4 designated as spares. Task 2 involves Sequence Flasher Remote Control Replacement, requiring two Remote Control Units (P/N: 1500867-2-C) for Runways 16 and 34, each containing an IP 66 Enclosure, I/O Unit, Managed Gigabit Ethernet Switch, and Single Mode SFP Module. Additional components include two Single Mode SFP Modules for the Vault for Runway 16/34 SFL communications. Software deliverables include a new Communication Protocol for the SFL interface, database modifications for the new SFL configuration, and factory testing.
The contractor is responsible for performing and recording testing and evaluation results, coordinating commissioning tasks with the manufacturer's representative, supporting and logging all equipment and software updates with manufacturer-specified testing, advising JBLM representatives of any deviations or discrepancies, providing a final trip/maintenance report, organizing and retaining project documentation, and delivering comprehensive training to all JBLM technicians. All work must comply with FAA 150/5340-26(x), Chapter 2 safety protocols.
View the file
Other files
Show 40 more
Latest 50 of 66 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project #8: McChord Runway Lighting Overt/Covert
Project: Repair Assault Overt/Covert Lights, McChord Field
1. Overview
The McChord Airfield overt/covert ligh ng system is currently in a failing state. Scope is to replace the en re overt/covert ligh ng system, replacement of the SFL system, and the training for the JBLM Airfield Ligh ng technicians.
2. Safety
All appropriate safety protocols will be followed, referencing the guidelines in FAA
150/5340-26(x), Chapter 2.
3. Tasks: This project includes two main tasks detailed below.
Task 1: Ligh ng system Replacement.
An example replacement system is detailed below:
Logi Track Device Hardware Upgrade
Runway 16/34:
Forty-eight (48) Logi Track Remotes (P/N: T6540-03-01-00 CLD, 2XLAMP, ON/OFF
PROGR 11768824)
Forty-four (44) to be installed.
Four (4) units designated as spares.
Task 2: Sequence Flasher Remote Control Replacement
An example replacement system is detailed below:
Sequencer Flasher Remote Control Hardware:
Runway 16:
One (1) Remote Control Unit (P/N: 1500867-2-C), which includes:
One (1) IP 66 Enclosure
One (1) I/O Unit
One (1) Managed Gigabit Ethernet Switch
One (1) Single Mode SFP Module
Runway 34:
One (1) Remote Control Unit (P/N: 1500867-2-C), which includes:
One (1) IP 66 Enclosure
One (1) I/O Unit
One (1) Managed Gigabit Ethernet Switch
One (1) Single Mode SFP Module
Vault:
Two (2) Single Mode SFP Modules for Runway 16/34 SFL communica ons.
So ware:
New Communica on Protocol for the new SFL interface.
Database Modifica on for the new SFL configura on.
Factory Test.
4. Maintenance & Service Responsibili es
Perform and record tes ng and evalua on results before services begin.
Coordinate commissioning tasks with the product manufacturer's representa ve, including new enclosure installa on support, new so ware installa on, onsite tes ng, and drawing updates.
Support and log the comple on of all equipment updates, so ware updates, and manufacturer-specified tes ng.
Advise the JBLM representa ves of any devia ons or discrepancies from approved services.
Provide a final trip/maintenance report for review and signature upon service comple on.
Organize, provide, and retain copies of all relevant project documenta on.
Provide training for all JBLM technicians.