Solicitation Amendment 47PB0024R0049_0005.pdf

PDF 554 KB Posted

Attached to
Construction-Manager as Constructor (CMc) for the Houlton Land Port of Entry, Houlton, ME
Solicitation number
47PB0024R0049
Issued by

About this file

This document is a Solicitation Amendment for a Construction Manager as Constructor (CMc) services contract for the Houlton Land Port of Entry in Houlton, Maine. The amendment extends the proposal due date from November 26, 2024 to December 12, 2024 and adds a new document, the "Houlton LPOE CMc RFI Tracker Sheet 2024 11 22", to address additional comments received from an offeror. The contract is for design and construction phase services with a Guaranteed Maximum Price (GMP) approach. The magnitude of construction is estimated between $22 - $32 million, which includes potential Inflation Reduction Act (IRA) funding. This is a full and open competition, not set aside for small businesses, but small businesses are encouraged to participate. The solicitation includes 71 attachments, and offerors must complete a non-disclosure agreement to access certain documents. A pre-proposal conference and site visit are scheduled for October 2024.

View the file

Other files

File Type Posted
128. A.0 SOW CMc Houlton LPOE Final revised 2024 12 17.pdf PDF
129. Exhibit D_2325-GSA-Houlton ME LPOE_Design Options.pdf PDF
Solicitation Amendment 47PB0024R0049_0007.pdf PDF
127. Houlton LPOE CMc RFI Tracker Sheet 2024 12 17.xlsx XLSX spreadsheet
113A. Exhibit J_Houlton_LEED_NC_Scorecard.pdf PDF
119. Exhibit_N_Houlton_ME_DBT_MSR_FSL.pdf PDF
112. Exhibit_I__National_Operational_Excellence_Checklists__Final_Concept.pdf PDF
126. Houlton LPOE CMc RFI Tracker Sheet 2024 12 06.xlsx XLSX spreadsheet
116. Exhibit_K_Houlton_ME_LPOE_2021_P100_Performance_Matrix_Final_Concept.pdf PDF
100. Exhibit_A_Houlton_BIL_-_AE_SOW__20221212_Indexed.pdf PDF
99. ContractData-20241031-042251.pdf PDF
129. Houlton Land Port of Entry - Construction Manager as Advisor & Commissioning Provider - Rev 09Dec24.pdf PDF
127. P100 Submittal Matrix v10_CMc.pdf PDF
125. Houlton LPOE CMc RFI Tracker Sheet 2024 11 22.xlsx XLSX spreadsheet
114. Exhibit J.1_GSA Sustainable Buildings_Checklist.pdf PDF
122. Exhibit_P_Houlton_ME_LPOE_Final_Concept_Specifications_Table_of_Contents.pdf PDF
121. Exhibit_Q_2325_GSA_Houlton_LPOE_Communications_Plan.pdf PDF
Solicitation Amendment 47PB0024R0049_0006.pdf PDF
102. Exhibit_C_100_percent_PDS_Report_Houlton_LPOE_02-08-2021.pdf PDF
101. Exhibit_B_Houlton_BIL_-_AE_SOW_Revised_4March24.pdf PDF
113. Exhibit_J_Final_Concept_Development_Report_Narrative_MEP.pdf PDF
Houlton LPOE CMc RFI Tracker Sheet 2024 11 22.xlsx XLSX spreadsheet
Solicitation Amendment 47PB0024R0049_0004.pdf PDF
33. A.7 GSA P-100 2021 with 2022 Addendum Final.pdf PDF
Solicitation Amendment 47PB0024R0049_0003.pdf PDF
35. D.4 P100 Submittal Matrix v10 CMc 2021.pdf PDF
98. Houlton LPOE CMc RFI Tracker Sheet 2024 10 29 - Site Visit RFI's.pdf PDF
85 Exhibit J_Houlton_LEED_NC_Scorecard.pdf PDF
80 Exhibit E.1_MPB Roof Structure.pdf PDF
96 Houlton LPOE CMc RFI Tracker Sheet 2024 10 23 - Conference RFIs.pdf PDF
97 Solicitation Document L - UNIFORMAT II - Level 3 Detail Reference Guide.xlsx XLSX spreadsheet
83 Exhibit G.1_MEPFP_Equipment.pdf PDF
87 Exhibit J.2_ConceptDevelopmentEnergyAnalysisNarrative.pdf PDF
72 FINAL Houlton Pre-Proposal Meeting Presentation 2024 10 10.pdf PDF
93 Exhibit AA_National Operational Excellence Checklists_Concept Development.pdf PDF
95 IRA Program Construction Solicitation Desk Guide 2024 10 01.pdf PDF
81 Exhibit F_MEP Basis of Design Narrative.pdf PDF
76 Pre-Proposal Site Visit Attendance Sheet 2024 10 17.pdf PDF
75 Presolicitation in SAM 2024 08 27.pdf PDF
86 Exhibit J.1_GSA Sustainable Buildings_Checklist.pdf PDF
94 Exhibit BB_Houlton ME LPOPE_Concept Development_Specifications Table of Contents .pdf PDF
Solicitation Amendment 47PB0024R0049_0001.pdf PDF
91 Exhibit Y_Flood Level Diagram from 2024-07-02_2325-GSA-Houlton ME LPOE_Mechanical-Electrical Resilience_Rev 1.pdf PDF
Solicitation Amendment 47PB0024R0049_0002.pdf PDF
5. Form B - Request for Construction Documents 2024 10 08.pdf PDF
8. Pre-Proposal Site Visit R1 2024 10 08.pdf PDF
7. Pre-Proposal Conference R1 2024 10 08.pdf PDF
74. Cost Accounting Standards Board Disclosure Statement CASB DS-1 OMB Form Number 0348-0051.pdf PDF
6. CBP Non-Disclosure Agreement Form 2024 10 08.pdf PDF
73. Contract Price Form Spreadsheet 2024 08 28.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 108 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

10/4/2024

Michele Valenza, Contracting Officer

EQ1PC-24-00260005

Acquisition Management Division (1PQ) LPOE, PMO (1PQE), GSA/PBS

10 Causeway Street, Rm 1100 Boston, MA 02222-1077 USA

47PB0024R0049

1PQE

Acquisition Management Division (1PQ) LPOE, PMO (1PQE), GSA/PBS

10 Causeway Street, Rm 1100 Boston, MA 02222-1077 USA

1PQE

11/22/2024

Amendment 0005 - Proposal Due date has been changed by the Contracting Officer to December 12, 2024 at 2:00 PM EST.

This amendment also adds "Houlton LPOE CMc RFI Tracker Sheet 2024 11 22" to address additional comments received from an Offeror and is hereby shared with all Offeror's.

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(1)

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 11/2016) BACK

(1) Accounting classification Net increase $

File details come from the government source that posted it. Updated .