100. Exhibit_A_Houlton_BIL_-_AE_SOW__20221212_Indexed.pdf

PDF 19 MB Posted

Attached to
Construction-Manager as Constructor (CMc) for the Houlton Land Port of Entry, Houlton, ME
Solicitation number
47PB0024R0049
Issued by

About this file

This is a preview of Federal Contract Opportunity #47PB0024R0049 for Construction Manager as Constructor (CMc) services at the U.S. Customs and Border Protection Land Port of Entry in Houlton, Maine. The project, funded through the Bipartisan Infrastructure Law (BIL) and targeted for Inflation Reduction Act (IRA) funding, includes both Design Phase services (Firm-Fixed Price) and Construction Phase services (Guaranteed Maximum Price).

The estimated construction magnitude is $22-32 million, including potential IRA funding. While not set aside for small businesses, both small and large businesses may participate under NAICS code 236220 with a size standard of $39.5 million average annual receipts. Key dates include a pre-proposal conference on October 10, 2024, at 10:00 PM EST, a site visit on October 17, 2024, at 1:00 PM EST, and proposal submissions due November 11, 2024, at 2:00 PM EST. Interested parties must complete both GSA's Request for Construction Documents and CBP's Non-Disclosure Agreement to access project documents. Technical and price proposals must be submitted separately, with offers valid for 120 calendar days.

View the file

Other files

File Type Posted
128. A.0 SOW CMc Houlton LPOE Final revised 2024 12 17.pdf PDF
129. Exhibit D_2325-GSA-Houlton ME LPOE_Design Options.pdf PDF
Solicitation Amendment 47PB0024R0049_0007.pdf PDF
127. Houlton LPOE CMc RFI Tracker Sheet 2024 12 17.xlsx XLSX spreadsheet
113A. Exhibit J_Houlton_LEED_NC_Scorecard.pdf PDF
119. Exhibit_N_Houlton_ME_DBT_MSR_FSL.pdf PDF
112. Exhibit_I__National_Operational_Excellence_Checklists__Final_Concept.pdf PDF
126. Houlton LPOE CMc RFI Tracker Sheet 2024 12 06.xlsx XLSX spreadsheet
116. Exhibit_K_Houlton_ME_LPOE_2021_P100_Performance_Matrix_Final_Concept.pdf PDF
99. ContractData-20241031-042251.pdf PDF
129. Houlton Land Port of Entry - Construction Manager as Advisor & Commissioning Provider - Rev 09Dec24.pdf PDF
127. P100 Submittal Matrix v10_CMc.pdf PDF
125. Houlton LPOE CMc RFI Tracker Sheet 2024 11 22.xlsx XLSX spreadsheet
114. Exhibit J.1_GSA Sustainable Buildings_Checklist.pdf PDF
122. Exhibit_P_Houlton_ME_LPOE_Final_Concept_Specifications_Table_of_Contents.pdf PDF
121. Exhibit_Q_2325_GSA_Houlton_LPOE_Communications_Plan.pdf PDF
Solicitation Amendment 47PB0024R0049_0006.pdf PDF
102. Exhibit_C_100_percent_PDS_Report_Houlton_LPOE_02-08-2021.pdf PDF
101. Exhibit_B_Houlton_BIL_-_AE_SOW_Revised_4March24.pdf PDF
113. Exhibit_J_Final_Concept_Development_Report_Narrative_MEP.pdf PDF
Solicitation Amendment 47PB0024R0049_0005.pdf PDF
Houlton LPOE CMc RFI Tracker Sheet 2024 11 22.xlsx XLSX spreadsheet
Solicitation Amendment 47PB0024R0049_0004.pdf PDF
33. A.7 GSA P-100 2021 with 2022 Addendum Final.pdf PDF
Solicitation Amendment 47PB0024R0049_0003.pdf PDF
35. D.4 P100 Submittal Matrix v10 CMc 2021.pdf PDF
98. Houlton LPOE CMc RFI Tracker Sheet 2024 10 29 - Site Visit RFI's.pdf PDF
85 Exhibit J_Houlton_LEED_NC_Scorecard.pdf PDF
80 Exhibit E.1_MPB Roof Structure.pdf PDF
96 Houlton LPOE CMc RFI Tracker Sheet 2024 10 23 - Conference RFIs.pdf PDF
97 Solicitation Document L - UNIFORMAT II - Level 3 Detail Reference Guide.xlsx XLSX spreadsheet
83 Exhibit G.1_MEPFP_Equipment.pdf PDF
87 Exhibit J.2_ConceptDevelopmentEnergyAnalysisNarrative.pdf PDF
72 FINAL Houlton Pre-Proposal Meeting Presentation 2024 10 10.pdf PDF
93 Exhibit AA_National Operational Excellence Checklists_Concept Development.pdf PDF
95 IRA Program Construction Solicitation Desk Guide 2024 10 01.pdf PDF
81 Exhibit F_MEP Basis of Design Narrative.pdf PDF
76 Pre-Proposal Site Visit Attendance Sheet 2024 10 17.pdf PDF
75 Presolicitation in SAM 2024 08 27.pdf PDF
86 Exhibit J.1_GSA Sustainable Buildings_Checklist.pdf PDF
94 Exhibit BB_Houlton ME LPOPE_Concept Development_Specifications Table of Contents .pdf PDF
Solicitation Amendment 47PB0024R0049_0001.pdf PDF
91 Exhibit Y_Flood Level Diagram from 2024-07-02_2325-GSA-Houlton ME LPOE_Mechanical-Electrical Resilience_Rev 1.pdf PDF
Solicitation Amendment 47PB0024R0049_0002.pdf PDF
5. Form B - Request for Construction Documents 2024 10 08.pdf PDF
8. Pre-Proposal Site Visit R1 2024 10 08.pdf PDF
7. Pre-Proposal Conference R1 2024 10 08.pdf PDF
74. Cost Accounting Standards Board Disclosure Statement CASB DS-1 OMB Form Number 0348-0051.pdf PDF
6. CBP Non-Disclosure Agreement Form 2024 10 08.pdf PDF
73. Contract Price Form Spreadsheet 2024 08 28.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 108 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT A

Statement of Work (SoW) for

Architect-Engineer (A/E) Contract for Construction Manager-as-Contractor (CMc)

Delivery Method

PROJECT IDENTIFICATION

Project Name Houlton, Maine - Land Port of Entry (LPOE)

Project No. LMEBIL01

Region New England Region (Region 1)

IDIQ A/E Firm TBD

Contract No. TBD

Task Order No. TBD

Building Nos. ME0661BH

ME0662BH

ME0663BH

LPOE Address Interstate 95 & US / Canada Border, Houlton, ME

Date October 25, 2022

A/E Statement of Work (v 2022/07) - CMc Delivery

U.S. Land Port of Entry, Highgate Springs, VT 05460

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

Design & Construction Division (1PC)

October 6, 2022

TABLE OF CONTENTS

Contents

1. SECTION 1- PROJECT DESCRIPTION

1.1. Location

1.2. Background and Previous Studies

1.2.1. Site

1.2.2. Existing Facility and Operations

1.2.3. Tenant Agencies

1.2.4. Additional Stakeholders

1.2.5. Maine Department of Transportation

1.2.6. Canada Border Services Agency

1.3. Existing Facilities

1.4. Proposed Facilities and Preferred Alternative

1.5. Project Goals and Objectives

1.5.1. Goals and Objectives – General

1.5.2. CBP Goals and Objectives

1.5.3. FDA Goals and Objectives

1.5.4. APHIS Goals and Objectives

1.5.5. GSA Goals and Objectives

2. SECTION 2- PROJECT TYPE AND DELIVERY METHOD

2.1. Project Type

2.2. CMc Delivery Method

2.3. Contract Parties and Contract Work

2.4. Professional Ethics and Standards of Practice

2.5. Project Team Roles and Responsibilities

2.5.1. A/E Team (Architect of Record)

2.5.2. Environmental Consulting Services (NEPA/EIS)

2.5.3. Construction Manager-as-agent (CMa)

2.5.4. Commissioning Provider (CxP)

2.5.5. Construction Manager-as-Constructor (CMc)

2.5.6. Art-in-Architecture (AiA)

2.5.7. Independent Scheduler

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

3. SECTION 3- GENERAL REQUIREMENTS

3.1. Owner’s Program of Requirements (POR)

3.1.1. BASE BID ITEMS

3.1.1.1. Main Port Building - Exterior Building

3.1.1.2. Main Port Building - Life Safety and Fire Protection Systems

3.1.1.3. Main Port Building - Accessibility

3.1.1.4. Main Port Building - Mechanical Systems

3.1.1.5. Main Port Building - Plumbing Systems

3.1.1.6. Main Port Building - Electrical Systems

3.1.1.7. FDA/GSA/APHIS Building - Exterior Building Envelope

3.1.1.8. FDA/GSA/APHIS Building - Life Safety and Fire Protection Systems

3.1.1.9. FDA/GSA/APHIS Building - Accessibility

3.1.1.10. FDA/GSA/APHIS Building - Mechanical Systems

3.1.1.11. FDA/GSA/APHIS Building - Plumbing Systems

3.1.1.12. Commercial Inspection Building - Exterior Building Envelope

3.1.1.13. Commercial Inspection Building - Life Safety and Fire Protection Systems

3.1.1.14. Commercial Inspection Building - Accessibility

3.1.1.15. Commercial Inspection Building - Mechanical Systems

3.1.1.16. Commercial Inspection Building - Plumbing Systems

3.1.1.17. Site Work - Sanitary Sewer System

3.1.1.18. Site Systems - Water Supply

3.1.2. Optional Bid Items

3.1.2.1. Primary Emergency Generator

3.1.2.2. Secondary Emergency Generator

3.1.2.3. EISA 438 Stormwater Retention

3.1.2.4. FDA/GSA/APHIS Building - Mechanical Systems

3.1.2.5. FDA/GSA/APHIS Building - Electrical Systems

3.1.2.6. Commercial Inspection Building - Mechanical Systems

3.1.2.7. Commercial Inspection Building - Electrical Systems

3.1.2.8. Site Systems - Pedestrian Circulation

3.1.2.9. Site Systems - Pavements

3.1.2.10. Site Systems - Landscaping

3.1.2.11. Site Systems - Structural

3.1.3. Tenant PORs

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

3.1.4. Spatial Data Management (SDM)

3.2. Project Duration and Schedule Milestone Dates

3.3. Reference Materials

3.3.1. Applicability of Reference Materials

3.3.2. Standards and Criteria Documents

3.4. Summary of Project Specific Clarifications to the P100 and/or other standards

3.5. Communications Plan

3.6. HSPD-12 Security Requirements (See also Section 3.7.7)

3.7. Electronic Project Management Information System (PMIS)

3.7.1. General PMIS Information

3.7.2. Project Collaboration and Documentation

3.7.3. Contents of PMIS

3.7.4. Equipment

3.7.5. Training

3.7.6. Support

3.7.7. HSPD-12 Security Requirements for PMIS/Kahua (See also Section 3.6)

3.8. Building Information Modeling (BIM)

3.8.1. BIM Coordination (See Section 5.2.4)

3.8.2. Design Reviews

3.9. Energy and Sustainability

3.9.1. Guiding Principles Checklist (GPC)

3.9.2. Energy Modeling and Performance

3.9.3. LEED® and SITES Certifications

3.9.4. GSA High Performance Building Tracking

3.9.5. Net-Zero Energy Performance

3.9.6. Embodied Carbon Reduction

3.9.7. Environmentally Preferable Paving Materials

3.9.7.1. Asphalt:

3.9.7.2. Low Embodied Carbon Concrete

3.10. Risk Management

3.10.1. Project Definition Rating Index (PDRI)

3.10.2. Cost and Schedule Risk Analysis

3.10.3. Climate Change Risk Management

3.10.4. Federal Flood Risk Management

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

3.11. Building Technology Services

3.12. Building Design Standard (BDS)

3.13. Art in Architecture (AiA)

3.14. Cost Management

3.14.1. General Requirements

3.14.2. Project Triage Tool Level Rating and Budget Activity (BA) Code

3.15. Partnering

3.16. Historic Preservation (RESERVED)

3.17. Commissioning

3.17.1. Phased Construction, Commissioning, Substantial Completion

3.18. Operational Excellence

4. SECTION 4-Site Acquisition Stage

4.1. Site Acquisition Phase

5. SECTION 5- Design Stage

5.1. Design Stage – GENERAL

5.1.1. Project Meetings

5.1.2. Document Review Process

5.1.3. Document Review Process – Dr. Checks

5.1.4. Design Quality Reviews (DQRs)

5.1.5. Value Management (VM) Studies and Workshops

5.1.6. Historic Preservation (RESERVED)

5.1.7. National Environmental Policy Act (NEPA)

5.1.8. Commissioning during Design

5.2. Pre-Design Phase

5.2.1. Review Reference Materials

5.2.1.1. Property Surveys

5.2.1.2. Geotechnical Report

5.2.1.3. Geothermal Study

5.2.2. Existing Conditions

5.2.3. Additional Studies

5.2.4. BIM Workshops (See Section 3.8.1)

5.2.5. Land Port of Entry Tours

5.2.6. Risk Analysis

5.3. Design Concept Phase

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

5.3.1. Design Concept Process

5.3.2. Design Charrette(s)

5.3.3. Border Wizard™ Analysis

5.3.4. Design Excellence Peer Reviews (DEPRs)

5.3.5. BIM-based Integrated Design Reviews (IDRs)

5.3.6. Project Readiness Checklist

5.3.7. Commissioner’s Concept Presentation

5.3.8. Construction Manager-as-constructor (CMc) Procurement

5.4. Design Development (DD) Phase

5.4.1. Mock-ups for Materials & Color Selection and Performance

5.5. System Testing

5.5.1. Design Development Process

5.6. Construction Documents (CD) Phase

5.6.1. Division 01 Specifications

5.6.2. Construction Documents Process

5.7. Construction Procurement Phase

6. SECTION 6- Construction Stage

6.1. Pre-Construction Start Coordination

6.1.1. Pre-Construction Meeting

6.1.2. BIM Coordination

6.1.3. Commissioning during Construction

6.2. Construction Phase

6.2.1. Construction Administration

6.2.1.1. Project Files and Record Keeping

6.2.1.2. Change Requests

6.2.1.3. Substitutions

6.2.1.4. Submittals

6.2.1.5. BIM Requirements

6.2.1.6. Periodic Site Walk-Throughs

6.2.1.7. Requests for Information (RFIs)

6.2.1.8. Value Management (VM) Studies

6.2.2. Construction Excellence Peer Reviews (CE PR)

6.2.3. Project Record Documents

6.2.4. Commissioning

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

6.3. Construction Closeout and Occupancy Phase

6.3.1. Pre-Turnover Process

6.3.2. Turnover Process

6.3.3. Final Record Documents

6.3.4. Commissioning

Attachments and Reference Documents

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

1. SECTION 1- PROJECT DESCRIPTION

This Statement of Work (SOW) is for architectural and engineering (A/E) services to design repairs and alterations to the Land Port of Entry (LPOE) for U.S. Customs and Border Protection at Houlton, ME.

The LPOE contains four buildings as follows:

1. ME0661BH (Main Port Building)

2. ME0662BH (CBP Commercial Inspection Building)

3. ME0663BH (FDA/GSA/APHIS Building)

4. ME0664BH (NII Building: Not Included in Project Scope)

The real estate assets included in the project are as follows:

Located at the northern terminus of Interstate 95 (I-95) in Houlton, Maine, the Houlton LPOE is a complex of four buildings (see above). The Main Port Building, CBP Commercial Inspection

Building and FDA/GSA/APHIS Building are owned and maintained by the GSA. The NII Building is maintained by CBP, however GSA has ultimate custody and control of that structure. The

Houlton LPOE is a 24-hour, 7-day, 365-days-per-year mission-critical facility; processing commercial and non-commercial vehicles entering and exiting the United States from the

Woodstock Border Crossing in Belleville, New Brunswick, Canada.

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

In general, the architectural and engineering (A/E) services include:

Design Stage Services Construction Stage Services

Detailed description of services is included in the remainder of the Statement of Work.

The Estimated Cost of Construction at Award for the project is $22,731,000. This will serve as the Design-to-Limit for the project.

1.1. Location

The LPOE at Houlton, ME is located at the northern terminus of Interstate 95. Aerial photo of existing site, with building identification:

NIC

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

1.2. Background and Previous Studies

GSA is working with its tenant agencies at the port – U.S. Customs and Border Protection (CBP), Food and Drug Administration (FDA), and the U.S. Department of Agriculture’s Animal and Plant

Health Inspection Service (APHIS) – to repair and alter the existing facility and systems, which are in need of upgrades and repairs.

The existing facility was constructed in 1985.

In 2021 GSA commissioned Oak Point Associates to perform a PDS scope of work to assess the state of the port. The study will be provided as an attachment to this scope of work.

1.2.1. Site

The Houlton LPOE is located at the northernmost terminus of Interstate 95 (I-95) at the border of

Houlton, ME USA and Bellevue, New Brunswick, CA (refer to the Boundary Survey Plan in the attachments). The Facility was constructed in 1985. The property consists of two parcels divided by the lane of I-95. The parcel between the north and southbound lanes of I-95 is 1.95 acres and the parcel to the north and west of the southbound lanes of I-95 is 3.94 acres. A right-of passage over paved surfaces was retained by the State of Maine weigh station that exists on the 3.94-acre parcel. There is no evidence of an access easement to the privately owned Deringer

Broker Building parcel to the north, but an access drive exists at the northeast corner of the property. The facility also has several existing utility and maintenance easements that cross I-95 northbound and southbound lanes. Another 1.84-acre parcel to the south of the existing 3.84-acre parcel was acquired by the United States of America from the State of Maine in 2005. The

2005 acquisition is subject to rights retained by the State of Maine for use as a truck weigh station, maintenance of drainage systems and slopes, and utility easements. A large wetland and waterbody to the west of the LPOE limits the viability of additional growth and property acquisition.

1.2.2. Existing Facility and Operations

The existing port facility currently consists of four buildings:

Building Nos. ME0661BH: 25,449 RSF (Main Port Building)

ME0662BH: 4,449 RSF (CBP Commercial Inspection Building)

ME0663BH 5,042 RSF (FDA/GSA/APHIS Building)

ME0000XX NII Building (CBP Owned, Not in Project)

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

1.2.3. Tenant Agencies

U.S. Customs & Border Protection (https://www.cbp.gov/)

U.S. Customs & Border Protection (CBP) is the main tenant at the port, occupying the majority of the facility. CBP’s operations are conducted in the Main Port Building, Primary Inspection, Secondary Inspection, the Commercial Inspection Building, and the Non-Invasive Inspection (NII) building.

FDA (https://www.fda.gov/)

The U.S. Food & Drug Administration (FDA) mission is to inspect food and agricultural products entering the U.S.

USDA – APHIS (https://www.aphis.usda.gov/aphis/ourfocus/importexport)

The U.S. Department of Agriculture’s Animal & Plant Health Inspection Service (APHIS).

GSA (https://www.gsa.gov/)

The U.S. General Services Administration (GSA) operates the building systems and maintains the port for its tenant agencies. While it has a small presence at the port, its role is important as it provides well-designed, functional, and energy efficient office space to tenants at the port. GSA is responsible for operation and maintenance of the buildings, mechanical systems, and other property management tasks such as custodial services, trash removal, landscape maintenance, and snow removal. These tasks are contracted out to an Operations & Maintenance (O&M) contractor.

1.2.4. Additional Stakeholders

Design and construction of the repair and alterations for the LPOE at Houlton shall be coordinated with the following stakeholders and projects:

A.N. Deringer (https://www.anderinger.com/) VERIFY CORRECT

BROKER

A.N. Deringer is the customs broker at the LPOE. The proposed project will not include any new facilities for Deringer. Anticipate coordination for the phasing of paving and site work.

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

1.2.5. Maine Department of Transportation

(MaineDOT) https://www.maine.gov/mdot/\

Maine Department of Transportation (MDOT) plans, develops, implements, and manages a statewide transportation network – including roads, bridges, railroads, airports, park-and-rides, bicycle and pedestrian facilities, and public transportation facilities and services.

1.2.6. Canada Border Services Agency

https://www.cbsa-asfc.gc.ca/menu-eng.html

Woodstock, New Brunswick Port of Entry

1.3. Existing Facilities

Refer to the 2021 PDS for information on the existing LPOE.

1.4. Proposed Facilities and Preferred Alternative

A PDS Study was completed for GSA in February 2021. The Preferred Alternative from the study includes design directives for repair and alteration to the building envelope(s), MEP systems, and site paving, among other elements. The existing LPOE will need to remain in operation while the new facility is being built.

Three concepts will be developed as appropriate for the Repair and Alteration items selected from the 2021 PDS. These concepts will be evaluated taking into consideration constructability, phasing to maintain 24/7 CBP operations, and the relative cost of each concept approach. Concepts should also provide the government with the ability to manage construction inflation risks by breaking the project into smaller components. Based on evaluation by GSA and other stakeholders a preferred alternative will be selected at the conclusion of this project phase.

In addition to meeting each agency’s Program of Requirements (POR), the design of the repair and alterations should address the Project Goals and Objectives described below in Section 1.5.

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

1.5. Project Goals and Objectives

1.5.1. Goals and Objectives – General

All goals and objectives are applicable to all stages of the project. The A/E shall document and track any evolution of these goals and objectives through the course of the project.

● Provide buildings and infrastructure that incorporate durable construction materials, sustainable design elements, and are climate resilient.

● Provide an upgraded port that is functional for each customer agency and their operations and interactions with the public.

● Perform design and construction operations efficiently and effectively using current technology tools for design, reviews, inspections, and project management processes.

● Adopt an integrated design approach that engages all team members and extends through all phases of the project.

● Meet specific sustainability goals, including:

o A Net Zero Ready facility o An 80% Fossil Fuel reduction o The use of GSA’s green proving ground technology o The use of key sustainable products o Achievement of LEED Gold if feasible based on limited repair and alteration scopes o Adherence to Guiding Principles for Sustainable Federal Buildings

(see Attachments) o Whole-building embodied carbon reduction

● Provide best value to GSA’s customer agencies, the community, and the

American taxpayer.

1.5.2. CBP Goals and Objectives

The new facility shall fulfill requirements of CBP’s POR and shall address problems and issues with the existing facility (see 2021 PDS).

1.5.3. FDA Goals and Objectives

The new facility shall fulfill requirements of FDA’s POR and shall address problems and issues with the existing facility. Goals include:

● Adequate parking for FDA personnel and visitors and access to the loading dock area for deliveries

● Charging stations for electric vehicles (EVs)

● Proper facilities and water supply for inspecting foodstuffs

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

● Proper facilities (e.g., platforms, rigging, safety harnesses) for inspections of commercial vehicles and trucks and their cargo

● Proper facilities collocated with but independent of CBP’s Commercial

Inspection operations.

1.5.4. APHIS Goals and Objectives

The new facility shall fulfill requirements of APHIS’ POR and shall address problems and issues with the existing facility. Goals include:

● Adequate parking for APHIS personnel and visitors

● Charging stations for electric vehicles (EVs)

● Proper indoor and outdoor facilities for inspecting plants, animals, and livestock

● Proper water supply for inspecting plants, animals, and livestock

● Outdoor platform for inspecting livestock on trucks

● Proper ventilation and floor finishes to resolve issues with humidity and slippery floors

● Wall finishes in inspection areas that are easy to clean and maintain

● Separate septic system for handling livestock waste from washing down inspection areas.

1.5.5. GSA Goals and Objectives

The new facility shall fulfill requirements of GSA’s POR and address problems and issues with the existing facility. Goals include:

● Adequate parking for GSA and its O&M contractors and subcontractors including charging stations for electric vehicles (EVs)

● Continuous availability of utilities (power, phone/data, water, sewer, and stormwater) and emergency power during phased construction

● Utility design to accommodate operational and emergency requirements of all port components

2. SECTION 2- PROJECT TYPE AND DELIVERY METHOD

2.1. Project Type

For the purpose of applying the submission requirements in Appendix A of GSA’s P100, “Facilities Standards for the Public Buildings Service,” and the cost estimating and schedule requirements of GSA’s P-120, “PBS Cost and Schedule Management Policy,” this project is defined as a Repair and Alteration project with funding from Budget Activity

BA55. The Funding Code for this project is PG11.

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

2.2. CMc Delivery Method

This project will utilize the Construction Manager-as-Contractor (CMc) delivery method.

At the end of the Concept Design Phase and prior to the beginning of the Design

Development Phase, GSA will hire a CMc who will work with the A/E through the Design

Development and Construction Documents stages to finalize the design. The CMc will work hand-in-hand with the selected architectural design and engineering team in order to assess constructability of the design as well as provide input and costing throughout the design development and construction document phases.

GSA has provided a reference (Federal Acquisition Policy FAR Part 536 subpart

536.71) to the GSA CMc Policy which details policies and procedures that GSA must follow with the CMc delivery method. The AE must review and understand these policies and procedures.

2.3. Contract Parties and Contract Work

The parties to this contract are the Architect/Engineer Contractor (A/E) and the United

States Government. For purposes of this contract, the office representing the Government is the General Services Administration (GSA), Public Building Service (PBS), Design &

Construction Division, Thomas P. O’Neill, Jr., Federal Building, 10 Causeway Street, 11th Floor, Boston, MA 02222, hereinafter referred to as GSA.

The individual authorized to act on the behalf of GSA in the administration of this contract is the GSA Contracting Officer (CO). The GSA Contracting Officer may delegate certain of his or her authorities to others (e.g., a Contracting Officer’s Representative (COR)), and if so, will notify the A/E in writing of the specific authorities delegated to and limitations placed upon the authorized individuals. The A/E shall not take any direction or act upon any information from anyone other than those having the requisite authority as confirmed by the GSA Contracting Officer’s written notification.

2.4. Professional Ethics and Standards of Practice

In the conduct of all activities required for or related to the performance of the contract work, the A/E shall conform to and uphold all established ethical principles and professional standards of practice governing the A/E’s segment of the A/E profession, including the International Union of Architects (UIA) Accord on Recommended

International Standards of Professionalism in Architectural Practice and the American

Council of Engineering Companies (ACEC) Ethical Guidelines.

2.5. Project Team Roles and Responsibilities

In the performance of the requirements of this contract, the A/E shall cooperate with and work in concert with other parties on the Project Delivery Team. The Project Delivery

Team will include other contractors, GSA personnel, customer agency representatives, and other stakeholders. GSA will develop, periodically update, and maintain throughout

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1) the course of the project a listing of the Project Delivery Team membership and respective roles and responsibilities. Other GSA-contracted major parties in the Project Delivery

Team and their overall roles and responsibilities are further identified in this Section.

2.5.1. A/E Team (Architect of Record)

The A/E shall provide at a minimum, experts in disciplines listed in GSA’s P100, “Facilities Standards for the Public Buildings Service,” and as otherwise required in this section (with credentials as indicated) as they apply to the Design and

Construction Stages of this project. The A/E shall utilize the personnel named in its offer to perform the services required under this contract. In the event that any of the personnel named in the accepted A/E proposal (incorporated into this contract by reference) become unavailable, the A/E shall promptly submit a detailed explanation of the circumstances necessitating the proposed substitution, a complete written resume for the proposed substitution, and any other information necessary for GSA to approve or disapprove the substitution.

See also FAR 52.244-4 regarding subcontractors and outside associates and consultants.

2.5.2. Environmental Consulting Services (NEPA/EIS)

GSA will contract for services for a consultant to lead the GSA through the NEPA process.

2.5.3. Construction Manager-as-agent (CMa)

The Construction Manager-as-agent (CMa) is responsible for ensuring that GSA’s interests as the owner are well served. In this regard, the CMa will assist GSA in ensuring that the requirements of GSA and its tenant agencies, with regard to scope, schedule, budget, quality, and other aspects of the project, are met throughout design and construction of the project. The CMa will serve as a facilitator and coordinator of the activities of all parties to ensure that the project execution proceeds according to plan. The CMa will perform services during the Design, Construction, and Tenant

Occupancy Stages to ensure that the design is built correctly during construction, realized in the completed facility, and conveyed successfully into facility management, operation, and maintenance. The CMa will also serve as GSA’s Value Management

(VM) consultant. The CMa will perform inspections during all phases of the construction stage. The CMa will participate in the commissioning process and shall coordinate with GSA and the Commissioning Provider (CxP) to identify appropriate commissioning program goals and to develop supporting inspection and testing practices to meet the objectives of the project commissioning plan. The specific activities, tasks, and deliverables required of the CMa are further delineated in the

CMa contract.

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

2.5.4. Commissioning Provider (CxP)

The Commissioning Provider (CxP) is responsible for providing documented confirmation that the completed facility fulfills the functional and performance requirements of GSA and its tenant agencies, the facility occupants, and the facility operators. The CxP will perform work as necessary to verify and document compliance with the GSA performance objectives throughout design, construction, start-up, and the initial period of operation. The specific activities, tasks, and deliverables required of the CxP are further delineated in the CxP contract.

2.5.5. Construction Manager-as-Constructor (CMc)

GSA will use a CMc delivery method for this project (see Section 2.2 – CMc Delivery

Method). The CMc is responsible for construction of the project in accordance with the construction documents during the Construction Stage. The CMc will also provide services during the Design Stage, including reviews of the schedule, budget, and constructability of the design.

During the design development (DD) and construction document (CD) phases, the A/E and the CMc will collaborate on the design, constructability issues, schedule, cost, through a process that is similar to value management. The goal of this collaboration is to establish a final Estimated Cost of Work that does not exceed the design to limit.

The CMc's involvement during the project design stage offers the government the ability to identify current market conditions concerning labor and material availability, constructability issues, and any phasing and sequencing impacts.

Ideally, the A/E and its subcontractors will communicate freely with the CMc and its trade subcontractors, and vice versa. This will ensure mutual understanding of both the A/E's design intent and the CMc's means and methods, and thus ensure greater certainty in pricing the construction work. It also increases the likelihood that design errors and omissions are recognized and resolved during design. In addition, this collaboration takes place during a time that does not significantly impact the construction schedule and that can result in expedited production and review of shop drawings once construction commences.

The CMc contractor shall review and become familiar with the scope of services under the A/E’s contract, especially the various standards, guidelines, policies, and documents that the A/E is required to follow in order to develop the design and construction documents. This review and familiarization is vitally important during the

Design Phase Services because provision of constructability and cost estimation reviews of the A/E’s design-related submissions is the main task of the CMc Contractor during the Design Phase Services. At its core, the CMc Contractor will help to ensure that the design and construction documents will enable the Government to exercise the Guaranteed Maximum Price (GMP) Option at a price that is at or below the GMP.

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

2.5.6. Art-in-Architecture (AiA)

GSA’s Art in Architecture program entails commissioning artists to create publicly scaled and permanently installed works of art that are appropriate to the diverse uses and architectural vocabularies of new and substantially modernized federal buildings, courthouses, and Land Ports of Entry. The intent is to achieve integration of art and architecture. The artist(s) may become involved in the design of building or sitework elements and will work collaboratively with the A/E Team. GSA will select and commission one or more artists during the Design Concept Phase to create new artwork for the port.

2.5.7. Independent Scheduler

The GSA may engage services of an independent scheduler to provide schedule review and analysis.

3. SECTION 3- GENERAL REQUIREMENTS

The General Requirements apply to all project phases. Some of the requirements noted in this section may be subject to the exercise of contract option(s).

As a general matter, GSA’s P100, “Facilities Standards for the Public Buildings Service,” is the primary document that governs the A/E’s performance of work. Other policies and procedures

(e.g., tenant agency design guides and GSA’s P-120 for cost estimating) provide detailed requirements and procedures with which the A/E shall also comply. When options are presented in the tenant design guides, the AE shall confirm and document the path forward. The purpose of this A/E Statement of Work is to describe services that the A/E shall provide in addition to the services outlined in other documents (refer to Section 3.3, Reference Materials).

3.1. Owner’s Program of Requirements (POR)

Existing work is ongoing at the Houlton LPOE. This new work will be incorporated into all new designs to the maximum extent possible in such a fashion that replacement of this work is not required. This work includes the following:

Replacement of the 3 primary booths

Expansion of the work area and booth replacement at Lane 1

Port Hardening

Run-by Siren

The plans and specifications for this work are included as attachments to this Statement of

Work.

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

Future work is also planned at the Houlton LPOE. This work includes the following:

Modular Firing Range Installation

Construction of a New Commercial Inspection Building (CIB)

This future work is unfunded at this time. However, future site locations have been identified on the property. A photo has been marked up showing the future locations on the existing LPOE property. A copy of which is included as an attachment to this Statement of Work. All design work under this statement of work, will limit impacts to these areas to allow future construction.

In addition, all design energy models and electrical loading should include this future work in the power requirements for the LPOE.

The following is the scope of the items which will be included in the Repair and Alteration

Design. These items will be designed as Base Bid Items and Optional Bid Items. The purpose of the Base Bid and Option Bid items is to provide a means to control costs and the associated bid risk to keep the project within the allotted budget. The items listed are not complete but notional and may be modified to meet project goals and other design requirements. These items are listed in priority order.

3.1.1. BASE BID ITEMS

3.1.1.1. Main Port Building - Exterior Building

Envelope The exterior, while in relatively good condition, will require the following renovations in order to maintain its integrity:

• Replace Existing Roof System

A new adhered roof system, complete with polyisocyanurate insulation, coverboard, PVC membrane, flashings, and metal fascia, is recommended. As part of the roof replacement project, roof drain replacements with heat trace systems should be provided. Increasing the depth of the roof insulation would provide some benefits in the thermal performance of the building and will be investigated and provided if LCCA determines added value. A fall protection system will be provided at the rooftop mounted equipment.

• Replace Existing Stone/Concrete Façade Panels

The existing stone/concrete façade panels are at the end of their service life and should be replaced. This type of panel is only produced by an extremely limited number of manufacturers and are no longer commonly available. In addition, the existing panels are applied directly over the exterior metal studs and are serving as both exterior sheathing and finishes, which greatly increases the likelihood of water infiltration and possible mold growth in the insulation cavity.

GSA personnel indicated that mold growth within the cavity has indeed been detected during past renovations projects. In order to protect the building and increase the building’s thermal performance it is recommended that the panels be carefully removed so that the existing exterior metal studs may be reused, an exterior glass mat gypsum board sheathing, air-barrier

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1) with an insulated metal wall panel should be evaluated along with other possible solutions.

Replacement of the second-floor stone/concrete façade will also require that the existing second floor aluminum storefront and windows be replaced. Bullet resistant panel and glass requirements shall be evaluated per the requirements of the LPOE Design Guide.

• Replace Existing Aluminum Storefront, Windows, and Entrances

The existing aluminum storefront, windows, and entrances are also approaching the end of their service life. Thermally broken aluminum storefront systems should be provided with insulated laminated glazing. Bullet resistant requirements of the LPOE Design Guide will be met.

• Remove and Replace Exterior Hollow Metal Doors and Frames and Building Sealants.

As part of this item, exterior metal elements shall be prepped and painted including exposed structural items, security bollards and garage doors.

3.1.1.2. Main Port Building - Life Safety and Fire

Protection Systems The following Life Safety and Fire Protection items are to be included in the design:

• Fire Alarm System

The existing fire alarm system shall be replaced with a combination fire alarm and voice emergency communication system. The existing system does not have voice capabilities, is not addressable, and does not have a layout nor mounting heights in compliance with the current NFPA 72. It has also been noted by building management to have false alarms.

Replacing the system will improve alerting the occupants and the responding fire department to fire events.

• Sprinkler System

A sprinkler system will be added to the building which is currently non-sprinklered. This improves the life safety and property protection measures.

• Fireproofing

Locations of missing fireproofing were found at utility supports throughout and in the large main lobby where the gypsum installers removed large sections to install top track during lobby renovations. This is recommended to be replaced to maintain the original rated type of construction of the building.

• Firestopping

There is minimal firestopping throughout the building. This is necessary to be installed to maintain the integrity of fire rated separations, in particular at the two exit stair enclosures and at the elevator machine room.

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

3.1.1.3. Main Port Building - Accessibility

• Elevator Modernization

Remove the existing hydraulic passenger elevator and replace with a machine room-less hydraulic elevator system.

• Stair to Roof

Access to the roof is currently via ladder. To meet PBS standards a permanent stair is required to access the roof top mounted mechanical equipment. In order to meet this requirement, the existing stair will need to be extended to provide access to the roof level. Remove roof deck at existing stair and provide structural framing, exterior enclosure envelope, roofing system, concrete filled metal pan stair to roof.

3.1.1.4. Main Port Building - Mechanical Systems

The entire HVAC system in the Main Port Building should be analyzed and upgrades recommended including the following:

• Replace Heating System

Alternatives for the replacement shall be developed. A Geothermal study for the Houlton LPOE is ongoing and geothermal should be considered as an option.

• Replace Cooling and Ventilation System

The first and second floor each have their own split system air handling unit which are responsible for cooling and providing ventilation. The systems are beyond the end of their usable life and in poor condition. They do not provide adequate temperature control for space comfort. They also do not have ventilation energy recovery. To solve these issues and meet energy requirements develop options including the use of geothermal systems.

• Replace Vehicle Inspection Bay Heating and Ventilation System

The heating and ventilation system and exhaust fans in the vehicle inspection bay are in poor condition and should be replaced in their entirety.

• Provide Building Automation System (BAS)

Provide a BAS system to control and monitor the HVAC systems throughout the building. BAS

System shall be a Niagara system. The BAS system will be in compliance with the standards of

PBS P100, GSA’s standardized National Computerized Maintenance Management System

(NCMMS), and Construction Operations Building Information Exchange (COBie) format. This will require approximately 100 control points. This will include points to tie into the fire alarm system for required HVAC points. Additionally, the points include water metering required by

P100.

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

3.1.1.5. Main Port Building - Plumbing Systems

• Replace Roof Drains

Heat trace freeze protections with monitoring will be provided for freeze protection.

• Provide Water Service Isolation Valves

Provide isolation valves at various locations in order to isolate parts of the building to make repairs simpler.

• Upgrade Domestic Hot Water System

The existing hot water system is in poor condition and does not reach the entire building.

Various smaller water heaters are located throughout the building. PBS P100 requires that 30% of the domestic water be heated by solar collectors if it is life cycle cost effective. Use of a geothermal system to provide domestic hot water should also be considered.

• Upgrade Plumbing Fixtures to Low-Flow

Comply with PBS P100 fixture requirements (0.5 gpm urinals, metered 0.25 gpm per cycle lavatories). Water closet requirement is 1.28 gpm but this may cause problems with the existing sanitary system, as it was not designed with 1.28 GPM flush valves in mind. The lower water flow can create blockages downstream from the fixtures if the existing sanitary lines do not have adequate slope or are damaged. Provide dual-flush (1.6gpm/1gpm per flush) water closets.

Evaluate the existing sanitary sewer system to evaluate whether this problem exists or not.

3.1.1.6. Main Port Building - Electrical Systems

• Upgrade Main Service - Main Switchboard

A new service entrance is recommended for the Main Port Building because the MSB is 35 years old, is approaching the end of its useful life and parts may be less available. The MSB contains only a very limited amount of spare capacity for future expansion. This work will require phasing, temporary power, and shutdowns to perform electrical cut-over. Every attempt will be made through the design to minimize building outages and disruption to the tenant.

• Replace Branch Circuit Panelboards and Feeders

The branch circuit panelboards and associated feeders are recommended for replacement.

• Replace Remaining Fluorescent Fixtures With LED and Provide Controls

The remaining fluorescent fixtures in the building are recommended to be replaced with LED fixtures for energy savings. Occupancy sensors are also recommended to comply with ASHRAE

90.1 and for energy savings.

• Replace Exterior Building Lighting and Provide Additional Exterior Building Lighting

Existing building-mounted fixtures, both wall and canopy, are recommended to be replaced with

LED fixtures. Lamps have been replaced with lamps of different color temperatures, lenses are

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1) dirty, cracked, and yellowed, and reflectors have been damaged. Fixtures will include battery backup at building egress locations to comply with NFPA 101. LED fixtures will comply with

ASHRAE 90.1 requirements and provide energy savings. At the time of fixture replacement, circuits will be switched to the generator panelboard so exterior fixtures are connected to the generator system.

• Replace Site Fixtures on 80-Foot Poles with LED

It is recommended that the pole mounted site fixtures with 1000W lamps be replaced with LED fixtures for energy savings. The LED fixtures will also improve visibility while reducing overall site glare.

• Provide Lightning Protection System

A lightning protection system is recommended for the building based on the requirements of the building being continuously occupied and continuity of service. The system will be designed according to NFPA 780 and will consist of roof mounted arrestors, down conductors on the exterior of the building and ground rods connecting the system to earth.

• Provide EV Charging Stations

Design and install EV Charging Stations for LPOE and GSA vehicles.

3.1.1.7. FDA/GSA/APHIS Building - Exterior Building

Envelope

• Replace Existing Roof System

A new adhered roof system, complete with polyisocyanurate insulation, cover board, PVC membrane, flashings, and metal fascia, is recommended. As part of the roof replacement project, roof drain replacements with heat trace systems should be provided. Increasing the depth of the roof insulation would provide some benefits in the thermal performance of the building and will be investigated and provided if LCCA determines added value. A fall protection system will be provided at the rooftop mounted equipment.

• Replace Existing Stone/Concrete Façade Panels

The existing stone/concrete façade panels are at the end of their service life and should be replaced. This type of panel is only produced by an extremely limited number of manufacturers and are no longer commonly available. In addition, the existing panels are applied directly over the exterior metal studs and are serving as both exterior sheathing and finishes, which greatly increases the likelihood of water infiltration and possible mold growth in the insulation cavity.

GSA personnel indicated that mold growth within the cavity has indeed been detected during past renovations projects. In order to protect the building and increase the building’s thermal performance it is recommended that the panels be carefully removed so that the existing exterior metal studs may be reused, an exterior glass mat gypsum board sheathing, air-barrier with an insulated metal wall panel should be evaluated along with other possible solutions.

Replacement of the second floor stone/concrete façade will also require that the existing second

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1) floor aluminum storefront and windows be replaced. Bullet resistant panel and glass requirements shall be evaluated per the requirements of the LPOE Design Guide.

• Replace Existing Aluminum Storefront, Windows, and Entrances

The existing aluminum storefront, windows, and entrances are also approaching the end of their service life. Thermally broken aluminum storefront systems should be provided with insulated laminated glazing. Bullet resistant requirements of the LPOE Design Guide will be met.

• Remove and Replace Exterior Hollow Metal Doors and Frames and Building Sealants.

As part of this item, exterior metal elements shall be prepped and painted including exposed structural items, security bollards and garage doors.

3.1.1.8. FDA/GSA/APHIS Building - Life Safety and

Fire Protection Systems The following Life Safety and Fire Protection items are to be included in the design:

• Fire Alarm System

The existing fire alarm system shall be replaced with a combination fire alarm and voice emergency communication system.

• Sprinkler System

The sprinkler system will be upgraded to a NFPA 13 system from the existing NFPA 13D system.

• Firestopping

There is minimal firestopping throughout the building. This is necessary to be installed to maintain the integrity of fire rated separations, in particular at the two exit stair enclosures and at

3.1.1.9. FDA/GSA/APHIS Building - Accessibility

• Stair to Roof

Access to the roof is currently via ladder. To meet PBS standards a permanent stair is required to access the roof top mounted mechanical equipment. In order to meet this requirement, the existing stair will need to be extended to provide access to the roof level. Remove roof deck at

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

3.1.1.10. FDA/GSA/APHIS Building - Mechanical

Systems

• Upgrade Building Automation System

The BAS system in this building shall be replaced and connected to the new Niagara BAS

System for the Main Port Building.

3.1.1.11. FDA/GSA/APHIS Building - Plumbing

Systems

Heat trace freeze protections with monitoring will be provided for freeze protection.

3.1.1.12. Commercial Inspection Building - Exterior

Building Envelope

• Replace Existing Roof System

A new adhered roof system, complete with polyisocyanurate insulation, cover board, PVC membrane, flashings, and metal fascia, is recommended. As part of the roof replacement project, roof drain replacements with heat trace systems should be provided. Increasing the depth of the roof insulation would provide some benefits in the thermal performance of the building and will be investigated and provided if LCCA determines added value. A fall protection system will be provided at the rooftop mounted equipment.

• Replace Existing Stone/Concrete Façade Panels

The existing stone/concrete façade panels are at the end of their service life and should be replaced. This type of panel is only produced by an extremely limited number of manufacturers and are no longer commonly available. In addition, the existing panels are applied directly over the exterior metal studs and are serving as both exterior sheathing and finishes, which greatly increases the likelihood of water infiltration and possible mold growth in the insulation cavity.

GSA personnel indicated that mold growth within the cavity has indeed been detected during past renovations projects. In order to protect the building and increase the building’s thermal performance it is recommended that the panels be carefully removed so that the existing exterior metal studs may be reused, an exterior glass mat gypsum board sheathing, air-barrier with an insulated metal wall panel should be evaluated along with other possible solutions.

Replacement of the second floor stone/concrete façade will also require that the existing second floor aluminum storefront and windows be replaced. Bullet resistant panel and glass requirements shall be evaluated per the requirements of the LPOE Design Guide.

• Replace Existing Aluminum Storefront, Windows, and Entrances

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

The existing aluminum storefront, windows, and entrances are also approaching the end of their service life. Thermally broken aluminum storefront systems should be provided with insulated laminated glazing. Bullet resistant requirements of the LPOE Design Guide will be met.

• Remove and Replace Exterior Hollow Metal Doors and Frames and Building Sealants.

As part of this item, exterior metal elements shall be prepped and painted including exposed structural items, security bollards and garage doors.

3.1.1.13. Commercial Inspection Building - Life Safety

and Fire Protection Systems The following Life Safety and Fire Protection items are to be included in the design:

• Fire Alarm System

The existing fire alarm system shall be replaced with a combination fire alarm and voice emergency communication system.

• Sprinkler System

A sprinkler system should be added to the building which is currently non-sprinkled.

• Firestopping

There is minimal firestopping throughout the building. This is necessary to be installed to maintain the integrity of fire rated separations, in particular at the two exit stair enclosures and at

3.1.1.14. Commercial Inspection Building -

Accessibility

• Stair to Roof

Access to the roof is currently via ladder. To meet PBS standards a permanent stair is required to access the roof top mounted mechanical equipment. In order to meet this requirement, the existing stair will need to be extended to provide access to the roof level. Remove roof deck at

Project No. NVT: LMEBIL01

Contract No. TBD

U.S. General Services Administration

New England Region (Region 1)

3.1.1.15. Commercial Inspection Building -

Mechanical Systems

• Upgrade Building Automation System

The BAS system in this building shall be replaced and connected to the new Niagara BAS

System for the Main Port Building.

3.1.1.16. Commercial Inspection Building - Plumbing

Systems

Heat trace freeze protections with monitoring will be provided for freeze protection.

3.1.1.17. Site Work - Sanitary Sewer System

Design the replacement of the Sanitary Sewer System. Options to evaluate for the design are as follows:

o Option 1, replacement of existing on-site wastewater disposal system includes replacement of the disposal field in the same location and footprint, replacement of the pump station controls and pumps with modernized controls and slide…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .