Houlton LPOE CMc RFI Tracker Sheet 2024 11 22.xlsx

XLSX spreadsheet 25 KB Posted

Attached to
Construction-Manager as Constructor (CMc) for the Houlton Land Port of Entry, Houlton, ME
Solicitation number
47PB0024R0049
Issued by

About this file

This document is a Request for Information (RFI) Tracker Sheet related to Solicitation No. 47PB0024R0049 for the Construction Manager as Constructor (CMc) services for the Houlton Land Port of Entry (LPOE) project in Houlton, Maine. The RFI responses address several key details, including: 1) the CAS requirement, which was denied removal; 2) the requirement for a mandatory Price Proposal, which cannot be waived; 3) the need to follow the Statement of Work (SOW) dated August 2, 2024 and other attachments, rather than conflicting supplemental documents; 4) the pricing structure, which must be submitted per the Contract Price Form and cannot be provided as a preconstruction fee or CM fee percentage; and 5) the design phase services scope, which includes schedule development, cost estimating, value engineering, and other collaborative activities with the A/E. The document also provides details on the required meetings and deliverables during the design phase.

View the file

Other files

File Type Posted
128. A.0 SOW CMc Houlton LPOE Final revised 2024 12 17.pdf PDF
129. Exhibit D_2325-GSA-Houlton ME LPOE_Design Options.pdf PDF
Solicitation Amendment 47PB0024R0049_0007.pdf PDF
127. Houlton LPOE CMc RFI Tracker Sheet 2024 12 17.xlsx XLSX spreadsheet
113A. Exhibit J_Houlton_LEED_NC_Scorecard.pdf PDF
119. Exhibit_N_Houlton_ME_DBT_MSR_FSL.pdf PDF
112. Exhibit_I__National_Operational_Excellence_Checklists__Final_Concept.pdf PDF
126. Houlton LPOE CMc RFI Tracker Sheet 2024 12 06.xlsx XLSX spreadsheet
116. Exhibit_K_Houlton_ME_LPOE_2021_P100_Performance_Matrix_Final_Concept.pdf PDF
100. Exhibit_A_Houlton_BIL_-_AE_SOW__20221212_Indexed.pdf PDF
99. ContractData-20241031-042251.pdf PDF
129. Houlton Land Port of Entry - Construction Manager as Advisor & Commissioning Provider - Rev 09Dec24.pdf PDF
127. P100 Submittal Matrix v10_CMc.pdf PDF
125. Houlton LPOE CMc RFI Tracker Sheet 2024 11 22.xlsx XLSX spreadsheet
114. Exhibit J.1_GSA Sustainable Buildings_Checklist.pdf PDF
122. Exhibit_P_Houlton_ME_LPOE_Final_Concept_Specifications_Table_of_Contents.pdf PDF
121. Exhibit_Q_2325_GSA_Houlton_LPOE_Communications_Plan.pdf PDF
Solicitation Amendment 47PB0024R0049_0006.pdf PDF
102. Exhibit_C_100_percent_PDS_Report_Houlton_LPOE_02-08-2021.pdf PDF
101. Exhibit_B_Houlton_BIL_-_AE_SOW_Revised_4March24.pdf PDF
113. Exhibit_J_Final_Concept_Development_Report_Narrative_MEP.pdf PDF
Solicitation Amendment 47PB0024R0049_0005.pdf PDF
Solicitation Amendment 47PB0024R0049_0004.pdf PDF
33. A.7 GSA P-100 2021 with 2022 Addendum Final.pdf PDF
Solicitation Amendment 47PB0024R0049_0003.pdf PDF
35. D.4 P100 Submittal Matrix v10 CMc 2021.pdf PDF
98. Houlton LPOE CMc RFI Tracker Sheet 2024 10 29 - Site Visit RFI's.pdf PDF
85 Exhibit J_Houlton_LEED_NC_Scorecard.pdf PDF
80 Exhibit E.1_MPB Roof Structure.pdf PDF
96 Houlton LPOE CMc RFI Tracker Sheet 2024 10 23 - Conference RFIs.pdf PDF
97 Solicitation Document L - UNIFORMAT II - Level 3 Detail Reference Guide.xlsx XLSX spreadsheet
83 Exhibit G.1_MEPFP_Equipment.pdf PDF
87 Exhibit J.2_ConceptDevelopmentEnergyAnalysisNarrative.pdf PDF
72 FINAL Houlton Pre-Proposal Meeting Presentation 2024 10 10.pdf PDF
93 Exhibit AA_National Operational Excellence Checklists_Concept Development.pdf PDF
95 IRA Program Construction Solicitation Desk Guide 2024 10 01.pdf PDF
81 Exhibit F_MEP Basis of Design Narrative.pdf PDF
76 Pre-Proposal Site Visit Attendance Sheet 2024 10 17.pdf PDF
75 Presolicitation in SAM 2024 08 27.pdf PDF
86 Exhibit J.1_GSA Sustainable Buildings_Checklist.pdf PDF
94 Exhibit BB_Houlton ME LPOPE_Concept Development_Specifications Table of Contents .pdf PDF
Solicitation Amendment 47PB0024R0049_0001.pdf PDF
91 Exhibit Y_Flood Level Diagram from 2024-07-02_2325-GSA-Houlton ME LPOE_Mechanical-Electrical Resilience_Rev 1.pdf PDF
Solicitation Amendment 47PB0024R0049_0002.pdf PDF
5. Form B - Request for Construction Documents 2024 10 08.pdf PDF
8. Pre-Proposal Site Visit R1 2024 10 08.pdf PDF
7. Pre-Proposal Conference R1 2024 10 08.pdf PDF
74. Cost Accounting Standards Board Disclosure Statement CASB DS-1 OMB Form Number 0348-0051.pdf PDF
6. CBP Non-Disclosure Agreement Form 2024 10 08.pdf PDF
73. Contract Price Form Spreadsheet 2024 08 28.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 108 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Follow-up RFIs

Solicitation No. 47PB0024R0049
Project Name:
Houlton, ME

Pre-Proposal Conference RFI's

RFI NumberQuestionResponseDate SubmittedDate ReceivedDate Answered
1We hereby request that the Modified CAS and CAS requirement is removed from the project in its entirety making the entire project CAS exempt.Request denied. Approval for removing or modifying CAS requires approval by the Head of Contracting Agency (HCA) and there is not enough detail/justification to warrant removal. Small business is exempt to CAS requirements.11/8/2411/12/2411/22/24
2The Solicitation lists the following breakdown of % evaluation criteria:

a. The Technical Proposal shall include the information requested below.

i. (1) Experience in Providing Design Phase Services and Construction Phase Services on Similar Projects (30%)

ii. (2) Management and Technical Approach (Design Phase Services and Construction Phase Services) (20%)

iii. (3) Qualifications and Experience of Key Personnel (15%)

iv. (4) Past Performance in Providing Design Phase Services and Construction Phase Services on Similar Projects Provided under Factor #1 (15%)

v. (5) Sustainability (15%)

vi. (6) Small Business Participation (5%)

vii. II.D. Price Proposal - No percentage is listed for the price proposal implying that this item has zero value at this juncture. Please confirm this pricing can be waived and is not required for the solicitation response?A Price Proposal is mandatory. Lack of a Price Proposal would deem the entire proposal as non-responsive. The Price Proposal is evaluated separate from the Technical Proposal. The Technical Proposal is deemed to be more important than Price.11/8/2411/12/2411/22/24
3The basis for these questions is as follows: The Statements of Work documents provided do not match the solicitation.Follow the Statement of Work (SOW) dated August 02, 2024 under Attachment 26 - A.0 SOW CMc Houlton LPOE Final 2024 08 02.11/8/2411/12/2411/22/24
4The basis for these questions is as follows:
o Supplemental document sent per RFI response AE Concept Development Narrative 2024 07 19 does not match the solicitation.Follow AE Concept Development Narrative dated 2024 07 19.11/8/2411/12/2411/22/24
5The basis for these questions is as follows:
o Supplemental document sent per RFI response GSA Program Development Study 100% PDS Report 2021 02 08 list multiple options within scopes of work but on the bid summary or bid breakdown no room to list options.Provide a Price Proposal based on bid sheets provided under Attachment 19 - Contract Price Form 2024 08 25. The Program Development Study 100% PDS Report dated 2021 02 08 is for reference only.11/8/2411/12/2411/22/24
6The basis for these questions is as follows: o The information provided is not clear or consistent. The documents list conflicting options, incomplete scopes descriptions and it is not possible to determine an actual scope of work to provide budgetary pricing at this time.Submit in accordance with the Statement of Work (SOW) dated August 02, 2024 under Attachment 26 - A.0 SOW CMc Houlton LPOE Final 2024 08 02.11/8/2411/12/2411/22/24
7The basis for these questions is as follows: We are requesting that the pricing proposal component in The Solicitation be waived and completed as part of the preconstruction / Design Phase Services as the team can work together to develop scope of work and formatting that can be budgeted during the process.Request denied. GSA requires a separate Price Proposal be submitted by the due date or the entire proposal will be considered non-responsive.11/8/2411/12/2411/22/24
8The solicitation lists a breakdown summary of Design Phase Services, Base Bid and Bid Options 1 Thru Bid Options 7. a. If a pricing proposal is required, please confirm it is budgetary only and non-binding with modifications to occur during the preconstruction process and scope development? We ask this because the presentation of scope and details are vacant leaving many items up for interpretation and we don’t feel a budget at this juncture will be equitable for the actual project or provide any value.CLIN 1 Design Phase Services can be awarded without negotiations and will be award as a firm fixed price contract. Provide a price for each option shown based on available information. Do not provide any exceptions or exclusions. If during evaluations, the Government is unable to assess what is being proposed then they may provide clarifying questions, hold discussions, and/or enter negotiations to evaluate the proposal.11/8/2411/12/2411/22/24
9The solicitation lists a breakdown summary of Design Phase Services, Base Bid and Bid Options 1 Thru Bid Options 7. b. We suggest providing a preconstruction fee based on a labor histogram that can be reviewed and modified as the team and scope is defined. Is this acceptable?No, this not acceptable. Submit a proposal in compliance with Attachment 19 - Contract Price Form 2024 08 25.11/8/2411/12/2411/22/24
10The solicitation lists a breakdown summary of Design Phase Services, Base Bid and Bid Options 1 Thru Bid Options 7. c. We suggest providing a CM fee that will be a percentage of the combined cost of General Conditions, General Requirements and trade work. Is this acceptable?No, this is not acceptable. The Government expects to see the same fee percentage for all work performed for base bid and all options per Attachment 19 - Contract Price Form 2024 08 25. The precentage would be what you normally include in overhead, direct, indirect costs and/or profit.11/8/2411/12/2411/22/24
11The solicitation lists a breakdown summary of Design Phase Services, Base Bid and Bid Options 1 Thru Bid Options 7. d. If general conditions and general requirements are required for proposal response, please provide a duration of schedule and an updated scope of work with which buildings will be impacted and if phasing is anticipated for different buildings.A Period of Performance was provided. The Houlton Land Port of Entry will remain open during construction. The Contractor will determine the means and methods on how to complete the work around U.S. Customs and Border Protection operations. Bidders are to submit a preliminary schedule consistant with the milestones listed in the Statement of Work.11/8/2411/12/2411/22/24
124. Please confirm that Design Phase Services is limited to preconstruction and only inclusive of:

a) Schedule Development

b) Cost-estimating and cost reconciliation services

c) Subcontractor participation

d) Value engineering services

e) Design assist servicesFollow the Statement of Work, Section IV - Scope of Services, paragraph A, pages 27 through 28.11/8/2411/12/2411/22/24
134.1 How many rounds of estimating and reconciliation are required or anticipated. It is not defined in any of the documentation provided? a) Schedule Development b) Cost-estimating and cost reconciliation services c) Subcontractor participation d) Value engineering services
e) Design assist servicesOne (1) Design Development submission, three (3) Construction Development submissions, one (1) for final negoitations of GMP, reconciliation reviews will be completed by the CMa which could result in a resubmission. Refer to the SOW, pages 27-28.11/8/2411/12/2411/22/24
145. The Statement of work lists the preconstruction phase services aka design phase services as having a number of meetings required. Please provide a count for each of the meetings to be attended and anticipated durations of each. A. Pre-Construction Phase Services a.k.a. Design Phase Services. The CMc shall exercise reasonable care in performing its Pre-Construction Services. The Owner and A/E shall be entitled to rely on, and shall not be responsible for, the accuracy, completeness, and timeliness of services and information furnished by the CMc. The CMc, however, does not warrant or guarantee estimates and schedules except as may be included as part of the GMP. The CMc is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the CMc shall promptly report to the A/E and Owner any nonconformity discovered by or made known to the CMc as a request for information in such form as the A/E may require.Refer to the SOW Section III General Requirements11/8/2411/12/2411/22/24
15Please provide a count for each of the meetings to be attended and anticipated durations of each. 1. PROJECT INITIATION MEETING
The CMc shall participate in an initial meeting with other members of the project team (the A/E, GSA, CMa, and customer agency representatives to review the project’s scope, status of design, discuss goals, begin initial project planning, and agree to the schedule for regularly scheduled Project Meetings.Refer to the SOW Section III General Requirements11/8/2411/12/2411/22/24
16Please provide a count for each of the meetings to be attended and anticipated durations of each. 2. COLLABORATION WITH THE A/E
During the A/E’s Design Phase Services, the CMc provides Pre-Construction advice to the owner and the A/E in a collaborative environment to identify the potential impact of the design on the project's actual construction and cost. Specifically, the CMc will focus on the design, constructability issues, schedule, cost, risks, and engage in a series of CMc Constructability Reviews and CERPA that occur after each A/E Design Submission. As required by the project the CMc shall facilitate in COST ESTIMATE RECONCILIATION and PROPOSED ALTERNATIVES workshops after each Constructability Review. The ultimate goal of this collaboration is to establish a final Estimated Cost of Work (GMP) that does not exceed the “initial target GMP” (as set forth in the Contractor’s proposal). The CMc's involvement during the project design phase provides GSA with the ability to identify current market conditions concerning labor and material availability, constructability issues, and any phasing and sequencing impacts. In addition to the Constructability Reviews and CERPA workshops the A/E and its subcontractors will communicate through “Informal Information Exchange”, “Design Assist” or “Delegated Design” processes or contracts that may involve the CMc and its trade subcontractors. This will ensure mutual understanding of both the A/E's design intent and the CMc's means and methods, and thus ensure greater certainty in pricing the construction work. It also increases the likelihood that design errors and omissions are recognized and resolved during design. In addition, this collaboration takes place during a time that does not significantly impact the construction schedule and that can result in expedited production and review of shop drawings once construction commences.Refer to the SOW Section III General Requirements11/8/2411/12/2411/22/24
17Please provide a count for each of the meetings to be attended and anticipated durations of each. 3. DELIVERABLES MATRIX The Deliverables Matrix has this project’s detailed list of design review deliverables and milestones. A copy of the Deliverables Matrix is attached. The CMc shall be responsible for General Information deliverable requirements as applicable to the services provided and Cost Estimating deliverable requirements. Deliverables are for the Project Phases beginning with the 100% Design Development Phase thru the Final Construction Documents: Issued for Construction Phase.Refer to the SOW Section III General Requirements11/8/2411/12/2411/22/24
18Please provide a count for each of the meetings to be attended and anticipated durations of each. 4. OPERATIONAL EXCELLENCE PROGRAM
The CMc Contractor must participate in Operational Excellence (OE) Reviews during each design phase. The Deliverables Matrix provides OE related deliverables requirements. The reviews include receiving and responding to questions and comments from the GSA’s regional and national (Central) Office of Facility Management (OFM) staff and building systems’ subject matter experts (SME).Refer to the SOW Section III General Requirements11/8/2411/12/2411/22/24
19Please provide a count for each of the meetings to be attended and anticipated durations of each. 5. DESIGN REVIEW - PROCESS and PROCEDURES GSA, and other occupant tenant agencies will review the A/E’s design submissions listed in the Deliverables matrix for their iterative development towards meeting the expected outcome of the design. The CMc shall participate in the design review process. Refer to CERPA.Refer to the SOW Section III General Requirements11/8/2411/12/2411/22/24
206. We suggest that the price for Target ECW – Acquisition and installation of low embodied carbon steel, asphalt, glass and concrete be provided on a unit cost basis that will show the delta increase in unit cost by the ton for steel and asphalt, square foot for glass and by the cubic yard for concrete. Is this acceptable?No, this is not acceptable. Bid in compliance with Attachment 19 - Contract Price Form 2024 08 25.11/8/2411/12/2411/22/24

&P

File details come from the government source that posted it. Updated .