112. Exhibit_I__National_Operational_Excellence_Checklists__Final_Concept.pdf
PDF 124 KB Posted
- Attached to
- Construction-Manager as Constructor (CMc) for the Houlton Land Port of Entry, Houlton, ME
- Solicitation number
- 47PB0024R0049
About this file
This is an Operational Excellence Final Concept checklist that provides detailed review criteria for federal building construction and renovation projects. The checklist covers major building systems and components including site design, landscaping, exterior/interior architecture, mechanical, electrical, plumbing, fire protection, and BAS/smart building systems.
The document outlines specific requirements and considerations for operational efficiency, maintainability, accessibility, and durability. Key elements include attic stock storage requirements, equipment staging/removal planning, utility coordination for overtime usage, commissioning requirements, and life cycle cost analyses. Notable items address loading dock configurations, mechanical room sizing (requiring 20% excess space for future equipment), BAS control systems (requiring 100% DDC systems), and water feature restrictions. The checklist uses a "NIC" (Not In Contract) designation for items that are not applicable to the current project scope and includes specific responses regarding existing conditions at the FDA building, including plans for new DDC controllers and electrical service upgrades.
View the file
Other files
Show 40 more
Latest 50 of 108 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
swinslow Text Box
EXHIBIT I
P-100
1.0 Agency Attic Stock- Obtain a list of Agency Attic Stock. Attic stock must be identified and stored according to local and federal codes within agency space. Ensure that the Agency is aware of this storage requirement and obtain a signed acknowledgement.
Agency Equipment - Obtain a list of Agency Equipment. Review with the Building Manager the list of equipment to determine if GSA’s O&M or
Custodial contractor will be responsible for the equipment or if it will be the responsibility of the Agency. Once a decision for all equipment is made, ensure that the Agency is aware of all equipment they will be required to maintain and obtain a signed acknowledgement.
Overtime Utilities - Discuss with client that Overtime Utilities (OTU) will be charged for agency owned equipment that is operated and maintained by GSA (e.g. computer room AC units, FCUs in LAN rooms). GSA will create an estimate and an RWA will be needed.
2.0 No Comments
2.1
No Comments
Circulation - Does the landscaping impact pedestrian circulation or create security hazards? NIC
Hardscaping (Northern Climates) - Ensure that proposed hardscaping, i.e. slate beds, rock boulders, are not located where snow can accumulate and cause sight line issues for security. Removal of snow adjacent to buildings is key in Northern climates. NIC
Irrigation (Potable Water Demands) - What demand will that have on the overall water usage of the building? Can gray water and stormwater be used instead? NIC
Irrigation (Xeriscaping) - Determine if all or part of the landscaping can be accomplished without irrigation (xeriscaping). NIC
Security - Does the landscaping impact security by providing concealment opportunities or limiting visibility of security personnel? NIC
Snow Removal (Northern Climates) - Are plantings near walk ways salt tolerant in areas where salt is used as a de-icer? NIC
Irrigation Systems - Proprietary Systems SHALL NOT be used. NIC
Islands Plantings - Are there plantings suggested in green islands that are small is size? Small islands do not support plantings due to the limited surface area for water collection. NIC
Maintainability (Native Plantings) - Are the plantings selected for the landscaping native to the Site? NIC
Maintainability (Survivability) - Are the plantings that have been chosen hardy plants that do not require excessive maintenance? NIC
Mulch (Beds) - Confirm that mulch is sufficiently contained to prevent washing onto sidewalks or into drains. NIC
Security (Planting Size) - Confirm landscape plants are size appropriate to ensure visibility for security. Confirm landscape plants are placed based on mature growth to minimize overcrowding and excessive pruning. NIC
Tree Selection (Deep Root Trees) - Are deep root trees selected for plaza and street level landscaping? If so, these trees typically are not able to establish adequate roots which will cause the trees to be in poor health and choose tree with shallow root depth requirements. NIC
Tree Selection (Grates) - Coordinate tree grate opening with the mature calibration of tree. NIC Tree Selection (Root Growth) - Has the species and soil been selected to ensure that tree root expansion is deep and down instead of shallow and out which will affect site design (concrete sidewalks, pavers). NIC
Accessibility - Is the plumbing and all components associated with the water feature in an easily accessible location? The area should not require any work to get to the components. NIC
Noise (Inside Feature) - Does the proposed water feature have the potential to generate unwanted noise if it is located near security or a community gathering location within the building. NIC
Parking Structure Below - Is the proposed water feature located directly above a parking garage or basements? If so, relocate it to where water leaks can not cause damage to structural building elements and damage to vehicles. NIC
Outdoor Decorative Water Features - Decorative Water features that are located outdoors should be avoided in cold and arid climates. NIC
Safety - Will the proposed depth of the water feature pose a safety concern for the public, and wildlife? Can they easily escape if they fall in?
NIC
Water Features (Splash Pads, Walking surfaces) - Ensure that water runoff and or water splashes do not create a slipping hazard for surrounding walking surfaces. NIC
Wildlife - Will the proposed water feature encourage wildlife to inhabit near the Federal Building? Will there be an anticipated issue with additional cleaning to remove byproducts of the wildlife? NIC
2.2
GSA Commissioning Guide
P-100 Submittal Matrix
OE Design Guide
WBDG - GSA Criteria
FINAL CONCEPT CHECKLIST
OPERATIONAL EXCELLENCE
OPERATIONAL EXCELLENCE KEY PRINCIPLES
1. Accessibility - The ease of which a product can be serviced
2. Reliability - The ability of a system or component to function under stated conditions
3. Durability - The ability to withstand wear, pressure or damage
4. Maintainability - The ease of which a product can be repaired
5. Cleanability - The ease of which a product can be cleaned
DESIGN GUIDE RESOURCES
FINAL CONCEPT
The final concept must show that the developed scheme can achieve the program, the requirements of P100, the space requirements and the budget. Major materials, both interior and exterior, structure, fenestration, and building systems must be well defined. Life cycle costing of the proposed building systems must be accomplished to determine the most cost-effective alternatives.
The concept phase is conducted to focus on the macro level elements of the design. These elements include, but are not limited to, siting, building massing, and environmental and community impacts and concerns. Most decisions about the space allocation and building performance requirements should have already been determined in the Program of Requirements, but revisited in this design phase. Details of specific equipment and materials selections will be explored in the next phase, not here.
PRE-DESIGN REQUIREMENTS
Pre-Design Information
SITE
Building Location
Landscaping Commissioning
Design Considerations
Irrigation
Plantings
Water Features
Site Design
Cranes and Load Placement - Has the Design A/E Firm conducted a structural review of where crane and load placements will be staged during construction or replacement of equipment?
TBD- Staging, phasing and general construction coordination to be discussed when the CMc is onboarded.
Equipment Removal - Confirm the drawings and narratives indicate how major mechanical and electrical equipment can be removed/replaced. Refer to Exhibit J
Concrete Surfaces- Ensure Concrete Mix is not colored. It will be very difficult to match colored concrete in the future. NIC
De-icing (Corrosion - Confirm paving materials are not damaged by deicing chemicals. NIC
De-icing (Rock Salt Usage) - Minimize use of rock salt where advantageous and replace it with a heat melt system. NIC
Horizontal Surfaces (Shaded areas) - Areas located in shade for extended periods of time should contain materials that are easily cleaned and reduce soiling. Areas in shade for extended period of time leads to black mold, mildew and other stains NIC
Limestone - Limestone has a high absorption rate which results in an accelerated soiling and discoloration. Limestone should not be used. NIC
Marble (Northern Climates) - Marble creates a slipping hazard in Northern Climates in the winter. Marble should not be used. NIC
Pavers (Climate) - Will the proposed pavers create a slip, trip or fall hazard during all climates for that location? How will this paver react to freeze/thaw cycles? NIC
Pavers (Site Pavers) - Pavers should be used sparingly due to the maintenance concerns with weeds, freeze and thaw effects. NIC
Surfaces near water features - Ensure that proposed surfaces near water features will not create slipping hazards when wet. NIC
ABAAS Slope Compliance - Do all surface slopes meet Federal and State ABAAS requirements? This includes general parking areas, sidewalks, ABAAS parking to ensure that water flows away from the building, and eliminates ponding of water. NIC
Delivery Routes - Does the route for deliveries require vehicles to to pass under canopies or evade oncoming traffic? If so, rework the design for the delivery route. NIC
Electric Vehicles - Clearly identify the number of Electric Vehicles this project needs and the space required for the charging stations. NIC
Flagpoles (Location) - Does your project require a Flagpole? NIC
Grading (Building Elevation) - Confirm 6" elevation separation between the finish grade next to the building and the ground level finish floor for moisture protection. NIC
Grading (Interior courtyard doors) - Ensure that all grading moves water away from the building entrance and walls. NIC
Geothermal (Locations, Gates) - Does the location of the geothermal wells impede the maintenance or potential function of any gates? NIC
Geothermal (Locations) - Ensure all geothermal wells are located outside of heavyweight driving lanes. NIC
Lift Movement - Ensure that all lift movements needed to maintain the exterior facade does not cause damage to landscaping, irrigation, or other hardscaping. Ensure that movement paths are shown on drawings. NIC
Sand Build-up (Southern Borders) - Ensure that removal of sand build-up does not accumulate along fences and buildings. NIC
Site Berms and Low Mounds - Ensure that proposed low mounds or berms do not interfere with the sight line and mowing efforts of the building.
NIC
Site Drainage (Sidewalks) - To minimize accumulation of surface water on sidewalks ensure that surfaces are slopped no less than 2%. NIC
Site Features on Sidewalks (Snow removal) - Ensure that site features, (ie Site Bollards, and Lights), are not located on the path that will cause issues for snow removal equipment NIC
Snow/icicles (Travel Path) - What is the consideration for melting watery icicles and snow shedding from roofs onto the sidewalk and drive lanes?
NIC
Snow Removal (Emergency Generator Pen) - Ensure that there is adequate clearance around the generator and tank for mechanical snow removal equipment. Also ensure there is a location to put the snow in these areas so that equipment can be accessed without issues. NIC
Snow Removal (Gate Path) - Ensure that mechanical snow removal equipment can remove snow from the gate path during snow events to ensure that the gates continue to operate. These areas should be concrete in nature. NIC
Snow Removal (Gates) - Are the proposed gates large enough to ensure that snow plows can adequately maneuver around them without causing damage to the gates? NIC
Snow Removal (Storage) - Identify where a snow storage area will be located. Is this space large enough for large snow events? NIC
Truck Turning Radii - Has a truck turning program been run through the site to ensure that delivery trucks and fire trucks have adequate space through the site? NIC
Truck Turning (Sally Port/Loading Dock Layout) - Ensure that access to Sally Ports and Loading docks do not require buses, trucks, or other vehicles to comeple difficult turning challenges to pass through. NIC
Wildland Urban Interface - Does this building fall inside the Wildland Urban Interface? What design will need to be incorporated to ensure access to the building is maintained during a fire event? NIC
Site Security
Bollards, Hydraulic and Wedge Barriers - These should be used sparingly as they have a history of being problematic and inoperable. Electric bollards are preferred.
Noted, will be incorporated if applicable
Bollards, Hydraulic and Wedge Barriers (Northern Climate) - Snow and ice accumulates within the mechanism and prevents a complete cycle for these Security features and causes maintenance issues. Use of hydraulic bollards in cold weather with infrequent cycling requires special provisions to keep the hydraulic fluid warm enough to circulate. Use electrically powered bollards and wedge barriers instead.
Noted, will be incorporated if applicable
Site Bollards (Northern Climate) - Site bollards should be capped to ensure that the concrete is not exposed to environmental elements. In colder climates concrete extends upwards as a result of accumulated and freezing water within the steel pipe casing which reduces the resistance of each bollard
Noted, will be incorporated if applicable
2.3
Best Management Practices - Provide the O&M requirements for each Best Management Practice that is being considered for this project. NIC
SWPPP - Has the SWPPP Plan been coordinated with the local stormwater management authority (Federal and State)? NIC
Requirements - Is your project redesigning, reconfiguring, or reconstituting 5,000+ SF of land in any manner that diverges from the present area's day use and composition?
If Yes then your project needs to comply with EISA Section 438
No
Permeable Pavers (Parking Lots) - Confirm adequate subsurface soil has been identified to ensure that movement will not occur in significant rain events. NIC
Snow/Ice Climate - How will snow, and ice removal affect the proposed porous pavement? Porous pavement in Northern Climates should not have porous pavement due to snow, and de-icing methods. NIC
Retention Ponds - GSA does not want retention ponds due to the ongoing maintenance cost that results in a wet body of water always being present. NIC
Retention Pond (Wildlife) - Will the proposed water feature encourage wildlife to inhabit near the Federal Building? Will there be an anticipated issue with additional cleaning to remove byproducts of the wild life? GSA does not want this added cost for operations and maintenance.
NIC
Equipment Staging/Removal
Pavement Surfaces
Site Layout
Stormwater Management EISA Section 438
Porous Pavement/Permeable Pavers
Detention/Retention Ponds
ARCHITECTURAL - EXTERIOR
3.0 Canopy
Custom Design - Avoid custom -design and installed building entry canopies, as they have an increase in repair and replacement costs. Existing to remain
Thermal Break (New Buildings) - Confirm there is a thermal break between outside and inside conditions. There needs to be a thermal break within the building envelope to present heat transfer. Confirmed.
Materials (Temperature Extremes) - How will the extreme exposure requirements for the canopy materials and assemblies act? NIC
Materials (Reliability - Prefabricated) - Is the proposed material readily available? Is the manufacturer reliable in the local market? Yes.
3.1 Access - Consider facade slope for future access of facade repairs, window washing etc. (e.g. negative sloped facades present accessibility challenges)
Existing to remain
Blast Requirements for new openings, or changes to building - Has a blast study been done for the new facade?
Has the Physical Security and Structural SME been involved in the project? NIC - Existing to remain
Garage Roll-up Doors (Standard Size) - Garage doors should be standard size to ensure that when the equipment breaks parts are readily available. NIC - Existing to remain
3.2 Acoustical (Nearby tenants) - Layout of spaces should consider the acoustical effects of the loading dock. NIC - Existing to remain
Acoustical (STC Rating) - Confirm STC rating of partitions is appropriate for the space usage. NIC - Existing to remain
Bollard Placement (Interior) - Ensure bollards are placed to adequately protect the doors, and door casing of the loading dock area. NIC - Existing to remain
Bollard Placement (Exterior) - Ensure bollards are placed to adequately protect the facade. NIC - Existing to remain
Configuration (Bay size requirements) - Confirm that bays are sized properly for the truck dimensions that will provide service. NIC - Existing to remain
Configuration (Construction Dumpster) - Ensure that there is a bay provided for a construction dumpster that is in addition to the delivery bay.
NIC - Existing to remain
Configuration (Number of bays) - Ensure that the proposed number of active bays meets the needs of the building. NIC - Existing to remain
Configuration (Trash and Recycling Locations) - Does your building require a designated bay for trash compactor and recycling bin? NIC - Existing to remain
Loading Dock Door Sizing - Ensure that the size of the doors within the loading dock are typical and are not custom. Custom doors are difficult to find repair parts and have significant lead times. NIC - Existing to remain
Material (Corten Steel)- Ensure corten steel is not used above a material that will stain when weathered, such as limestone and concrete. NIC - Existing to remain
Ramp (Building Access) - Confirm a ramp is provided when the loading dock is at a different elevation then the corridor to the building. If a ramp is not feasible then ensure a lift is provided. NIC - Existing to remain
Security (Access) - Confirm that security measures ensure that no unscreened vehicle or pedestrian can access the loading dock? NIC - Existing to remain
Security (Card Access) - Confirm card access is installed on all interior building doors to ensure that access is limited. NIC - Existing to remain
Security (Screening) - Confirm that the security screening area is immediately accessible to the mailroom and allows x-ray of large packages.
NIC - Existing to remain
Security (Sight) - Maintain a clear line of sight between the security area and the loading dock entrance, as well as to ancillary equipment, such as dumpsters and compactors NIC - Existing to remain
Trench Drains - Ensure trench drains are installed at loading docks. Drains should not be placed where truck tires will be located. NIC - Existing to remain
Truck Movement - Ensure that truck movement is shown to ensure that trucks can easily deliver to the loading dock. NIC - Existing to remain
Sally Ports
No Comments
3.3 Green Roof (Maintenance) - Maintenance for green roofs is very labor intensive and is not suggested for GSA Public Buildings. Green roofs are likely to fail and cause issues to roof drains, roofing membrane, and roofing structures. NA
3.4 Glazing Sizes - Minimize the number of different sizes of glazing units for punched windows, storefront and curtain wall systems. Oversized and custom glazing should be discouraged. Confirmed.
3.5 No Comments
4.0 Glare of skylights and clerestory windows - Confirm through modeling that proposed clerestory or skylights will NOT create a glare issue within the atrium? NIC / NA
4.1
Aerosol Cleaning products - No commercial cleaning products to include aerosol products without review by Regional SME NA
Environment - Does the proposed Art work require special conditioning such as temperature, humidity, natural or artificial light levels or air movement? NA
Existing Artwork Changes - Confirm that any changes to the location or modification of existing artwork has been reviewed by the Regional Fine
Arts SME. NA
HVAC Dynamics - How will changes in HVAC (planned shutdowns, or failure) affect the proposed Artwork? (ie mold, humidity, temperature) NA
Lighting Dynamics (Damage) - Confirm that lighting dynamics have been reviewed by the SME to ensure no damage to the art work. NA
Lighting Dynamics (Illumination) - Confirm that any illumination changes have been reviewed by the SME. NA
Location Identification - Identify location of proposed artwork as well as stand off distances. NA
O&M Impacts (Exterior - Integration) - How will the exterior artwork be integrated with the Site Features (ie snow removal, irrigation, location of salt and sand removal, lawn care)? NA
O&M Impacts (Interior - Integration) - How will the interior artwork be integrated with the interior MEP systems, furniture layout and circulation?
NA
O&M Impacts (Interior - MEP Impacts) - Show that O&M staff can maintain all MEP systems without impacts to the art work? (No, special equipment should be needed to maintain any building system.) NA
O&M Maintainability - Provide detailed instruction maintenance of the Artwork. NA
Artwork - Outline the security measures that are needed to maintain the integrity of the art work? NA
Etched glass - If etched glass is used as artwork ensure that the 3rd plane of the glass is heat strengthened laminated. NA
Hardscaping (Northern Climates) - Ensure that proposed hardscaping, (ie slate beds, ground mounds) are not located where snow can accumulate and cause sight line issues for security. (Removal of snow adjacent to buildings is key in Northern climates.) NA
Safety Concerns - Ensure that all artwork is vetted to ensure there are no potential safety concerns for any security, or CBP officers. (ie Slanted slate to create a rock garden safety concerns) NA Sightline Study - Produce a sightline study that shows that the proposed Artwork will not create a visual interference with the integrity of the building security. NA
4.2
No Comments
Exterior Facade
Loading Dock and Sally Ports
Roofs
Windows
Vestibule
ARCHITECTURAL - INTERIOR
Atriums
Art in Architecture Maintainability
Security
Finishes Bathrooms
No Comments
Soap Dispenser - Confirm the building standard for soap dispensers prior to specifying counter installed soap dispenser. NIC
Carpet (Location) - Carpets should be contained to office areas. They should not be in break rooms, O&M and Janitorial office, kitchens/dining areas, mother's room, waiting rooms. Medium and high traffic corridors should be durable hard floors.
NIC
Lifts / Pallet jacks - Confirm that all floor finishes can withstand heavy loading from equipment such as lifts and pallet jacks throughout the path of travel and building.
NIC
Non conditioned space - Are finishes and building contents such as wood, acoustical ceiling tiles, paper, etc, vulnerable to swings in humidity? If so, how will the HVAC system and enclosure be designed and operated to protect moisture-vulnerable materials?
NIC
No Comments
No Comments
4.3
Access - Freight elevators are required to reach the top floor (roof). NIC Capacity and size - Confirm freight elevator capacity and size will accommodate all anticipated equipment or other building components that are transported internally as well as point loads of lifts.
NIC
No Comments
4.4
No Comments
No Comments
4.5
No Comments
4.6 No Comments
4.7 BAS Location - Ensure the BAS system is located in a room that is accessible 24/7 by the O&M staff. Ensure the room is adequately sized with a desk and large enough for 2 employees to be working at the system at a time. Ideally, the BAS should be located in a separate office and not part of the O&M office or Building Management Office. It can be co-located with the GSA LAN room.
The BAS will be located in the currnet
BAS room within the FDA building.
Building Management Office - GSA offices should be sound attenuated to an STC rating (ideally 52), especially if adjacent to contractor offices.
NIC
Custodial Breakroom - Based on building need and size, the Custodial team should have a breakroom that is separate from their workshop area
NIC
Custodial Closets - Ensure that one custodial closet is located on each floor of the building. Ensure that it is properly sized to store custodial carts and that it contains a slop sink as well a floor drain. Nothing else should be stored here aside from janitorial needs. NIC
Custodial Equipment Storage- Ensure there is adequate storage for custodial equipment (vacuums, floor machines, snow removal equipment etc.). All storage should occur on site and not at a different facility. Consider location of custodial equipment storage rooms for the use of the equipment (e.g. snow removal equipment would most likely not be stored with vacuums). NIC
Custodial Office- Based on building need and size (e.g. Courthouse, LPOE, Federal Building), the Custodial contractor should have office space that accounts for all administrative staff, project managers and supervisors. NIC
Custodial Supplies Storage- Ensure there is adequate storage for custodial supplies (paper goods, soaps, bins etc.). All storage should occur on site and not at a different facility. NIC
Electronic Waste Recycling - Ensure there is adequate space for storage of electronic waste. Confirm with BMO the size of required space needed based on building needs. NIC
GSA LAN Room - All federal buildings require a GSA LAN room even if GSA is not located in the building. The BAS can be included in this room but a workstation is needed. NIC
Loading Dock - Ensure that there is a discussion regarding the requirements at the loading dock (e.g. where should the trash and recycling bins be located). See Loading Dock Section 3.2 for additional information. NIC
Mechanical Rooms - Design spaces with at least 20% excess space for future equipment changes/adds.
The mechanical rooms have not been increased due to existing condition contstraints. If room for 20% excess space is required, an RFI to GSA will be issued.
Mechanical Rooms - Design spaces with at least 20% excess space for future equipment changes/adds.
The mechanical rooms have not been increased due to existing condition contstraints. If room for 20% excess space is required, an RFI to GSA will be issued.
O&M Attic Stock Storage - Ensure there is adequate storage area for attic stock (e.g. carpet tiles, ceiling tiles, paint). All storage should occur on site and not at a different facility.
To be coordinated with GSA
O&M Breakroom - Based on building need and size, the O&M team should have a breakroom that is separate from their workshop area. NIC
O&M Equipment Storage - Confirm where all O&M equipment will be stored when not in use (e.g. lifts, ladders, carts) NIC
O&M Office - The O&M contractors should have office space that accounts for all administrative staff, project managers and supervisors. NIC
O&M Supplies Storage - Ensure there is adequate storage area with heavy duty shelving for O&M supplies (e.g. filters, fan belts). All storage should occur on site and not at a different facility. NIC
O&M Workshop / Garage - Ensure that the workshop area is sized properly to house all operations of the O&M needs. This should be a separate area with no Mechanical Equipment in the space (e.g. AHUs) NIC
Recycling - Ensure there is adequate space for recycling sorting and storage. Confirm with BMO the size of receptacle needed and location. NIC
Trash - Ensure there is adequate space for trash receptacles. Confirm with BMO the size of dumpsters needed and location. NIC
4.8 Fitness Centers - Confirm that fitness centers are not located where sound will transmit noise or vibrations both horizontally and vertically. (Ideally fitness centers should be located on the slab on grade) NIC
Interior Courtyard Access (Pathway) - What is the designated pathway to get to the interior courtyard? In the pathway is the flooring forgiving to dirt and debris being tracked in (ie no carpet). NIC Interior Courtyard Access (Pathway) - What is the designated pathway to get to the interior courtyard? In the pathway is the flooring forgiving to dirt and debris being tracked in (ie no carpet). NIC
General Finishes
Wall
Shades
Ceiling
Programing Lessons Learned
Lead
Historic Buildings
Mechanical, Electrical, Custodial Rooms
GSA Program Requirements
Elevators Freight Elevator
General
Hazardous Material Asbestos
Countertops
Floor
5.0 Atriums HVAC
5.1 Building Envelope
No Comments
5.2 Commissioning
No Comments
5.3
No Comments
General
No Comments
Transfer Ducts
No Comments
5.4 No Comments
5.5 Accessibility No Comments
Condensate
No Comments
Chemical Treatment Systems
No Comments
Energy Energy Analysis - Define and confirm the assumptions for the hours of operations, overtime occupied hours, night cleaning, special equipment usage, building start up.
Operations will reamin 27/7/365, same as existing.
Energy Model Calibration - Show the basis of the calibration of the model against real buildings.
Pending Energy Analysis Completion, scheduled for 12/9/24 Energy Usage - Designer to document estimated energy consumption meets building energy goals, and that information has been sent to GSA.
Preliminary energy estimate is realistic in comparison to similar GSA buildings in the geographic/climatic area.
Pending Energy Analysis Completion, scheduled for 12/9/24
Heating and Cooling Plant
Exterior Mechanical Equipment - Does your project install exterior mechanical equipment?
Is there a weatherproof hose bib located adjacent to the mechanical equipment?
Does your Mechanical Equipment provide a dedicated service outlet within the unit or a GFCI weatherproof receptacle adjacent or within 25 ft of each piece of mechanical equipment in accordance with NFPA 70 210-63.
Exterior equipment is provided. A weatherproof hose bib is provided at the roof adjacent to mech equipment.
A dedicated service outlet is provided with the equipment.
Heating and Cooling Plant - Confirm that the peak heating and cooling load requirements and equipment selection is selected per the P-100?
Does each chiller have its own cooling tower or cell, condenser, and chilled water pump? Are there redundant chilled water and condenser water pumps.
Peak heating and cooling requirements & equipment selection is in compliance with P100. VRF option has spare condenser capacity.
HVAC System (Turndown Capacity) - Has your A/E provided in their narrative how they are specifically addressing capacity turndown with respect to minimum building loads, chiller and boiler capacity, and pumping capacity, and part load efficiency (50%, 25% and unoccupied)?
Has this been reviewed by the Equipment Specialist and Mechanical SME? Confirmed.
Interior Mechanical Equipment - Confirm that hose bibs and GFCI electrical outlets are proposed adjacent or within 25 fet of each piece of mechanical equipment. Confirmed.
Maintainability
Maintainability (Availability of service contractor) - Confirm that the equipment which is selected can be serviced by local technicians and does not require specialty skills not present in the geographic location of the building system Confirmed.
Maintainability (Controls) - Confirm building systems are easily operated/maintained, and controls that are easily understood by available personnel. Confirmed.
Radiant Floor (Cooling) - Not recommended. This should not be used for mixed and hot/humid climates; consult Mechanical SME if this is being recommended as this needs to be carefully designed. NA
Replacement of old equipment
No Comments
Sensors for BAS
No Comments
No Comments
5.6 Fuel Storage Tanks
State and Local Requirements - Has the A/E Firm reviewed the State and Local requirements to ensure that the fuel tank design is compliant?
5.7 Mechanical Space Programing
No Comments
6.0 Drains, Valves & Piping
No Comments
No Comments
Replacement Pipe - Has all piping older than 50 years been removed and replaced within your space? If not, a condition assessment is needed and a justification is needed, if replacement is not considered.
PLUMBING
Access (Smoke, Fire, Turning Vanes, Fusible Link for Fire Dampers)
Existing Equipment
New Equipment
Thermostat
Drains
Isolation Valves
Piping
MECHANICAL
Duct Work
Replacement Pipe (Bathroom) - Does the project include a bathroom renovation? If so, has all the piping located in the bathroom been replaced?
Have the fixtures been replaced? A condition assessment of the piping and fixtures is needed.
Plumbing fixtures will be replaced with new in same location. New fixtures will reconnect to existing piping. If a condition assesment is needed, it will be coordinated with
GSA.
6.1 Fixtures
No Comments
Hose Bibs - Hose bibs should be installed every 100' on each side of the building to ensure that maintenance has access to water. These need to be able to be locked when not in use.
Non-freeze wall hydrants will be provided to be in compliance.
No Comments
No Comments
6.2 No Comments
7.0
Accessibility - Confirm there is at least 3 feet clearance around all fire protection equipment for operation and maintenance. Confirmed
Fire Extinguisher - The Regional FPE AHJ will determine where fire extinguishers need to be deployed (e.g. are they required in breakrooms).
Fire extinguishers shall be indicated on architectural drawings.
Fire Pump Disconnect - The Regional FPE AHJ will determine if a disconnect with a tamper switch can be installed between the fire pump and the utility line for when work on the control panel is needed (an equivalence is needed to provide the intent of NFPA 20 while also allowing Building
Management to disconnect at the building level vs having to coordinate with the utility company to disconnect).
There are no existing fire pumps for the main port building. Fire Water will be provided with adequat pressure from utility company.
Knox Box - Has the local fire department and or the Authority Having Jurisdiction (AHJ) approved the location of the box?
Location of knox box has not yet been coordinated.
8.0 No Comments
8.1 Electric Vehicles (Future Infrastructure) - Identify where future infrastructure, including pavement cuts, is located on drawings and confirm all equipment can service future needs.
Electric Vehicles (Number Required) - Clearly identify the number of Electric Vehicles this project needs, and the space required for the charging stations.
8.2 Electrical Rooms
No Comments
8.3 Electrical Service
No Comments
Existing Service
Electrification Project - Confirm that adequacy of the existing equipment can support the new equipment (ie natural gas boilers to electric boilers).
The electrical scope has been revised. Please refer to RFIs 0025 and 0026. WSP will request an electrical service upgrade and new distribution equipment is being specified.
Electrification Project (Existing Equipment) - Confirm that the existing power grid can support an electrification upgrade?
The electrical scope has been revised. Please refer to RFIs 0025 and 0026. WSP will request an electrical service upgrade and new distribution equipment is being specified.
Switchboard and Switchgear - Confirm the existing switchboard does not need to be upgraded due to any new MEP equipment.
The electrical scope has been revised. Please refer to RFIs 0025 and 0026. WSP will request an electrical service upgrade and new distribution equipment is being specified.
New Service
No Comments
8.4 Generator
No Comments
8.5 Lighting
No Comments
No Comments
No Comments
8.6 Outlet Locations
No Comments
No Comments
8.7 Panelboards
No Comments
8.8 Photovoltaics
Emergency fixtures
General Fixtures
Low-flow water fixtures
Water Heaters
General
FIRE PROTECTION
General
ELECTRICAL
Conductors & Conduit Systems
Electric Vehicles
Exterior
Interior
Exterior
Interior
8.9 Power Service
No Comments
8.10 Short Circuit, Coordination and Arc Flash Study
Circuit - Has the electrical engineer submitted a preliminary short circuit analysis? TBC
8.11 Voice and Data Distribution System
Location - Has the location of the distribution equipment been determined? NIC
9.0
DDC Controllers - Does your project affect BAS Controllers? Building automation systems must be 100 percent DDC systems. In existing buildings, all pneumatic controllers should be replaced with DDC.
The main port building will be provided with new DDC controlers in compliance with P1000
9.1 Building Technologies Technical Reference - Have you provided the Building Technologies Technical Reference Guide, GSA Smart Building
Program Guide, GSA Smart Building Implementation Guide and Division 230923 (DDC & BAS) and Division 25 (Integrated Controls)
Specifications for details on scanning, servers, and other network requirements to the A/E?
These documents have been shared with AE from GSA
Existing BAS Capacity - Is the existing BAS system hardware, software and size sufficient to be compatible with the new installation to include the new points/connections? New BAS will be provided
Existing BAS Age - Has the age of the BAS system and components been taken into consideration? In most cases, we should not keep existing controls equipment unless they were recently modernized. New BAS will be provided IPV6 Capability - Confirm any / all IP addressable components are IPV6 capable. Confimed
9.2
SME Review - Has this project been coordinated with the Regional Smart Buildings Team/Program Managers?
A meeting is currently being coordinated by GSA
9.3
Infrastructure - Confirm all cable placements do not conflict with serviceable equipment, access panels etc.
This level of detail is not required in the P100 submittal matrix. Will be coordinated for a future submission
Infrastructure - Does the design include the location of GSA switches and routers to include an enclosure, rack, or shelves?
This level of detail is not required in the P100 submittal matrix. Will be coordinated for a future submission Location - Ensure the BAS system is located in a room that is 24/7 accessible by the O&M staff. Ensure the room is adequately sized with a desk and large enough for 2 employees to be working at the same time. Should be located in a separate office and not included in O&M office or
Building Management office.
The main port building will be provided with new DDC controlers in compliance with P1000
9.4 No Comments
9.5 No Comments
10.0 Building Envelope Evaluation- Is there a life-cycle analysis for building envelope elements like windows, walls and roofs?
A LCCA was completed during the
Concept Development phase. It is scheduled to be updated by 12/9/24.
Cost Savings - Has a value engineering study been performed on the project, showing proposed cost saving items do not negatively impact quality and durability? (DB Bridging Offerors' tech proposal)
A value engineering study has not yet been completed.
Custodial Evaluation - Does the life-cycle cost estimate provide a realistic custodial value? Yes.
Interior Finishes Evaluation - Is there a life-cycle analysis for interior finishes like doors and walls? NIC
Lifecycle Cost - What is the impact to Total Cost of Ownership/Lifecycle costs over a 50-year period if each of the construction cost savings measures were implemented? (Per P100 1.9.4 and 19 CFR 436) TBC
Major Equipment Evaluation - Is there a life-cycle analysis for major equipment? Yes. A LCCA was completed during the Concept Development phase. It is scheduled to be updated by
12/9/24.
O&M Evaluation - Does the life-cycle cost estimate provide a realistic O&M value? (e.g. does the cost include training) Yes. A LCCA was completed during the Concept Development phase. It is scheduled to be updated by
12/9/24.
Repair Evaluation - Does the life-cycle cost estimate includes a reasonable repair component? Yes. A LCCA was completed during the Concept Development phase. It is scheduled to be updated by
12/9/24.
Replacement Evaluation- Does the life-cycle cost estimate include a reasonable replacement cost for all affected building components (this should include finishes and equipment)?
Yes. A LCCA was completed during the Concept Development phase. It is scheduled to be updated by
12/9/24.
Utility Evaluation - Does the life-cycle cost estimate provide a realistic utility value? Yes. A LCCA was completed during the Concept Development phase. It is scheduled to be updated by
12/9/24.
11.0 Budget - Has the commissioning related costs been included in the Feasibility Study, Enhanced Feasibility Study and the Program Development
Study? Unknown
Commissioning (Time Frame) - Ensure that the Total Building Commissioning (TBC) occurs from acceptance to a minimum of one year after construction to ensure performance during all seasonal weather is verified and documented.
This issue will be addressed in the development of the CX Plan as it progresses thru the design phases.
BAS / SMART BUILDING
BAS Controllers
COMMISSIONING
General
BAS System
Compliance with ADM 7002.1
General
Outside of normal business hours
Overtime Utilities
COST ESTIMATE
General
Commissioning Plan - Has the GSA facility management, and Building Management team approved the final Commissioning Plan?
A draft of tthe Cx Plan has been distributed for GSA review and comment
Retesting Costs - Does the Cx Plan identify the responsibility for retesting costs and identify the protocol for restesting including the required number of retests? (To encourage construction quality control, the cost of retests and schedule delays caused by retesting should be the responsibility of the contractor)
This issue will be addressed in the development of the CX Plan as it progresses thru the design phases.
Testing and Commissioning- Does the Estimated Total Project Cost (ETPC) include both commissioning services and testing services? Yes; to be provided by the CMc