This file is an Air Force Form 3065 Contract Progress Report for the demolition project FNWZ 21-0071, involving One Great Mystery Construction, Inc. as the contractor. The project involves complete demolition of Building 6119, a 2,892 square foot facility located at an Air Force site, with the contract covering comprehensive demolition services including removal of concrete slabs, foundations, sidewalks, utilities, structural elements, mechanical systems, and associated site infrastructure.

The progress report details 37 line items of work, each currently showing 1% completion, with a total cumulative progress of 37.50%. The contract is associated with Solicitation Number FA466126Q0005 under the Department of the Air Force Global Strike Command. The demolition scope includes removing all building components such as framing, mechanical systems, electrical infrastructure, plumbing, roofing, and site features, with work to be performed to a depth of three feet below existing grade elevation. The contract period covers from x/xx/2021 to x/xx/2022, with a completion date of x/xx/2022.

View the file

Other versions and copies of AF Form 3065

File Revision Posted Attached to
33 - AF Form 3065 Progress Report Template - 01 Apr 1996.pdf Apr 1, 1996 SABER IDIQ
33 - AF Form 3065 Progress Report Template - 01 Apr 1996.pdf Apr 1, 1996 SABER IDIQ
Attachment C - AF Form 3065.pdf Revision not stated Airfield Blast Shield
AF Form 3065.xlsx Revision not stated Demo B5276 & B8129 Amendment 0001
Attachment G - BLANK SAMPLE AF Form 3065.xlsx Revision not stated Robins AFB Paving Multi-Award IDIQ
SOW App 003 AF IMT 3065 Progress Report.pdf Revision not stated Amendment 002***Multiple Award Construction Contract (MACC), Joint Base Elmendorf-Richardson (JBER), AK – Solicitation
FNWZ 17-0021A - Att E - AF Form 3065.xlsx Revision not stated Demo B6142
Attachment 5 - AF FORM 3065 Contract Progress Report.pdf Revision not stated Security System Upgrades
Atch 30-APPENDIX 28 AF Form 3065 Progress Report Template.pdf Revision not stated Nellis AFB Paving IDIQ
Attachment 4_AF IMT 3065_199600401_VI_Progress Report.pdf Revision not stated Hazardous Materials Abatement Contract - IDIQ
Attachment 10 - BLANK SAMPLE AF Form 3065.xlsx Revision not stated Dismantling of Modular Facility & Storage Racks
Attachment 2.8 - AF Form 3065 Progress Report Template.xlsx Revision not stated Multiple Award Basic Ordering Agreement for Construction Services at Cannon AFB, NM
Exhibit 7 - AF Form 3065 Contract Progress Report.pdf Revision not stated Multiple Award Task Order Contract (MATOC) Mechanical HVAC/Mechanical Maintenance, Repair and Minor Construction Work Amendment 2
BLANK SAMPLE AF Form 3065.xlsx Revision not stated Civil Engineering Multiple Award Construction Contract III, IDIQ
Atch 08 - AF Form 3065 Progress Report.xlsx Revision not stated B9992-Doc Stewart Playgrounds [AMENDED INVITATION FOR BID]
Atch BLANK SAMPLE AF Form 3065.xlsx Revision not stated Design/Build ANG ACS Weapons Facility
16. AF Form 3065 Contract Progress Report (1 page) - BLANK.pdf Revision not stated Simplified Acquisition of Base Engineer Requirements (SABER) IDIQ at Seymour Johnson AFB, Goldsboro, NC.
Atch 08 - AF Form 3065 Progress Report.xlsx Revision not stated B9992-Doc Stewart Playgrounds [PRE-SOLICITATION]
Attachment 11 - AF Form 3065.pdf Revision not stated Construct/Repair LOX Canopies
Attachment 11 - AF Form 3065.pdf Revision not stated Communication Lines Installation, Tyndall AFB, FL
Show all 20

Who attaches AF Form 3065

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

CONTRACT PROGRESS REPORTOMB No. 0704-0188
CONTRACTORPROJECT #:FNWZ 21-0071
One Great Mystery Construction, Inc.PROJECT NAME:Demo Bldg 6119
REPORT #:PERIOD COVEREDCONTRACT NO.CONTRACT COMPLETION DATE
1FROM: x/xx/2021 TO: x/xx/2022FA4661-x/xx/2022
LINEWORK ELEMENT% OF% COMPLETED% COMPLETED
NO.TOTAL JOBTHIS PERIODCUMULATIVE
1Bonds1.00%
2Mobilization1.00%
3Construction Submittals1.00%
4Demolition1.00%
5Site/Utility Work1.00%
6Foundation/Slab on grade1.00%
7Frame/Roof Work1.00%
8Building envelope/Insulation1.00%
9Plumbling1.00%
10HVAC materials1.00%
11HVAC labor1.00%
12Electrical Materials1.00%
13Electrical labor1.00%
14Fire Protection1.00%
15Finishes/Paint1.00%
16Testing1.00%
17Contractor Punchlist1.00%
18O&M, As-Builts, & Closeout (FIXED AMOUNT)1.50%
191.00%
201.00%
211.00%
221.00%
231.00%
241.00%
251.00%
261.00%
271.00%
281.00%
291.00%
301.00%
311.00%
321.00%
331.00%
341.00%
351.00%
361.00%
371.00%
TOTAL37.50%0.00%0.00%
REMARKS:
Scheduled % Complete: _____%
Actual % Complete: _____%
At the Contracting Officer’s discretion and according to the payments clause of the contract, the information
provided on this form may be used for computing progress payments.
PROGRESS OR COMPLETION CERTIFICATE
I hereby certify that the contractor has satisfactorily completed the indicated percentage of the contract per contract specifications.
SUBMITTED BY OR FOR
ContractorBase Civil Engineer
TYPED NAME AND TITLESIGNATUREDATE
XX
REVIEWED BY OR FOR CONTRACTING OFFICER
TYPED NAME AND TITLESIGNATUREDATE

In House Reproduction of AF FORM 3065 PREVIOUS EDITION IS OBSOLETE U.S. G.P.O. 1984-4207979/13318

&"Times New Roman,Regular"&12

X