This is a Task Assignment Change Order Form (CN212 CO1) issued by the Florida Department of Environmental Protection (FDEP) for a project at O'Leno State Park. The change order involves the consultant firm Dodstone Architects, with Karin Zawrotny serving as the consultant representative and Edward Straight as the FDEP Contract Manager. The project concerns the design of a Middle Campground Bathhouse Replacement at O'Leno State Park in Florida.

The change order is a time-only extension with no cost increase to the task assignment. The original task amount of $62,646.15 remains unchanged, with the net increase/decrease in task amount for this change order being $0.00. The original task end date of June 30, 2022, has been extended by 302 calendar days to April 28, 2023, due to extended waiting periods and approvals for permits that caused time concerns. All required signatures from FDEP representatives (Budget Representative, Project Manager, and Contract Manager) and the consultant were executed between June 15-23, 2022, prior to the close of the fiscal year on June 30, 2022.

View the file

Other files

File Type Posted
CN-370000-CN212-AM1.pdf PDF
CN-370000-CN212-CMC3.pdf PDF
CN-370000-CN212-T11CO1.pdf PDF
CN-370000-CN212-T11CO2.pdf PDF
CN-370000-CN212-T12.pdf PDF
CN-370000-CN212-T13.pdf PDF
CN-370000-CN212-T14CO1.pdf PDF
CN-370000-CN212-T16.pdf PDF
CN-370000-CN212-T18CO2.pdf PDF
CN-370000-CN212-T18CO3.pdf PDF
CN-370000-CN212-T19CO1.pdf PDF
CN-370000-CN212-T21.pdf PDF
CN-370000-CN212-T22.pdf PDF
CN-370000-CN212-T23CO3.pdf PDF
CN-370000-CN212-T5.pdf PDF
CN-370000-CN212-T7.pdf PDF
CN-370000-CN212-T7CO1.pdf PDF
CN-370000-CN212-TA15.pdf PDF
CN-370000-CN212-TA3.pdf PDF
CN-370000-CN212-TA8 CO4.pdf PDF
CN-370000-CN212-T15CO2.pdf PDF
CN-370000-CN212-T18CO4.pdf PDF
CN-370000-CN212-T1CO2.pdf PDF
CN-370000-CN212-T22CO1.pdf PDF
CN-370000-CN212-T23CO4.pdf PDF
CN-370000-CN212-T24CO3.pdf PDF
CN-370000-CN212-T25.pdf PDF
CN-370000-CN212-T4.pdf PDF
CN-370000-CN212-T8.pdf PDF
CN-370000-CN212-T8CO3.pdf PDF
CN-370000-CN212-CMC1.pdf PDF
CN-370000-CN212-CMC2.pdf PDF
CN-370000-CN212-T10.pdf PDF
CN-370000-CN212-T11.pdf PDF
CN-370000-CN212-T15CO3.pdf PDF
CN-370000-CN212-T17.pdf PDF
CN-370000-CN212-T18.pdf PDF
CN-370000-CN212-T18CO1.pdf PDF
CN-370000-CN212-T23CO2.pdf PDF
CN-370000-CN212-T8CO2.pdf PDF
CN-370000-CN212-T9.pdf PDF
CN-370000-CN212-T9CO1.pdf PDF
CN-370000-CN212-TA05C01.pdf PDF
CN-370000-CN212-TA1.pdf PDF
CN-370000-CN212-TA14.pdf PDF
CN-370000-CN212.pdf PDF
PC-370000-CN212.pdf PDF
CN-370000-CN212-T11CO3.pdf PDF
CN-370000-CN212-T14CO2.pdf PDF
CN-370000-CN212-T14CO3.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN212 15 1 61281

O'Leno State Park Middle Campground Bathhouse Replacement

Dodstone Architects

Karin Zawrotny 850-656-7326 kzawrotny@dostone.com

Edward Straight 850-245-2685 Edward.Straight@FloridaDEP.gov

Extended waiting periods and approvals for permits have caused time concerns that require additional time to be added. This is a time only extension, per attached dated 6/8/2022.

$ 62,646.15 $ 62,646.15 $ 62,646.15 $ 62,646.15

$ 0.00 $ 62,646.15 $ 0.00 $ 62,646.15

8/31/2021

6/30/2022

06/30/2022

04/28/2023

Diane Langston Diane Langston Digitally signed by Diane Langston Date: 2022.06.15 10:59:39 -04'00'

Edward Straight Edward Straight Digitally signed by Edward Straight Date: 2022.06.15 09:17:13 -04'00'

Ralph M. Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2022.06.15 11:19:42 -04'00'

Karin I. Zawrotny Karin I Zawrotny Digitally signed by Karin I Zawrotny Date: 2022.06.17 14:17:29 -04'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2022.06.23 11:21:18 -04'00'

$ 0.00

From: Karin Zawrotny To: Straight, Edward Subject: Re: FDEP Project # 61281 O"Leno Middle Campground Bathhouse Date: Wednesday, June 8, 2022 7:42:10 AM Attachments: image001.jpg

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Edward, We absolutely want to move forward with this.

We are requesting a no-cost time extension for project 61281 (O'Leno Middle Campground Bathhouse) such that the completion date will be April 28, 2023 (an extension of 302 calendar days).

Please advise if you need anything further from us.

Karin Zawrotny, AIA

LEED AP BD+C

Dodstone Architects

#AR0015211

3011-1 Powell Road Tallahassee, FL 32308 P: 850.656.7326 www.dodstone.com

Follow us on:

Facebook | Instagram

On Tue, Jun 7, 2022 at 3:57 PM Straight, Edward <Edward.Straight@floridadep.gov> wrote:

Hello all, unfortunately after reviewing some files and documents today I discovered that the above Task Assignment expires on 30 June 2022. In an effort to resolve this I wanted to extend this T/A until 28 April 2023. I only want to perform this change one time hence the length of time of 302 calendar days. This Time Extension Change Order will require an email from Dodstone requesting such an extension for time only utilizing that 28 April 2023 as an end date. If you elect to move forward with this I must have this completed, signed and executed prior to the close of the fiscal year which is 30 June 2022 so we will have to move quickly. Please give me a call if you need to further clarification. Thank you as always, Edward.

Edward Straight

Design Project Manager

Bureau of Design and Construction

3800 Commonwealth Boulevard, MS 520 mailto:kzawrotny@dodstone.com mailto:Edward.Straight@FloridaDEP.gov https://secure-web.cisco.com/1OTFvtwFLNDZ_1IxDMIg4Cqb_VuZDFpqQkdfMEAtqb9xAkDCYnPfBCLU6gI6VPadX3PRlZejsAjjK-quuco1siB9flZqHpiZVLnJ5LM17y7Y8riyDBKRL5W2sVK3QZj9mbtLUUPDYTfU_PtrqOsSWPMusHHiCM0SuKxSuxn-yblIyQaZ46VtJc5FRX1FOVlsd60PK40mJ89IQzOMOA4pAku4JIXq-aX0FLmOcTh4Pl0NS9jKF4t0Cf_rlM4BijUBn0HxLZXde3nt_cCkI2Cve8YxNKfuwSPjLkFYdxJ3AzGG_Re3SlWxou07Amvq8bNzvE3L21B6cawDHP80PibHi6g/https%3A%2F%2Fg.page%2FDodstoneArchitects%3Fshare https://secure-web.cisco.com/1OTFvtwFLNDZ_1IxDMIg4Cqb_VuZDFpqQkdfMEAtqb9xAkDCYnPfBCLU6gI6VPadX3PRlZejsAjjK-quuco1siB9flZqHpiZVLnJ5LM17y7Y8riyDBKRL5W2sVK3QZj9mbtLUUPDYTfU_PtrqOsSWPMusHHiCM0SuKxSuxn-yblIyQaZ46VtJc5FRX1FOVlsd60PK40mJ89IQzOMOA4pAku4JIXq-aX0FLmOcTh4Pl0NS9jKF4t0Cf_rlM4BijUBn0HxLZXde3nt_cCkI2Cve8YxNKfuwSPjLkFYdxJ3AzGG_Re3SlWxou07Amvq8bNzvE3L21B6cawDHP80PibHi6g/https%3A%2F%2Fg.page%2FDodstoneArchitects%3Fshare http://www.dodstone.com/ https://secure-web.cisco.com/1kW2LWYPYhPerYEWNrg2jWsQzFjnxq4_ohMUSBL1ETui8taP8pPZQajjFi1femYzieb8LiQG6jsh9uc0oC_BWRlfV3wxz2YZzLmIjlN-C7LW-q359sp_OyMkK45YBjdHuvBTPmlmLA6zDssIA_5P-zdHI8JM7ZQnNWbc4lqO05FoTZtqcGkTMAr8i8hjaeY2Z9BGVLTPtLUdSyAl_9-T0fdwP9vyXoFiPaBtv4GAR0f3P4XV12tfBhKa5OVJc2h4KPcm29LQLdfDxZBy7Nsi0Nw2R8SAqXvQNXD2mZ80caxf6Km4zS3NPAg1ykwEP4JeUhmgsWVGJx4E-k93sioGQ9A/https%3A%2F%2Fwww.facebook.com%2FDodstoneArchitects%2F https://secure-web.cisco.com/15qlEtQqLWyT-9ABTsMgekIyIDd4JEIwA1zkUVMfzhOOWuvQiWIM1p8dxXKHeX_Xhn3DvxxZydPx6PkHrcJlJEX2qcp976hXnfLNIgjh6pax0g8qIuC7GIhtgVDmTbpRGr2-sMhkXlFK3MfNYiTpISSAThivsQq7DMe9i-4VFFI3Q7zdV_cjsKKswmSaak_UI9JVjpfVN_Ovkii_WTAu4iQNa99El3avj7fT7ylbnfrFd9lPXCi_3TMK8ktlsQNBIH9c5cGVfsrQA1kEhiycX06AExC66E09sWz_fVBxtlCxT6CNKmR6nwno4E85yDFVIhC7Mh2vFss5IhjKxXHy0zg/https%3A%2F%2Fwww.instagram.com%2Fdodstone%2F mailto:Edward.Straight@floridadep.gov

Matson_d Text Box

CN212 CO1

Tallahassee, Florida 32399

Office: 850-245-2685

This communication does not constitute an authorization for any increase in the scope of work, cost, or time for the project being discussed. All changes to services, cost, or time must be accomplished in accordance with the formal process outlined in the contract. The DEP objects to, and shall not be responsible for, any changes to services, costs, or additional time not authorized by an executed Contract Amendment, Task Assignment Change Order, Construction Change Order, or Construction Change Directive, as appropriate for this contract.

https://secure-web.cisco.com/1KMrcPJcVqjI_-TSb6pzrN4h5dCiiY3eQzW096oqkLQg8IxsuuYHRMwwIVCOYuB4qj3JXSTe88gWd1HEfuAw8_sZm3uNbUy_rtrxOdSKezd55-Zi6F03G3roBnSncA30hy4LuEOkA34Oy7zMBM2MOLLpvsFuVmoX82gMiaqpkigxE6NhEZOs1-XdR1KrXodtbnLlICodDajIdxFDQU5iaYqU-jHXW7FODDEtgDzi_htuuot-NwKBa2kmOGv43oS4wHfAjJVPnt1Jz6id3CGyJuhZ6_zuwA3G0Mos3LuWxQ6cGJ0GQAQwrwK2at7NKLa4HGLjbcfI-61bmY1HTOeOo9Q/https%3A%2F%2Ffloridadep.gov%2F http://secure-web.cisco.com/1LUVAV9gt_P8oHpjAxoV55uXCysG83HGwStnBBMrVj6pV1KlhX1dbA8KfgELLafiazRSB2Xs2cNC4_1DhQTksO1FNnDZCrfM_UkyBlSoDk2R8cOhAIboIvcRf1QmIhM6lRr0NlGgtp0M5CcVpOPAUNAVU0XY-cidVhRGw6UygkjVlROixqYYl3huxNSoo3aReFEU1Wvx6I5fHRxX8xatGo8mdEr1QBbOg0-RQVTCQEitNvFiQo0YmzAsUeKJmR83Fi15mp6sGkMhTGFrLoNJarJW36sHhQghZnH1sQL0-VjG3brirG09YkIpKXjL8gIf3/http%3A%2F%2Fsurvey.dep.state.fl.us%2F%3Frefemail%3DEdward.Straight%40FloridaDEP.gov

O'leno TACO.pdf
Re_ FDEP Project # 61281 O'Leno Middle Campground Bathhouse.pdf

File details come from the government source that posted it. Updated .