Att. AA) B60 AMD 004 Drawings 012726.pdf
PDF 3 MB Posted
- Solicitation number
- N6247026R0012
About this file
This document is a collection of architectural and engineering drawings for Building 60 Repairs at Portsmouth Naval Shipyard in Kittery, Maine, under the Department of the Navy. The project is managed by Naval Facilities Engineering Systems Command (NAVFAC) Mid-Atlantic, with project number 1740579. The drawings include site constraints and requirements plans, foundation part plans, and outage schedules essential for managing construction activities and utility interruptions during the repair work.
The construction project encompasses fire protection system repairs, envelope and exterior restoration, and mechanical, electrical, and plumbing system upgrades. Key constraints include maintaining emergency vehicle access, restricting work within 75 feet of the Piscataqua River's top of bank per National Resource Protection Act regulations, preserving at least five of ten parking spaces adjacent to Building 60 at all times, and maintaining minimum 5-foot-wide pedestrian access routes to building entrances and fire hydrants throughout construction. The outage schedule identifies multiple utility disconnections required across fire protection, water service, steam/hot water, compressed air, electrical power, and telecommunications systems, with maximum permitted durations ranging from 1 hour to 6 months depending on the system and purpose. All outages require contractor submission of detailed outage plans, pre-outage meetings with government representatives, and explicit approval from the Contracting Officer, with Tier 2 outages requiring minimum three-week advance notice. Tier 1 infrastructure work areas include existing water lines and storm drains below the slab, which contractors must protect and avoid disturbance beyond designated work areas.
View the file
Other files
Show 40 more
Latest 50 of 157 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SATISFACTORY TO DATE
APPROVED
FOR COMMANDER NAVFAC
A
B
C
D
1 2 3 4 5
1 2 3 4 5
A
B
C
D
SHEET
NAVFAC DRAWING NO.
DESIGNER
DRAWN BY
CHECKED BY
OF
EPROJECT NO.:
DRAWFORM REVISION: 14 SEP 2023
DESIGN MANAGER
PROJECT MANAGER
FEAD/PM&E
FIRE PROTECTION
B6 0 R
EP
AI
RS
UNCLASSIFIED
UNCLASSIFIED
UN
CL
AS
SI
FI
ED
KI
TT
ER
Y, M E
PO
R
TS
M
O U
TH
N
AV
AL
S H
IP
YA
R D
ACTIVITY
1740579
T. CARLETON
L. LYONS
S. RUCINSKI
SY
S
DE
SC
RI
PT
IO
N
DA
TE
AP
R
N
AV
AL
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
S
YS
TE
M
S C
O M
M
AN
D
NA
VA
L F
AC
ILI
TI
ES
E
NG
IN
EE
RI
NG
S
YS
TE
MS
C
OM
MA
ND
MI
D-
AT
LA
NT
IC
PO
R
TS
M
O U
TH
N
AV
AL
S H
IP
YA
R D
KI
TT
ER
Y, M
E
D
EP
AR
TM
EN
T
O F
TH
E
N
AV
Y
R O
IC
C
-M E
GRAPHIC SCALE
CHECK GRAPHIC SCALE BEFORE USING
60'20' 40'20' 10' 1"=20'
PLAN
NORTH
SITE CONSTRAINTS AND REQUIREMENTS PLAN
ST
O
RE
R
ST
RE
ET
SMOOT STREET
TU
RN
ER
S
TR
EE
T
PISCATAQUA RIVER
BLDG 59
BLDG 43BLDG 65
IR SOIL SITE
IR SOIL SITE
BLDG 60
BLDG 62A
BLDG 62
EEOP
EEOP
EEOP
GENERAL SHEET NOTES (CONTINUED)
6. PROVIDE TEMPORARY TYPE 3 CONSTRUCTION BARRIER (SEE SHEET G-010) AROUND THE PERIMETER
OF THE CONSTRUCTION SITE WHERE WORK IS BEING PERFORMED AND CONTRACTOR STAGING AND STORAGE AREAS. CONTROL ACCESS TO THE CONSTRUCTION SITE VIA OPENINGS IN THE FENCE THAT CAN BE SECURED TO PREVENT ACCESS. COORDINATE THE EXACT LOCATION OF FENCE WITH THE
CONTRACTING OFFICER.
7. CONDUCT AND COMPLETE WORK IN A MANNER THAT MAINTAINS ACCESS FOR EMERGENCY RESPONSE
VEHICLES THROUGHOUT THE CONSTRUCTION PERIOD.
8. CONSTRUCTION EQUIPMENT IS PERMITTED TO TEMPORARILY OCCUPY PORTIONS OF AN EXISTING FIRE
LANE WITH AN APPROVED OUTAGE. BLOCKING OF FIRE LANES IS PROHIBITED WITHOUT PRIOR
APPROVAL. ONLY MOTORIZED EQUIPMENT, STAFFED BY AN ON-SITE OPERATOR, CAN BE UTILIZED IN THE AREA AND MUST BE ABLE TO BE MOVED IMMEDIATELY UPON REQUEST TO ALLOW FOR UNIMPEDED FIRE DEPARTMENT ACCESS. EXECUTION OF CONSTRUCTION SCOPE WITHIN FIRE LANES MUST BE COMPLETED OUTSIDE OF NORMAL WORKING HOURS (WEEKEND OR AFTER 1600). SCHEDULE WILL NEED
TO BE COORDINATED AND APPROVED BY THE CONTRACTING OFFICER.
9. EXCAVATIONS WITHIN VEHICLE TRAVEL WAYS MUST BE COVERED WITH STEEL PLATES WHEN
CONSTRUCTION IS NOT ACTIVE. DESIGN STEEL PLATES TO ACCOMMODATE AASHTO HS-20 TRAFFIC
LOADING.
10. SEE SHEETS G-008 AND G-009 FOR INFORMATION RELATIVE TO OUTAGES.
11. FOR WORK THAT OBSTRUCTS PEDESTRIAN ACCESS TO SURROUNDING BUILDINGS, OBTAIN AN
APPROVED OUTAGE AND PROVIDE ALTERNATE PEDESTRIAN ACCESS ROUTES AROUND THE
CONSTRUCTION AREA THAT MEETS ACCESSIBILITY STANDARDS.
12. WORK ON THE WEST AND SOUTH SIDES OF BUILDING 60 MUST BE SEQUENCED TO MINIMIZE THE
NUMBER OF PARKING SPACES REQUIRING AN OUTAGE AT ANY GIVEN TIME. ROAD OUTAGE WORK
MUST BE SEQUENCED SO THAT 5 OF THE TOTAL 10 PARKING SPACES IMMEDIATELY ADJACENT to BUILDING 60 REMAIN AVAILABLE AND ACCESSIBLE AT ALL TIMES. COORDINATE THE SEQUENCE OF
PARKING OUTAGES AND GAIN APPROVAL FROM THE CONTRACTING OFFICER.
13. WORK AREA ALONG THE NORTH SIDE OF BUILDING 60 IS RESTRICTED BY THE PROXIMITY OF THE PISCATAQUA RIVER. PROVIDE WORK PLAN IDENTIFYING STAGING LAYOUT IN THIS AREA AS WELL AS WORK BEING PERFORMED FROM THE EXTERIOR/INTERIOR OF THE BUILDING. NO WORK IS PERMITTED
BELOW THE TOP OF BANK.
14. SEE SHEET C-001, NOTE 9 FOR TRAFFIC CONTROL PLAN SUBMITTAL REQUIREMENTS.
15. SEE TO SHEETS CG101 AND C-501 FOR EROSION AND SEDIMENT CONTROL REQUIREMENTS. PROVIDE ADDITIONAL EROSION AND SEDIMENT CONTROLS AROUND DOWN GRADIENT SIDE OF THE AVAILABLE
CONTRACTOR STAGING AND STORAGE AREAS.
16. MAINTAIN CLEAR PATHWAY (5' WIDE, MIN) FROM FIRE LANE TO FIRE HYDRANT'S AND PIV'S AT ALL
TIMES.
17. MAINTAIN CLEAR PATHWAY (5' WIDE, MIN) FROM FIRE LANES TO BUILDING 60 AND SURROUNDING
BUILDINGS ACCESS DOORS AT ALL TIMES.
18. SEE SPECIFICATION SECTION 01 14 00.00 22 WORK RESTRICTIONS PWD-ME FOR ADDITIONAL
INFORMATION AND TIER 1 INFRASTRUCTURE REQUIREMENTS.
KEYNOTES(THIS SHEET ONLY)
FIRE LANE - DO NOT STORE MATERIALS WITHIN THIS AREA AND COORDINATE WITH THE CONTRACTING
OFFICER FOR WORK WITHIN THIS AREA. SEE GENERAL NOTE 8.
AREA AVAILABLE FOR CONTRACTOR CONSTRUCTION STAGING AND STORAGE.
MAINTAIN PEDESTRIAN ACCESS ROUTE FREE OF OBSTRUCTIONS (5' WIDE, MIN) FROM BUILDING ACCESS
DOORS TO FIRE LANE AT ALL TIMES.
LIMIT OF PROJECT PAVEMENT REMOVAL. SEE SHEET CR101.
MAINTAIN PEDESTRIAN ACCESS ROUTE FREE OF OBSTRUCTIONS (5' WIDE, MIN) FROM OFFICE TRAILER
TO SMOKE SHELTER AND PARKING AREA.
WORK AREA FOR BUILDING 60 ENVELOPE AND EXTERIOR REPAIRS.
20'
20'
(TYP)
(TYP)
HIGHEST ANNUAL TIDE
(HAT) LINE, ELEV=5.8'
TOP OF SLOPE (SEE
GENERAL SHEET
NOTES 4, 5 AND 13)
100-YEAR FLOOD,
ELEV=9.0'
DAP
DAP
DEW
G-006
BLDG
MAINTAIN PEDESTRIAN AND VEHICULAR ACCESS ROUTE FREE OF OBSTRUCTION TO BUILDING 292
(SANITARY SEWER PUMP STATION) AND THE ADJACENT MANHOLE AT ALL TIMES THROUGHOUT
CONSTRUCTION.
BUILDING OVERHEAD DOOR ACCESS (18' HIGH x 16' WIDE).8
PROJECT SIGNAGE. COORDINATE THE EXACT LOCATION WITH CONTRACTING OFFICER.9
OFFICE
TRAILER 2
CONCRETE
PLANTER/BARRIER, TYP
WYMAN AVENUE
LOAD CENTER
4 VAULT
10 APPROXIMATE CONSTRUCTION AND STAGING AREA FOR ADJACENT CONSTRUCTION PROJECT (NOT IN CONTRACT). SEE GENERAL SHEET NOTE 2. MAINTAIN PEDESTRIAN AND VEHICULAR ACCESS ROUTE
FREE OF OBSTRUCTIONS TO THIS AREA AT ALL TIMES DURING CONSTRUCTION.
GRANITE
BLOCKS, TYP
SMOKING
SHELTER
(TYP)5
30'
LEGEND
PEDESTRIAN ACCESS ROUTE (5' WIDE, MIN)
AREA AVAILABLE FOR CONTRACTOR CONSTRUCTION STAGING
AND STORAGE
FIRE LANE (SEE GENERAL SHEET NOTE 8)
PORTION OF FIRE LANE IMPACTED BY CONSTRUCTION (SEE GENERAL
SHEET NOTE 8)
IR SOIL AREA
BUILDING 60 ENVELOPE AND EXTERIOR REPAIR WORK AREA, AND TEMPORARY
STAGING AND CONTRACTOR STORAGE. CONSTRUCTION FENCE MAXIMUM 10
FEET FROM FACE OF BUILDING WALL, UNLESS INDICATED OTHERWISE
AREA AVAILABLE FOR CONTRACTOR LONG TERM STORAGE
GENERAL SHEET NOTES
1. SEE SHEET C-001 FOR LEGEND AND ABBREVIATIONS.
2. OTHER CONSTRUCTION PROJECTS (NOT IN CONTRACT) IN THE VICINITY OF BUILDING 60 WILL BE
ONGOING CONCURRENTLY WITHIN THE BUILDING 60 CONSTRUCTION PERIOD. COORDINATE WITH
THE CONTRACTING OFFICER TO OBTAIN RECORD DRAWINGS AND CONSTRUCTION SCHEDULES.
3. VEHICLES ARE PERMITTED TO ONLY TEMPORARILY PARK IN THE DESIGNATED CONTRACTOR
CONSTRUCTION STAGING AND STORAGE AREA AND OTHER AREAS APPROVED BY THE
CONTRACTING OFFICER. THE CREW MUST PARK ELSEWHERE.
4. SOIL STOCKPILES ARE ALLOWED ONLY WITHIN THE CONTRACTOR STAGING AND STORAGE AREAS IDENTIFIED ON THIS PLAN. SOIL STOCKPILES MUST BE LOCATED AT LEAST 75 FEET FROM THE TOP
OF SLOPE AS DEFINED BY NATIONAL RESOURCE PROTECTION ACT (NRPA) REGULATIONS.
5. SOIL DISTURBANCE BEYOND WHAT IS INDICATED ON DRAWINGS IS PROHIBITED WITHIN 75 FEET OF THE TOP OF SLOPE AS DEFINED BY NATIONAL RESOURCE PROTECTION ACT (NRPA) REGULATIONS.
OFFICE TRAILER 1
(TYP)6
(OPTION 9)
#48
EXISTING FIRE HYDRANT
(SEE GENERAL SHEET
NOTE 16)
EXISTING PIV (SEE
GENERAL SHEET
NOTE 16)
EXISTING PIV (SEE
GENERAL SHEET NOTE 16)
(TYP)3
OHD
OHD OHD OHD
OHD
OHD
(LIMIT OF)
MAINTAIN ACCESS TO PARKING SPACES AT ALL TIMES THROUGHOUT CONSTRUCTION. SEE GENERAL SHEET NOTE 12 FOR ADDITIONAL PARKING SPACES REQUIRING ACCESS ADJACENT TO BUILDING 60.
APPROXIMATION LOCATION OF EXISTING WATER LINE BELOW SLAB (TIER 1 INFRASTRUCTURE).12
EW(12")
1-2 HOURS
CONSTRUCTION PERIOD
8 HOURS (OFF HOURS)
FP SHEETS
B60 FIRE ALARM SYSTEM
B60 POWER
EXISTING TRAILERS
1 AND 2 POWER
B74 DC POWER
2 WEEK (OFF HOURS)
B60 SPRINKLER SYSTEM
CONSTRUCTION PERIOD B60 STEAM/HOT
WATER SERVICE
4 MONTHS
4 MONTHS
CONSTRUCTION PERIOD
2 WEEKS
6 MONTHSG-006 TRAFFIC, FIRE DEPARTMENT
ACCESS, AND PARKING
B60 COMPRESSED AIR
SERVICE
CONSTRUCTION PERIODPD SHEETS
1 DAY (OFF HOURS) B60 STEAM/HOT
WATER SERVICE
1 WEEK (OFF HOURS)
1 MONTH
8 HOURS (OFF HOURS)
ITEM
FIRE PROTECTION
REFERENCE
DESIGNATION
FP1
A WATER
B ROAD (TRAFFIC)
PURPOSE REFERENCE
LOCATION/DRAWING
MAXIMUM PERMITTED
DURATION FOR EACH OUTAGE
ITEMS AFFECTED
BY THE OUTAGE
OUTAGE SCHEDULE
CIVIL
C1
C2
SITE WORK IN STORER STREET INCLUDES WATER SERVICE RELOCATION, CONSTRUCTION OF GENERATOR, MECHANICAL PADS, BOLLARDS, REGRADING, AND PAVING.
HYDRANT FLOW TEST
(CONSTRUCTION)
CONDUCT A HYDRANT FLOW TEST AS PART OF THE PROJECT REQUIREMENTS FOR THE SPRINKLER SYSTEMS
FP2 FIRE ALARM BUILDING 60 FIRE ALARM SYSTEM IS BEING REMOVED AND REPLACED
FP3 FIRE SPRINKLER SYSTEM
ELECTRICAL
E1 B60 POWER
B74 DC POWER PERMANENT
WATER ROAD/TRAFFIC
MECHANICAL
M1 STEAM/HOT WATER
BUILDING 62/62A WATER SERVICE WILL BE TEMPORARILY DISCONNECTED WHILE A PORTION OF BUILDING 60'S WATER SERVICE IN STORER STREET IS REROUTED AND BUILDING 62/62A SERVICE IS RECONNECTED. SEE OUTAGE SCHEDULE NOTE 13.
B62/B2A WATER
SERVICE
ARCHITECTURAL
A1 WORK ON THE EXTERIOR OF THE BUILDING INCLUDING WINDOW REPAIR, ROOFING REPLACEMENT, AND MASONRY
RESTORATION, WILL REQUIRE ACCESS FROM TURNER ST
BUILDING 60 STEAM AND HOT WATER SYSTEM ARE BEING REMOVED AND REPLACED.
A2 WORK ON THE EXTERIOR OF THE BUILDING INCLUDING WINDOW REPAIR, ROOFING REPLACEMENT, AND MASONRY
RESTORATION, WILL REQUIRE ACCESS FROM STORER ST
PLUMBING
P1 WATER SERVICE
M2
BUILDING 60 SPRINKLER SYSTEM IS BEING REMOVED AND REPLACED
SITE WORK IN TURNER STREET INCLUDES WATER SERVICE RECONSTRUCTION, REGRADING, AND PAVING.
C3 [OPTION 9]
REMOVE DC POWER CONNECTION BETWEEN BUILDINGS 60 AND 74.E2
PROVIDE TEMPORARY POWER PANELS AND TRANSFORMERS TO PROVIDE POWER NEEDED FOR CONSTRUCTION SERVICES AS WELL AS TEMPORARY POWER TO THE EXISTING TRAILERS 1 AND 2. FOR BIDDING PURPOSES, ASSUME REUSE OF EXISTING
FEEDER CONDUCTORS, FOR TEMPORARY POWER.
A3 WORK ON THE EXTERIOR OF THE BUILDING INCLUDING WINDOW REPAIR, ROOFING REPLACEMENTAND MASONRY RESTORATION
WILL REQUIRE ACCESS ON THE SOUTH SIDE OF BUILDING 60.
GENERAL
G1 PARTIAL ROAD/PARKING CONSTRUCTION LAYDOWN IN TURNER STREET DURING STRUCTURAL PILE WORK
P2
COMPRESSED AIR BUILDING 60 COMPRESSED AIR SYSTEM IS BEING REMOVED AND REPLACED.P3
E3
STEAM/HOT WATER BUILDING 60 STEAM AND HOT WATER SYSTEM ONAGE.
B60 POWER BUILDING 60 ELECTRICAL POWER SERVICE ONAGE
PARTIAL ROAD/PARKING
PARTIAL ROAD/PARKING
PARTIAL ROAD/PARKING
PARTIAL ROAD/PARKING
PARTIAL ROAD/PARKING
G-006, AE100'S,
AE200'S
B60 WATER SERVICEBUILDING 60 WATER SERVICE ONAGEWATER SERVICE
2 WEEKS (OFF HOURS)OPTION 9: SITE WORK INCLUDES RECONSTRUCTION OF ELECTRIC DUCTBANK IN TURNER STREET FROM LOAD CENTER 4 TO
BUILDING 60.
PARTIAL ROAD/PARKING
CONSTRUCTION PERIODG-006G2 PARTIAL ROAD/PARKING CONSTRUCTION LAYDOWN AREA ON EAST SIDE OF BUILDING 60
ED101, ED102,
ES101, EP501
ED102
EP102, EP501
TIER 2
TRAFFIC, FIRE DEPARTMENT
ACCESS, AND PARKING
G-006, CR101,
CS101, PD SHEETS
G-006, CR101,
CS101, CG101
TRAFFIC, FIRE DEPARTMENT
ACCESS, AND PARKING
TRAFFIC, FIRE DEPARTMENT
ACCESS, AND PARKING
TRAFFIC, FIRE DEPARTMENT
ACCESS, AND PARKING
G-006, CR101,
CS101, CG101
G-006, CR101,
CS101, C-201
TRAFFIC, FIRE DEPARTMENT
ACCESS, AND PARKING
TRAFFIC, FIRE DEPARTMENT
ACCESS, AND PARKING
PARKING
G-006, AE100'S,
AE200'S
G-006, AE100'S,
AE200'S
P SHEETS
MD SHEETS
M SHEETS
FD SHEETS
FP SHEETS
P4
PERMANENTPERMANENT OUTAGE TO UNUSED SERVICE TO B292. B292 COMPRESSED
AIR SERVICE
COMPRESSED AIR PD SHEETS
CONSTRUCTION PERIODE4 B60 EV CHARGING REPLACE BRANCH CIRCUITS FEEDING THE EXISTING EV CHARGING STATIONS. ED102, EP102 EV CHARGING STATIONS
TIER
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
TIER 2
B60 POWER
EXISTING TRAILERS
1 AND 2 POWER
1. OUTAGES REQUIRED BY THE SCOPE OF WORK INCLUDE, BUT ARE NOT LIMITED TO, THOSE LISTED IN THE OUTAGE SCHEDULE. OUTAGE REQUEST SUBMISSIONS, EXECUTION, AND COORDINATION PERFORMING
THE OUTAGES ARE THE RESPONSIBILITY OF THE CONTRACTOR.
2. SUBMIT A WRITTEN OUTAGE PLAN, INCLUDING SEQUENCE FOR OUTAGES AND EXPECTED DURATION OF EACH OUTAGE INCLUDING, BUT NOT LIMITED TO, THOSE LISTED IN THE OUTAGE SCHEDULE. MINIMIZE QUANTITY AND DURATION OF OUTAGES. HIGHLIGHT EACH REQUESTED OUTAGE INDIVIDUALLY ON THE 3 WEEK LOOK AHEAD SCHEDULES. AN APPROVED SCHEDULE AND OUTAGE PLAN ARE REQUIRED PRIOR TO
START OF CONSTRUCTION ACTIVITIES.
3. SCHEDULE AND COORDINATE OUTAGES WITH THE CONTRACTING OFFICER.
4. OUTAGES MAY BE SHORT DURATION, LONG DURATION, A PERMANENT REMOVAL OUTAGE, OR REQUEST
TO TURN ON/PUT EQUIPMENT INTO SERVICE (A.K.A. AN 'ONAGE').
5. PREPARE A GOVERNMENT FURNISHED OUTAGE REQUEST FORM FOR EACH OUTAGE AND SUBMIT TO THE CONTRACTING OFFICER. TIER 2 OUTAGE REQUESTS NEED TO BE SUBMITTED TO THE CONTRACTING OFFICER A MINIMUM OF THREE WEEKS AHEAD OF THE ANTICIPATED OUTAGE DATE. OUTAGES IDENTIFIED AS TIER 1 IN THE OUTAGE SCHEDULE WILL REQUIRE ADDITIONAL TIME FOR GOVERNMENT REVIEW AND
APPROVAL.
6. OUTAGES IDENTIFIED INCLUDE THE CONNECTION TO, OR REMOVAL FROM AN EXISTING UTILITY SYSTEM.
AN APPROVED OUTAGE IS REQUIRED FOR CONNECTION TO OR REMOVAL FROM EXISTING UTILITY SYSTEMS. ADDITIONAL OUTAGES MAY BE REQUIRED, DEPENDING ON THE CONTRACTOR'S SCHEDULING SEQUENCING OPERATION, WRITTEN OUTAGE PLAN, AND DIRECTIONS FROM THE CONTRACTING OFFICER, AND THE REQUIREMENTS OF SHIPYARD ACTIVITIES SUPPORTED BY BUILDING 60 UTILITIES.
7. MULTIPLE OUTAGES MAY BE REQUIRED FOR EACH PURPOSE AND/OR WORK ITEM. FOR BIDDING PURPOSES ONLY. MULTIPLE OUTAGES OF THE SAME ITEM MUST BE SEPARATED BY 24 HOURS (MINIMUM).
8. THE MAXIMUM PERMITTED DURATION OF EACH OUTAGE IN THE OUTAGE SCHEDULE IS FOR BIDDING
PURPOSES ONLY. THE EXACT OUTAGE DURATION LIMITATIONS WILL BE DETERMINED BY THE
CONTRACTING OFFICER.
9. MAJOR SYSTEMS AND FACILITIES AFFECTED BY OUTAGES ARE LISTED IN THE OUTAGE SCHEDULE. THE CONTRACTOR MUST CONFIRM SPECIFICS WITH THE CONTRACTING OFFICER PRIOR TO REQUESTING EACH
OUTAGE.
10. AS PART OF EACH OUTAGE REQUEST, INCLUDE REQUESTED GOVERNMENT SUPPORT, REQUIRED GOVERNMENT ESCORTS, TECHNICAL STAFF, SECURITY STAFF, AND SYSTEM OPERATION, TESTING, OR
RESTART SUPPORT ANTICIPATED.
11. PROVIDE TEMPORARY SERVICES FOR UTILITIES AFFECTED BY OUTAGES IF THE DESIRED WORK INCLUDED IN THE OUTAGE REQUEST CANNOT BE COMPLETED WITHIN THE MAXIMUM OUTAGE DURATION LISTED AND WHERE SPECIFICALLY INDICATED. PROVIDE TEMPORARY SERVICE/UTILITIES THAT MEET OR EXCEED THE EXISTING SYSTEM'S CAPACITIES. INCLUDE SPECIFIC NARRATIVE DISCUSSION OF THE DESIRED WORK, GOVERNMENT SUPPORT, THE SYSTEMS IMPACTED BY THE OUTAGE, AND A DETAIL DESCRIPTION FOR THE TEMPORARY SERVICE/UTILITY PROVISIONS PROPOSED AS PART OF THE OUTAGE
REQUEST. INCLUDE NARRATIVE DISCUSSION OF TRANSITIONS FROM EXISTING SERVICE(S) TO
TEMPORARY SERVICE(S) AND RETURN TO EXISTING/INSTALLED SERVICE(S) AS PART OF OUTAGE
REQUEST.
12. PRIOR TO EACH OUTAGE, CONDUCT ON-SITE PRE-OUTAGE MEETINGS WITH THE GOVERNMENT AND TRADE TECHNICIANS TO REVIEW THE DETAILS OF THE REQUESTED OUTAGE. THESE MEETINGS ARE A PREREQUISITE FOR APPROVING THE OUTAGE REQUESTS. STATE PROPOSED MEETING DATE/TIME IN EACH OUTAGE REQUEST. FINAL PRE-OUTAGE MEETING DATES AND TIMES WILL BE DETERMINED BY THE
CONTRACTING OFFICER.
13. DURING WATER OUTAGES AT BUILDING 60 PROVIDE ELECTRIC WATER COOLER/BUBBLER WITH HOT AND COLD WATER SERVICE AT BUILDING 62A. COORDINATE LOCATION AND FREQUENCY OF REPLACEMENT
WATER BOTTLE DELIVERIES WITH THE CONTRACTING OFFICER.
14. STEAM UTILITY OUTAGES MUST OCCUR DURING NON-HEATING SEASON (PROHIBITED SHUTDOWN
NOVEMBER THROUGH MARCH).
(SHEETS G-008 AND G-009)
(SHEETS G-008 AND G-009)
1. THIS OUTAGE SCHEDULE IS AN OVERVIEW OF THE POTENTIAL OUTAGES REQUIRED AND DOES NO REPRESENT A FULL LIST OF REQUIRED OUTAGES. SEE CONSTRUCTION SCHEDULE STRATEGY (SHEET G-007) FOR ADDITIONAL INFORMATION. CONTRACTOR MUST COORDINATE THE FINAL NUMBER OF
OUTAGES, THE CONSTRUCTION SCHEDULE, AND CONSTRUCTION SEQUENCING PLAN WITH THE
GOVERNMENT. SEE SPECIFICATION SECTION 01 14 00.00 22 FOR ADDITIONAL INFORMATION.
SATISFACTORY TO DATE
APPROVED
FOR COMMANDER NAVFAC
SEAL
A
B
C
D
1 2 3 4 5
1 2 3 4 5
A
B
C
D
SHEET
NAVFAC DRAWING NO.
DESIGNER
DRAWN BY
CHECKED BY
OF
EPROJECT NO.:
D E
P A
R T
M E
N T
O F
T H
E N
A V
Y N
A V
A L F
A C
IL
IT
IE
S
E N
G
IN
E E
R
IN
G S
Y S
T E
M S
C O
M M
A N
D
DRAWFORM REVISION: 14 SEP 2023
DESIGN MANAGER
PROJECT MANAGER
FEAD/PM&E
FIRE PROTECTION
N A
V A
L F
A C
IL
IT
IE
S
E N
G
IN
E E
R
IN
G S
Y S
T E
M S
C O
M M
A N
D
M
ID
-A T
LA
N
T
IC
P O
R T
S M
O U
T H
N A
V A
L S
H
IP
Y A
R D
K
IT
T
E R
Y M
E
UNCLASSIFIED
UNCLASSIFIED
U N
C L
A S
S
IF
IE
D
ACTIVITY
S Y
M D
E S
C R
IP
T
IO
N
D A
T E
A P
P R
1740579
T. CARLETON
L. LYONS
S. RUCINSKI
F
IN
A L
S U
B M
IS
S
IO
N
/0
1/
R
S H
/2
/2
:0
:3
P
M
C U s e rs \m d o n o v a n \D o c u m e n ts \2
.2
B L
D G
A
R C
H
IT
E C
T U
R A
L -V m d o n o v a n
V F
X R
.r v t
G-008
B
R
E P
A
IR
S
O U
T A
G E
S C
H E
D U
L E
RSH
JMR
MJD
K
IT
T E
R Y
M
E P
O R
T S
M O
U T
H N
A V
A L S
H
IP
Y A
R D
R O
IC
C
-M E
G -0
GENERAL NOTES
OUTAGE SCHEDULE NOTES
R S
H
/2 7/
A M
E N
D M
E N
T
ITEMREFERENCE
DESIGNATION
PURPOSE LOCATION/
DRAWING
MAXIMUM PERMITTED
DURATION FOR EACH OUTAGE
ITEMS AFFECTED
BY THE OUTAGE
OUTAGE SCHEDULE CONTINUED
TELECOMMUNICATIONS
CONSTRUCTION PERIODT1 COMMUNICATIONS BUILDING 60 COMMUNICATIONS NETWORKS (NETWORK N AND P) WILL BE MODIFIED AS PART OF THE BUILDING RENOVATIONS. ED101, ED102, ET101, ET102, ES101, ET501
B60 COMMUNICATIONS
NETWORKS N AND P
CONSTRUCTION PERIODT2 TELEPHONES BUILDING 60 TELEPHONE DISTRIBUTION WILL BE MODIFIED AS PART OF THE BUILDING RENOVATIONS. ED101, ED102, ET101, ET102, ES101, ET501
B60 TELEPHONE SERVICE
EXISTING TRAILER 2
TELEPHONE SERVICE
TIER
TIER 2
TIER 2
1. SEE SHEET G-008 FOR GENERAL NOTE AND OUTAGE SCHEDULE NOTES.
SATISFACTORY TO DATE
APPROVED
FOR COMMANDER NAVFAC
SEAL
A
B
C
D
1 2 3 4 5
1 2 3 4 5
A
B
C
D
SHEET
NAVFAC DRAWING NO.
DESIGNER
DRAWN BY
CHECKED BY
OF
EPROJECT NO.:
D E
P A
R T
M E
N T
O F
T H
E N
A V
Y N
A V
A L F
A C
IL
IT
IE
S
E N
G
IN
E E
R
IN
G S
Y S
T E
M S
C O
M M
A N
D
DRAWFORM REVISION: 14 SEP 2023
DESIGN MANAGER
PROJECT MANAGER
FEAD/PM&E
FIRE PROTECTION
N A
V A
L F
A C
IL
IT
IE
S
E N
G
IN
E E
R
IN
G S
Y S
T E
M S
C O
M M
A N
D
M
ID
-A T
LA
N
T
IC
P O
R T
S M
O U
T H
N A
V A
L S
H
IP
Y A
R D
K
IT
T
E R
Y M
E
UNCLASSIFIED
UNCLASSIFIED
U N
C L
A S
S
IF
IE
D
ACTIVITY
S Y
M D
E S
C R
IP
T
IO
N
D A
T E
A P
P R
1740579
T. CARLETON
L. LYONS
S. RUCINSKI
F
IN
A L
S U
B M
IS
S
IO
N
/0
1/
R
S H
/2
/2
:5
:2
P
M
C U s e rs \m d o n o v a n \D o c u m e n ts \2
.2
B L
D G
A
R C
H
IT
E C
T U
R A
L -V m d o n o v a n
V F
X R
.r v t
G-009
B
R
E P
A
IR
S
O U
T A
G E
S C
H E
D U
L E
C O
N T
IN
U
E D
RSH
JMR
MJD
K
IT
T E
R Y
M
E P
O R
T S
M O
U T
H N
A V
A L S
H
IP
Y A
R D
R O
IC
C
-M E
G -0
GENERAL NOTES
R S
H
/2 7/
A M
E N
D M
E N
T gjknp e6 e7 e8 e9 e10 e12 mo hi e11 l
A A
A A
5' - 0"
3 (TYP)
i.1 g.1
8.3
7.1
J.2
EXIST LEDGE
ELEV=9.20'±
EXIST LEDGE
ELEV=9.20'±
EXIST LEDGE
ELEV=8.90'±
EXIST LEDGE
ELEV=7.10'±
EXIST LEDGE
ELEV=6.60'±
EXIST LEDGE
ELEV=6.20'±
EXIST LEDGE
ELEV=6.90'±
C1
SB501
(13.38'±)
(13.38'±)
(10.30'±)
(10.30'±)
REFER TO GENERAL
NOTES 1 AND 2
12' - 7 1/4" ±
8'
3/
4"
/4
" 5
7.8
J.1
8.1
5.8
(TYP OF 6)
CJ
CJ
SLOPE
16.91'17.00'
(10.30')
10 (SIM)
e6 e7 e8 hi
8.3
7.1
J.2
7.8
C J
C J
C J
C J
CJ
CJ
CJ
CJ
CJ
CJ
C J
HSS COLUMN
(TYP OF 4)
(TYP)
J.1
8.1
CJ
C J
E J
E J
EJ
LEGEND
TIER 1
INFRASTRUCTURE
WORK AREA
SATISFACTORY TO DATE
APPROVED
FOR COMMANDER NAVFAC
SEAL
A
B
C
D
1 2 3 4 5
1 2 3 4 5
A
B
C
D
SHEET
NAVFAC DRAWING NO.
DESIGNER
DRAWN BY
CHECKED BY
OF
EPROJECT NO.:
D E
P A
R T
M E
N T
O F
T H
E N
A V
Y N
A V
A L F
A C
IL
IT
IE
S
E N
G
IN
E E
R
IN
G S
Y S
T E
M S
C O
M M
A N
D
DRAWFORM REVISION: 14 SEP 2023
DESIGN MANAGER
PROJECT MANAGER
FEAD/PM&E
FIRE PROTECTION
N A
V A
L F
A C
IL
IT
IE
S
E N
G
IN
E E
R
IN
G S
Y S
T E
M S
C O
M M
A N
D
M
ID
-A T
LA
N
T
IC
P O
R T
S M
O U
T H
N A
V A
L S
H
IP
Y A
R D
K
IT
T
E R
Y M
E
UNCLASSIFIED
UNCLASSIFIED
U N
C L
A S
S
IF
IE
D
ACTIVITY
1740579
T. CARLETON
L. LYONS
S. RUCINSKI
/2
/2
:4
:2
P
M
C U s e rs \m d o n o v a n \D o c u m e n ts \2
.2
B L D
G
S T
R U
C T
U R
A L
-V m d o n o v a n
V F
X R
.r v t
SB101
B R
E P
A
IR
S
F O
U N
D A
T
IO
N P
A R
T P
L A
N
E A
S T
DNM
WFG
MJC
K
IT
T E
R Y
,M A
IN
E
P O
R T
S M
O U
T H
N A
V A
L S
H
IP
Y A
R D
R O
IC
C
-M E
S B
SCALE: 1/8" = 1'-0"
A1
FOUNDATION PART PLAN - EAST
MATCH LINE
PLAN
NORTH
PLAN
NORTH
1/8" = 1' - 0" 0 5' 10' 15' 30'
GENERAL NOTES
GRAPHIC SCALE(S)
KEY PLAN
1'-0"x2'-0" CONTINUOUS REINFORCED CONCRETE FOOTING.
8" REINFORCED CONCRETE FOUNDATION WALL.
6" REINFORCED CONCRETE STOOP SLAB WITH BROOM FINISH.
5" REINFORCED CONCRETE SLAB-ON-GROUND. DOWEL TO
ADJACENT EXISTING SLAB. SEE DETAIL C4/SB502.
1'-6"x1'-6" REINFORCED CONCRETE PIER. TOP OF PIER
ELEVATION = 9.63'. SEE DETAIL C4/SB502.
3'-0"x3'-0"x1'-0" REINFORCED CONCRETE FOOTING ON LEVELING
PAD. BOTTOM OF FOOTING ELEVATION = 7.30'. SEE DETAIL
C4/SB502.
SAWCUT CONTROL JOINT. SEE DETAIL A3/SB501.
NON-SHRINK GROUT PAD FOR FIRE PUMP MEZZANINE STEEL
BEAMS. SEE DETAIL B3/SB501.
OPTION 7: PATCH SPALLING CONCRETE. SEE DETAIL B2/SB502.
OPTION 7: REPAIR BUTTRESS END OF WALL. SEE DETAIL
A5/SB503.
(2) DIAGONAL #5S, 3'-0" LONG, SPACED 4" ON-CENTER AND
LOCATED 4" FROM CORNER.
OPTION 7: PATCH SPALLING CONCRETE. SEE DETAIL A3/SB502.
1. REFER TO SHEET CS101 FOR NEW WATER LINE ENTRANCE THROUGH
EXISTING FOUNDATION WALL (ABOVE EXISTING SLAB ELEVATION).
2. REFER TO ELECTRICAL DRAWINGS FOR NEW POWER LINE THROUGH
EXISTING FOUNDATION WALL FOR GENERATOR.
3. EXISTING LEDGE ELEVATIONS ARE APPROXIMATE AND ARE BASED ON
EXISTING REFERENCE DRAWING 60-51-42.
SCALE: 1/8" = 1'-0"
A3
CONTROL JOINT PLAN
PLAN
NORTH
EXISTING REINFORCED CONCRETE FOUNDATION WALL.
EXISTING REINFORCED CONCRETE BUTTRESS WALL.
EXISTING REINFORCED CONCRETE PIER.
EXISTING 5"± THICK REINFORCED CONCRETE SLAB-ON-GROUND.
EXISTING REINFORCED CONCRETE CONTINUOUS FOOTING.
EXISTING REINFORCED CONCRETE EQUIPMENT PAD.
EXISTING REINFORCED CONCRETE STOOP PAD.
EXISTING STORM DRAIN LINE BELOW SLAB. SEE CIVIL DRAWINGS.
EXISTING WATER LINE BELOW SLAB (TIER 1 INFRASTRUCTURE 3-
FEET EITHER SIDE OF WATER LINE). SEE CIVIL DRAWINGS.
EXISTING STEEL FRAMED STAIRS AND RAILING.
EXISTING KEYNOTES (THIS SHEET ONLY)
KEYNOTES (THIS SHEET ONLY)
M A
R K
D E
S C
R
IP
T
IO
N D
A T
E
F
IN
A L
S U
B M
IS
S
IO
N
/0
1/
A
M E
N D
M E
N T
/2
7/ e1 abcdefgjkn e4 e2 e3 e3 p e6 e7 mo hil
A A
A A
UP
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
2(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
(TYP)
2 2
4.2
5.6 i.1 g.1 f.1
(TYP)
2.1
2.5
2.8 n.9 k.9 k.1
CJ
C J
C J
C
JCJ
C J
C J
C J
EXIST LEDGE
ELEV=8.30'±
EXIST LEDGE
ELEV=8.30'±
EXIST LEDGE
ELEV=8.30'±
EXIST LEDGE
ELEV=6.90'±
EXIST LEDGE
ELEV=6.20'±EXIST LEDGE
ELEV=4.60'±
EXIST LEDGE
ELEV=4.40'±
EXIST LEDGE
ELEV=-5.10'±
EXIST LEDGE
ELEV=-0.50'±
EXIST LEDGE
ELEV=-1.90'± EXIST LEDGE
ELEV=-0.30'±
EXIST LEDGE
ELEV=7.10'±
55 6 6
EXIST LEDGE
ELEV=9.20'±
EXIST LEDGE
ELEV=7.50'±
EXIST LEDGE
ELEV= -2.20'±
(TYP)
CJ
CJ
CJ
CJ
CJ
C J
C J
C J
CJ
C J
CJ
C J
C J
C J
C J
C J
CJ
CJ
CJ
CJ
CJ
CJ
CJ
CJ
CJ
CJ
CJ
CJ
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
C J
2.4
3.5 n.5 k.5
5.8
13' - 0"
1' - 6"
(TYP)
CJ
C J
(SIM)
3'
6"
(TYP)
(TYP)
CJ
CJ
CJ
CJ
C J
C J
C J
CJ
CJ
CJ
C J
SB401
B1
UP
A5
SB502
CJ
CJ
CJ
C J
C J
CJ
C J
24' - 9 5/8" 14' - 0"
9'
8"
(TYP)
C J
C J
(TYP)
EXIST LEDGE
ELEV=6.20'±
EXIST LEDGE
ELEV=8.10'±
12' - 0" 6' - 2" 4' - 4 1/4" 14' - 9 3/4"
7'
2"
(TYP) 8
CJ
CJ
CJ
CONDUIT BELOW
(SEE A5/SB502, SIM)
EJ EJ
E J
C J
EJ EJ
C J
CJ
C J
EJ
EJEJ
E J
E J
E J
EJ
CJ
CJ
CJ
CJ
CJ
CJ
CJ
C J
C J
C J
C J
C J
C J
C J
(TYP)
(TYP)
1'
6"
6"
17' - 0" 1' - 6"
CJ
CJ
CJ
CJ
CJ
C J
C J
CJ
CJ CJ
TIER 1
INFRASTRUCTURE
WORK AREA
SATISFACTORY TO DATE
APPROVED
FOR COMMANDER NAVFAC
SEAL
A
B
C
D
1 2 3 4 5
1 2 3 4 5
A
B
C
D
SHEET
NAVFAC DRAWING NO.
DESIGNER
DRAWN BY
CHECKED BY
OF
EPROJECT NO.:
D E
P A
R T
M E
N T
O F
T H
E N
A V
Y N
A V
A L F
A C
IL
IT
IE
S
E N
G
IN
E E
R
IN
G S
Y S
T E
M S
C O
M M
A N
D
DRAWFORM REVISION: 14 SEP 2023
DESIGN MANAGER
PROJECT MANAGER
FEAD/PM&E
FIRE PROTECTION
N A
V A
L F
A C
IL
IT
IE
S
E N
G
IN
E E
R
IN
G S
Y S
T E
M S
C O
M M
A N
D
M
ID
-A T
LA
N
T
IC
P O
R T
S M
O U
T H
N A
V A
L S
H
IP
Y A
R D
K
IT
T
E R
Y M
E
UNCLASSIFIED
UNCLASSIFIED
U N
C L
A S
S
IF
IE
D
ACTIVITY
1740579
T. CARLETON
L. LYONS
S. RUCINSKI
/2
/2
:4
:2
P
M
C U s e rs \m d o n o v a n \D o c u m e n ts \2
.2
B L D
G
S T
R U
C T
U R
A L
-V m d o n o v a n
V F
X R
.r v t
SB102
B R
E P
A
IR
S
F O
U N
D A
T
IO
N P
A R
T P
L A
N
W E
S T
DNM
WFG
MJC
K
IT
T E
R Y
,M A
IN
E
P O
R T
S M
O U
T H
N A
V A
L S
H
IP
Y A
R D
R O
IC
C
-M E
S B
MATCH LINE
PLAN
NORTH
KEYNOTES
PLAN
NORTH
1/8" = 1' - 0" 0 5' 10' 15' 30'
GRAPHIC SCALE(S)
KEY PLAN
INFILL EXISTING TRENCH WITH CONCRETE. SEE DETAIL C3/SB501.
INFILL EXISTING EQUIPMENT PIT WITH CONCRETE. SEE DETAIL
B4/SB502.
INTERIOR BOLLARD. SEE DETAIL B5/SB502.
2-1/2" x 3/16" BANDED EDGE GALVANIZED STEEL GRATING. SEE
DETAIL C4/SB503.
7-1/2" THICK REINFORCED CONCRETE SLAB-ON-GROUND. SEE
DETAIL A4/SB501.
SAWCUT CONTROL JOINT. SEE DETAIL A4/SB501.
2'-0"x2'-0"x2'-0" ELEVATOR SUMP PIT. SEE DETAIL C2/SB502.
8" REINFORCED CONCRETE FOUNDATION WALL. SEE DETAIL
C1/SB502.
REINFORCED CONCRETE BULKHEAD. SEE DETAIL C4/SB501.
SCALE: 1/8" = 1'-0"
B1
FOUNDATION PART PLAN - WEST
(2) DIAGONAL #5S, 3'-0" LONG, SPACED 4" ON-CENTER AND
LOCATED 4" FROM CORNER.
1'-6"x1'-6" REINFORCED CONCRETE PIER. TOP OF PIER
ELEVATION = 9.63'. SEE DETAIL C4/SB502 (SIMILAR).
REINFORCED CONCRETE FOOTING. BOTTOM OF FOOTING
ELEVATION = 7.00'.
ELEVATOR PIT LADDER. SEE DETAIL A1/SB501.
HOUSEKEEPING PAD. SEE DETAIL B4/SB501. COORDINATE
EXACT SIZE WITH ELECTRICAL DRAWINGS.
FLOOR DRAIN.
EXISTING REINFORCED CONCRETE FOUNDATION
WALL.
EXISTING REINFORCED CONCRETE PIER.
EXISTING 6"± THICK REINFORCED CONCRETE
SLAB-ON-GROUND WITH 1-1/2"± CONCRETE
TOPPING SLAB.
EXISTING CONCRETE PIT SUPPORTING EXISTING
EQUIPMENT. DEPTH OF PIT INDICATED ON
SHEET SD102.
EXISTING REINFORCED CONCRETE JIB CRANE
FOUNDATION.
EXISTING 7-1/2"± THICK REINFORCED CONCRETE
SLAB-ON-GROUND.
EXISTING 6"± THICK REINFORCED CONCRETE
SLAB-ON-GROUND AND 1-1/2"± THICK WOOD
PLANK FLOOR BOARDS.
1. TOP OF EXISTING AND NEW SLAB-ON-GROUND ELEVATION
= 10.30'±.
2. REFER TO SHEET SB401 FOR PILE AND PILE CAP LAYOUT.
3. EXISTING LEDGE ELEVATIONS ARE APPROXIMATE AND
ARE BASED ON EXISTING REFERENCE DRAWING 60-02-2.
GENERAL NOTES
LEGEND
EXISTING STEEL CHANNEL STAIR STRINGERS
AND CONCRETE FILLED METAL PAN STAIR
TREADS.
EXISTING W6± STEEL COLUMN SUPPORTING
EXISTING STAIRS OR MEZZANINE.
EXISTING HSS STEEL COLUMN SUPPORTING
EXISTING STAIRS OR MEZZANINE.
EXISTING STORM DRAIN LINE BELOW SLAB.
(TIER 1 INFRASTRUCTURE 3-FEET EITHER SIDE
OF WATER LINE). SEE CIVIL DRAWINGS.
EXISTING WATER LINE BELOW SLAB. SEE CIVIL
DRAWINGS.
EXISTING 4'-0"x4'-0"x1'-0"± REINFORCED
CONCRETE FOOTING.
EXISTING 2'-0"x4'-0"x1'-0"± REINFORCED
CONCRETE FOOTING.
(THIS SHEET ONLY)
EXISTING KEYNOTES (THIS SHEET ONLY)
M A
R K
D E
S C
R
IP
T
IO
N D
A T
E
F
IN
A L
S U
B M
IS
S
IO
N
/0
1/
A
M E
N D
M E
N T
/2
7/
| G-006 |
| G-006 |
G-009
File details come from the government source that posted it. Updated .