AF Form 3065 Dyess Progress Report 42 Gov.pdf
Air Force Form PDF 301 KB Posted
- Attached to
- Repair Maintenance Shop BLDG 8040
- Solicitation number
- FA4661-21-R-0001
View the file
Other versions and copies of AF Form 3065
Show all 20
Who attaches AF Form 3065
Other files
Show 40 more
Latest 50 of 163 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDRESS
REPORT NO. PERIOD COVERED PROJECT NO. CONTRACT NO. COMPLETION Date 42 From 16 Sept. Thru 30 Sept.2019 FNWZ 12-0053 20-Oct-19
LINE % OF % COMPLETED % COMPLETED
NO. TOTAL JOB THIS PERIOD CUMULATIVE
1 0.11% 0.00% 0.11% 2 1.10% 0.00% 1.10% 3 1.10% 0.00% 1.10% 4 2.20% 0.00% 2.20% 5 Remediation Testing 1.10% 0.00% 1.10% 6 2.20% 0.00% 2.20% 7 3.75% 0.00% 3.75% 8 2.51% 0.00% 2.51% 9 3.30% 0.00% 3.29%
10 1.65% 0.00% 1.65% 11 9.45% 0.00% 9.44% 12 5.20% 0.00% 5.20% 13 1.43% 0.03% 1.39% 14 1.87% 0.00% 1.87% 15 19.40% 0.00% 19.34% 16 4.95% 0.00% 4.94% 17 2.75% 0.40% 2.15% 18 2.75% 0.00% 2.74% 19 4.95% 0.03% 4.91% 20 1.87% 0.01% 1.85% 21 2.75% 0.01% 2.75% 22 2.75% 0.00% 0.00% 23 0.55% 0.00% 0.55% 24 1.10% 0.00% 1.09% 25 Tape, Float, Texture, & Paint 1.76% 0.01% 1.74% 26 2.20% 0.11% 1.44% 27 1.21% 0.00% 0.00% 28 3.85% 0.25% 3.25% 29 1.65% 0.00% 0.98% 30 0.77% 0.00% 0.00% 31 1.65% 0.00% 0.00% 32 0.95% 0.00% 0.00% 33 0.55% 0.00% 0.00% 34 Fire Suppression Finishout 1.10% 0.75% 1.00% 35 1.40% 0.00% 1.40% 36 Exterior Fencing 1.65% 0.00% 0.83% 37 0.18% 0.00% 0.00% 38 0.07% 0.00% 0.00% 39 0.22% 0.00% 0.00%
1.60% 87.87%
REMARKS: All of the fire suppression piping is installed and tested. All of the walls in the north end and restrooms are covered with kerdi board and tile has begun. All floors are leveled. The painting of the fire suppression lines are ongoing. Refrigeration piping testing is ongoing and insulation is still being done on the pipes. Electrical installation is ongoing. West overhead door was fixed per CE's request. Remaining doors, hardware, cabinets and accessories along with bollards and fencing will be on the next report due on 20 Oct.
Scheduled: 96.53% Through 30 Sept. 2019 Actual: 87.87%
SIGNATURE DATE
Wayne Owens 9/30/2019
SIGNATURE DATE
SIGNATURE DATE
HVAC Equipment And Removal / Stored and Onsite (Compressor Tanks, Stack)
Fire Suppression Rough-In, !ncludes Materials onsite From Previous Submittal
Wall Insulation
Toilet Partitions, Cabinets, & Counters
Concrete Foundation Demolition
Wall Framing
Exterior Sheathing New, /Removal Of Old,/ Column 12 N.End Removal,/ Removal Of Perlins
Doors & Frames
Interior Framing & Sheathing / Structural Steel
Roof Framing
CMU
Windows
Electrical Rough-In
Plumbing Rough-In Fire Alarm / MNS Rough-In
FA4661-15-D-0002
Repair Maintenance Shop BLDG 8040
Bonds
Submittals
3401 S Gevers St # 1, San Antonio, TX 78210
CONTRACT PROGRESS REPORT OMB NO. 0704-0188
Public reporting burden for this collection of information is estimated to average 15 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to the Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (OMB No. 9000-0058), 1215 Jefferson Davis Highway, Arlington VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person sall be subject to any penalty for failing to comply with a collection of information if t does not display a currently valid OMB control number.
PLEASE DO NOT RETURN YOUR FORM TO THE ABOVE ADDRESS. RETURN COMPLETED FORM TO: SAF/AQCO, 1060 AIR FORCE PENTAGON, WASHINGTON DC 20330-1060.
CONTRACTOR
TYPE OR PRINT NAME AND TITLE
FARR Builders llc
WORK ELEMENT
TOTAL 100.00%
At the Contracting Officer's discretion and according to the payments clause of the contract, the information provided on this form may be used for computing progress payments
PROGRESS OR COMPLETION CERTIFICATE
I hereby certify that the contractor has satisfactorily completed the indicated percentage of the contract per contract specifications.
SUBMITTED BY OR FOR
CONTRACTOR BASE CIVIL ENGINEER
1.60% 87.87%
Mobilization
Remediation
Framing And Electrical Demolition
Concrete Foundations & Slabs
Wayne Owens, PS
REVIEWED BY OR FOR BASE CIVIL ENGINEER
TYPE OR PRINT NAME AND TITLE
Daryl Carnes Construction Inspector
REVIEWED BY OR FOR CONTRACTING OFFICER
TYPE OR PRINT NAME AND TITLE
O&M & As-Builts
HVAC Rough-In
Exterior Asphalt & Concrete
Wall Sheathing
Ceramic & Porcelain Tile / Kerdi
Electrical Fixtures Onsite And Installed Plumbing Fixtures Restroom Accessories Guard Rail & Bollards HVAC Start-Up Fire Alarm / MNS Testing
Demolition Of Existing South End Steel
Interior & Exterior Signage Contractor Punchlist
| 2019-10-01T15:45:46-0500 | |
| CARNES.DARYL.ANTHONY.1129799397 |