7. Pre-Proposal Conference R1 2024 10 08.pdf

PDF 351 KB Posted

Attached to
Construction-Manager as Constructor (CMc) for the Houlton Land Port of Entry, Houlton, ME
Solicitation number
47PB0024R0049
Issued by

About this file

This document is a Pre-Proposal Conference letter for Solicitation 47PB0024R0049 for a Construction Manager as Constructor (CMc) contract for repairs and alterations at the Houlton Land Port of Entry (LPOE) in Houlton, Maine.

The key details are: the Pre-Proposal Conference is scheduled for October 10, 2024; the Proposal is due November 21, 2024 at 2:00 PM EST; the Magnitude of Construction is estimated between $22-32 million, which includes potential Inflation Reduction Act (IRA) funding; Technical Factors are more important than Price Factors; a Site Visit is scheduled for October 17, 2024; Award is anticipated on or about February 28, 2025. The solicitation has 71 attachments, including the Presolicitation, Solicitation, Agreement, required forms, technical documents, and guidance. Access to certain documents requires completing a Form B and/or CBP Non-Disclosure Agreement. This solicitation is not set aside for Small Business, but Small and Large Businesses are encouraged to participate.

View the file

Other files

File Type Posted
128. A.0 SOW CMc Houlton LPOE Final revised 2024 12 17.pdf PDF
129. Exhibit D_2325-GSA-Houlton ME LPOE_Design Options.pdf PDF
Solicitation Amendment 47PB0024R0049_0007.pdf PDF
127. Houlton LPOE CMc RFI Tracker Sheet 2024 12 17.xlsx XLSX spreadsheet
113A. Exhibit J_Houlton_LEED_NC_Scorecard.pdf PDF
119. Exhibit_N_Houlton_ME_DBT_MSR_FSL.pdf PDF
112. Exhibit_I__National_Operational_Excellence_Checklists__Final_Concept.pdf PDF
126. Houlton LPOE CMc RFI Tracker Sheet 2024 12 06.xlsx XLSX spreadsheet
116. Exhibit_K_Houlton_ME_LPOE_2021_P100_Performance_Matrix_Final_Concept.pdf PDF
100. Exhibit_A_Houlton_BIL_-_AE_SOW__20221212_Indexed.pdf PDF
99. ContractData-20241031-042251.pdf PDF
129. Houlton Land Port of Entry - Construction Manager as Advisor & Commissioning Provider - Rev 09Dec24.pdf PDF
127. P100 Submittal Matrix v10_CMc.pdf PDF
125. Houlton LPOE CMc RFI Tracker Sheet 2024 11 22.xlsx XLSX spreadsheet
114. Exhibit J.1_GSA Sustainable Buildings_Checklist.pdf PDF
122. Exhibit_P_Houlton_ME_LPOE_Final_Concept_Specifications_Table_of_Contents.pdf PDF
121. Exhibit_Q_2325_GSA_Houlton_LPOE_Communications_Plan.pdf PDF
Solicitation Amendment 47PB0024R0049_0006.pdf PDF
102. Exhibit_C_100_percent_PDS_Report_Houlton_LPOE_02-08-2021.pdf PDF
101. Exhibit_B_Houlton_BIL_-_AE_SOW_Revised_4March24.pdf PDF
113. Exhibit_J_Final_Concept_Development_Report_Narrative_MEP.pdf PDF
Solicitation Amendment 47PB0024R0049_0005.pdf PDF
Houlton LPOE CMc RFI Tracker Sheet 2024 11 22.xlsx XLSX spreadsheet
Solicitation Amendment 47PB0024R0049_0004.pdf PDF
33. A.7 GSA P-100 2021 with 2022 Addendum Final.pdf PDF
Solicitation Amendment 47PB0024R0049_0003.pdf PDF
35. D.4 P100 Submittal Matrix v10 CMc 2021.pdf PDF
98. Houlton LPOE CMc RFI Tracker Sheet 2024 10 29 - Site Visit RFI's.pdf PDF
85 Exhibit J_Houlton_LEED_NC_Scorecard.pdf PDF
80 Exhibit E.1_MPB Roof Structure.pdf PDF
96 Houlton LPOE CMc RFI Tracker Sheet 2024 10 23 - Conference RFIs.pdf PDF
97 Solicitation Document L - UNIFORMAT II - Level 3 Detail Reference Guide.xlsx XLSX spreadsheet
83 Exhibit G.1_MEPFP_Equipment.pdf PDF
87 Exhibit J.2_ConceptDevelopmentEnergyAnalysisNarrative.pdf PDF
72 FINAL Houlton Pre-Proposal Meeting Presentation 2024 10 10.pdf PDF
93 Exhibit AA_National Operational Excellence Checklists_Concept Development.pdf PDF
95 IRA Program Construction Solicitation Desk Guide 2024 10 01.pdf PDF
81 Exhibit F_MEP Basis of Design Narrative.pdf PDF
76 Pre-Proposal Site Visit Attendance Sheet 2024 10 17.pdf PDF
75 Presolicitation in SAM 2024 08 27.pdf PDF
86 Exhibit J.1_GSA Sustainable Buildings_Checklist.pdf PDF
94 Exhibit BB_Houlton ME LPOPE_Concept Development_Specifications Table of Contents .pdf PDF
Solicitation Amendment 47PB0024R0049_0001.pdf PDF
91 Exhibit Y_Flood Level Diagram from 2024-07-02_2325-GSA-Houlton ME LPOE_Mechanical-Electrical Resilience_Rev 1.pdf PDF
Solicitation Amendment 47PB0024R0049_0002.pdf PDF
5. Form B - Request for Construction Documents 2024 10 08.pdf PDF
8. Pre-Proposal Site Visit R1 2024 10 08.pdf PDF
74. Cost Accounting Standards Board Disclosure Statement CASB DS-1 OMB Form Number 0348-0051.pdf PDF
6. CBP Non-Disclosure Agreement Form 2024 10 08.pdf PDF
73. Contract Price Form Spreadsheet 2024 08 28.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 108 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 47PB0024R0049 Construction Manager as Constructor (CMc) Contract, Repairs and Alterations

Houlton Land Port of Entry (LPOE), Houlton, Maine 04730

PRE-PROPOSAL CONFERENCE

Thursday, October 10, 2024, at 10:00 AM EST

1. Paul Murphy, Senior Contracts Specialist, will conduct the Pre-proposal Conference on behalf of GSA. Personnel in attendance were advised to register via email with the names of individuals attending to Paul Murphy.

Date: Thursday, October 10, 2024 Time: 10:00 AM Location: Join with Google Meet:

Meeting ID meet.google.com/iqb-xyfg-fsr Phone Numbers (US) 9211-444-+1 530

PIN: 373 853 980#

Key Personnel for the General Services Administration:

• The Contracting Officer (CO) for this contract is Michele Valenza

• The Contracts Specialist (CS) for this contract is Paul Murphy

• Maine LPOE Project Executive is Eugene Mozzoni

• The Contracting Officer’s Representative (COR) is Kenneth Perez

• Other key personnel will be introduced dependent on attendance.

2. The Solicitation has 71 attachments so we will not discuss all of them but rather mention those that have specific requirements that need to be addressed when forming your technical and price proposals.

3. Attendees are advised that any remarks and/or explanations made during this virtual meeting shall not change the terms of the solicitation. The terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing by the Contracting Officer. All amendments have to be signed by the Offeror and provided upon delivery of their proposal.

4. The following items will be discussed; however, this list may not be all inclusive. The attachments have been grouped into somewhat logical locations so that Subject Matter Experts may find it easier to locate documents that best suits their expertise. Total Pages of a document are placed in parenthesis (##).

a. The Presolicitation, “The Solicitation”, and “The Agreement” provide the most detail for submitting your proposal. The number preceding an entry is the attachment reference.

i. 2. Presolicitation in SAM 2024 08 24 (9). This is provided rather than repasting the original Presolicitation. Changes and important

Docusign Envelope ID: 6ACD1D02-8A72-49A3-B37D-428F0F09B663 requirements/reminders are highlighted and added in the Solicitation for additional clarity.

ii. 3. “The Solicitation” - Houlton CMc FINAL R4 2024 10 04 (61); and

4. “The Agreement” - Houlton CMc Final 2024 10 04 (76).

iii. 5. Form B - Request for Construction Documents 2024 08 07 (2) will be attached to the Solicitation and is for “Other Sensitive But Unclassified (SBU)” documents. Each Offeror will not be able to view the documents until GSA receives a completed Form B Document Security via email sent to paul.murphy@gsa.gov. Paul Murphy will send confirmation of receipt for every email received.

The Form B is not needed prior to the Pre-Proposal Conference as this virtual meeting is to help prepare each Offeror for submitting their Proposal and there is limited notice of this virtual meeting.

iv. 6. CBP Non-Disclosure Agreement Form 2024 10 04 (4) will be attached to the Solicitation and is for “Protected Critical Infrastructure Information (PCII)”, “Sensitive Securing Information (SSI)”, and “Other Sensitive But Unclassified (SBU)” documents. Each Offeror will not be able to view the documents until we receive a completed HS CBP Non-Disclosure Agreement Form via email sent to both lawrence.a.comiskey@cbp.dhs.gov and paul.murphy@gsa.gov. Only Paul Murphy will send confirmation of receipt for every email received. This is not needed prior to the Pre-Proposal Conference as this virtual meeting is to help prepare each Offeror for submitting their Proposal. This NDA is much more restrictive due to the security requirements of the Land Port of Entry Facility and U.S. Customs and Border Protection personnel safety.

b. The following attachments require completion of specific areas and signatures and must be included with your proposal.

i. 1. 47PB0024R0049 - Standard Form 1442 - Solicitation Offer and Award 2024 10 04 (2); 11. GSA Form 527 Contractors Qualifications And Financial Information 2021 10 01 (6); 12. Standard Form 24 - Bid Bond 2023 10 01 (4); 13. Standard Form 1416 - Payment Bond for Other Than Construction Contracts 1998 10 01 (2); 14. Standard Form 1418 - Performance Bond for Other Than Construction Contracts 1999 02 01 (2); 16. Offeror Representations and Certifications Form 2024 05 01 (21); 17. PBS Past Performance Questionnaire 2024 08 11 (5);

19. Contract Price Form 2024 08 25 (7); 20. Contract Line Item Number (CLIN) Sheet.xlsx 2024 08 24 (10); 23. Small Business Participation Commitment Document Template 2024 10 03 (2); and

24. Small Business Participation Compliance Report Template 2024 10 03 (4).

Docusign Envelope ID: 6ACD1D02-8A72-49A3-B37D-428F0F09B663 mailto:paul.murphy@gsa.gov mailto:lawrence.a.comiskey@cbp.dhs.gov mailto:paul.murphy@gsa.gov

c. Informational: This project is issued pursuant to the 15. Davis Bacon Act Wage Determination for Aroostook County ME General Decision Number ME20240006 2024 08 23 (5) - an updated wage rate will be issued to the Offeror prior to award; 65. Maine Industry Day CBP101 Updated 2023 2023 11 28 (23); 66. Maine Industry Day GSA CIPMO National Program Overview 2023 11 28 (21); and 67. Maine Industry Day Maine APEX Accelerator Who We Are and What We Do - LPOE 2023 11 28 (19).

d. Evaluations: 18. Evaluation Factors Explained 2024 10 02 (8) will be very helpful to ensuring the Offeror provides a comprehensive technical and price proposal; 22. Small Business Participation Evaluation Factor Solicitation Instruction Examples 2022 08 01 (2); 25. Small Business Participation Evaluation Factor Solicitation Evaluation Examples 2022 08 01 (2); and 45 P.9 IRA Project Submittal Reporting Form 2024 09 04 (5 Tabs).

e. Subcontracting and Small Business Participation: 9. Individual Model Subcontracting Plan - Jan 2023 - Final 508 2024 08 13 (31); and 10. Tips on Preparing a Subcontracting Plan 2024 10 03 (6).

f. Technical: 26. A.0 SOW CMc Houlton LPOE Final 2024 08 02 (50); 27. A.1 SOW AE for CMc Houlton LPOE Delivery Method Revised 2024 03 04 (63);

28. A.2 SOW CMa with Commissioning CxP Services for Houlton LPOE 2023 09 28 (39); 29. A.3 SOW CMa COBie Services Houlton LPOE 2024 04 15 (8); 30. A.4 SOW - 2023 LPOE CBP Design Guide Comparison Revision 1 2024 02 10 (3); 45 P.9 IRA Project Submittal Reporting Form 2024 09 04 (89); 48. CBP Land Port of Entry Design Standard 2023 12 06 (751); 49. CMa Commissioning Services Plan - Revision 0 2024 06 05 (62); 52. GSA Communications Plan Template LPOE Project 2024 04 18 (39); 53. GSA Data Normalization for Building Automation Systems V25 (91); 57. GSA PBS CAD Standard 2021 03 10 (5); 58. GSA Program Development Study 100% PDS Report 2021 02 08 (559); 59. GSA Regional BIM Standard V1.0 2022 06 10 (50); 63. GSA Technology Policy for PBS-Owned Buildings Monitoring and Control Systems 2022 12 14 (25); 64. Hazardous Materials Assessment Report Houlton LPOE 2020 08 14 (77); 68. Roof Map Houlton LPOE 2020 06 23 (1); 69. Roof Moisture Analysis Report Houlton 2020 06 23 (22); and 71. SOW Sustainability Language 2024 04 17 (1).

g. Guidance: 31. A.4 GSA P-100 Final 2024 05 01 (368); 332. A.6 GSA P-100 Appendix Life Cycle Cost Analysis Requirements (10); 33. A.7 GSA P-100 2021 with 2022 Addendum Final (326); 34. A.8 GSA P-120 Public Buildings Service Cost and Schedule Management Policy Requirements 2022 11 07 (81); 35. D.4 P100 Submittal Matrix v10 CMc 2021 (263); 35. D.4 P100 Submittal Matrix v10 CMc 2021 (58); 50. GSA Building Technologies Technical Reference Guide V3 Redact Final 2024 05 01 (125); 51. GSA Commissioning Guide Final 2020 09 01 (66); 54. GSA Decision Resource RCP CMIP Houlton ME 2022 02 25 (5); 55. GSA Design Excellence Policies

Docusign Envelope ID: 6ACD1D02-8A72-49A3-B37D-428F0F09B663 and Procedures 2022 11 17 (48); 56. GSA Maine LEC Materials Alternatives Market Research 2024 03 22 (56); 60. GSA Smart Building Implementation Guide V1 2022 04 22 (25); 61. GSA Smart Buildings 2021 12 16 (7); 62.

GSA Smart Buildings Program Guide V2 2022 04 22 (26); and 70. Safe Guarding Assets from the Observed and Expected Changes in Climate Submission Requirements 2022 02 26 (5).

h. Inflation Reduction Act: 37. P.5 IRA Sustainability Factor Table 2024 08 25 (3 Tabs); 38. P.5a IRA Low Embodied Carbon Asphalt Requirements 2023 12 23 (2); 39. P.5b IRA Low Embodied Carbon Concrete Requirements 508 2023 12 12 (6); 40. P.5c IRA Low Embodied Carbon Glass Requirements 508 2023 12 12 (4); 41. P.5d IRA Low Embodied Carbon Steel Requirements 508 2023 12 12 (4); 42. P.6 IRA FAQs Encyclopedia 2024 03 06 (14); 43. P.7 IRA Interpretation of Sections 60502 and 60503 2022 11 10 (6); 44. P.8 IRA Project Submittal Form and Data Dictionary (16); and 45 P.9 IRA Project Submittal Reporting Form 2024 09 04 (6 Tabs).

5. This acquisition is for a CMc contractor to complete the work required in the Scope of Work for the Construction Manager as Constructor (CMc), Repairs and Alterations, Houlton Land Port of Entry (LPOE), Houlton, Maine 04730.

6. Proposals are due November 21, 2024, at 2:00 pm EST via email (unless extended in writing by the Contracting Officer by an Amendment to the Solicitation). Documents to be submitted include technical submittals, separate from the Cost Proposal, Standard Form 24 - Bid Bond, Small Business Subcontracting Plan (if the Offeror is a large business), Offeror Representations and Certifications Form, GSA Form 527 Contractor's Qualifications and Financial Information, Past Performance Questionnaire (PPQ), and 47PB0024R0049 - Standard Form 1442 - Solicitation Offer and Award 2024 10 04. This list is not inclusive. It is the responsibility of the Offeror to ensure all requirements are met. Proposals received after 2:00 PM EST will be considered late and will be rejected.

NOTE: The price proposal needs to be broken down to Uniformat Level 2. NOTICE:

Keep in mind when submitting your proposal, that your email and attachments cannot exceed 25 MB, or it will not arrive to paul.murphy@gsa.gov. If necessary, send a second email to paul.murphy@gsa.gov with the remaining attachments. It is the Offeror’s responsibility to ensure each email containing documents have been confirmed receipt, if confirmation of receipt is delayed or not received in a timely manner.

A completed proposal, if multiple emails, needs to adhere to the November 21, 2024, at 2:00 pm EST deadline to be considered.

7. The Magnitude of Construction has an estimated price range for the Project is between $22,000,000 and $32,000,000. Offerors are cautioned that price proposals exceeding this range may be determined ineligible for award based on budgetary limitations.

Docusign Envelope ID: 6ACD1D02-8A72-49A3-B37D-428F0F09B663

This range does include potential Inflation Reduction Act (IRA) funding.

The CMc Contingency Allowance (CCA) is three percent (3%) of the Estimated Cost of the Work (ECW), as defined in the Agreement.

The Contract contemplated by this Solicitation provides for fifty percent (50%) shared savings, as defined in the Agreement.

8. Technical Factors are considerably more important than Price Factors, however, make sure to fully address each Technical (Non-price Factors) as stated in the solicitation. A document named Evaluation Factors Explained 2024 10 02 is attached to the Solicitation to assist each Offeror in the development of their individual proposal.

9. Request for clarification/information to the Pre-Proposal Conference needs to be submitted in writing no later than October 18, 2024, eight (8) calendar days after the Conference. GSA will respond in writing no later than October 25, 2024, seven (7) calendar days after the Conference via an amendment posted on SAM.gov. All questions, whether technical or administrative, are to be submitted in writing to paul.murphy@gsa.gov. Paul Murphy will send confirmation of receipt for every email received.

10. A site walk through will be held on Thursday, October 17, 2024, at 1:00 PM EST and will be held at Houlton Land Port of Entry, Interstate 95 & US/Canada Border, 27 Customs Loop, Houlton, ME 04730. The specifics of this site visit will be contained in a separate document.

11. Award will be made to the Offeror that represents the best value to the Government, based on the criteria set forth in the solicitation. We anticipate contract award on or about February 28, 2025. A Kick-Off Meeting will be held at a date to be determined later. The Notice to Proceed (NTP) may be issued at that time as determined by the Contracting Officer.

12. Let me know if you have any questions pertaining to this document at paul.murphy@gsa.gov.

Paul Murphy Contracts Specialist Acquisition Management Division Public Building Service New England Region

Docusign Envelope ID: 6ACD1D02-8A72-49A3-B37D-428F0F09B663

10/8/2024 mailto:paul.murphy@gsa.gov mailto:paul.murphy@gsa.gov

2024-10-08T07:14:16-0700
Digitally verifiable PDF exported from www.docusign.com