This is a WebAIM Short Form Task Group Instruction (TGI) dated 06-MAY-2025 for the USS Blue Ridge, focusing on a Deaerating Feed Tank Tightness & Operational Test. The document specifies a technical task (TGI No. 25571-3-300KTR) for testing and operational verification of a Deaerating Feed Tank (S/A 88714D - KTR) within the ship's system 25571. The task involves three primary work elements: contractor work (22/KE), Quality Assurance work (33/G1), and Support/Facility work (EXSA), all of which are to accomplish and document the tightness and operational test in accordance with the referenced technical procedure TP 25571-3-300KTR. The document is marked FOUO (For Official Use Only) and includes preparation details from Kamimura, Yousuke and approval by Ohta, Jason Y. from code 246.2, with the task managed by zone manager Takahashi, Yasuhiko.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
06-MAY-2025 1310
20.14.15.2.9020 (September 2024) ICN: 3819P43701 KeyOp: T01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 25571-3-300KTR TT T 6 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25571
CU PHASE TITLE: DEAERATING FEED TANK (T & OP), S/A 88714D - KTR
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 2
EXSAZBG1
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
KAMIMURA, YOUSUKE 246.2 3152434987 21-APR-2025
APPROVED BY: CODE: PHONE: DATE:
OHTA, JASON Y. 246.2 3152435901 02-MAY-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EXSA-ZBG1
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
TAKAHASHI, YASUHIKO U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
437C1101
Tightness & Operational Test for DEAERATING FEED TANK - KTR.
TGI Short Form
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
06-MAY-2025 1310
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P43701 KeyOp: T01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 25571-3-300KTR TT T 6 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25571
CU PHASE TITLE: DEAERATING FEED TANK (T & OP), S/A 88714D - KTR
FOUO Pg 2 of 2
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 TP 25571-3-300KTR DEAERATING FEED TANK (T
& OP) - KTR
LAT Y
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
(V) Contractor work:
Accomplish/document the tightness & operational test in accordance with reference, TP 25571-3-300KTR.
22/KE PC N
(G) QA work:
Accomplish/document the tightness & operational test in accordance with reference, TP 25571-3-300KTR.
33/G1 QA N
(S) S/F work:
Accomplish/document the tightness & operational test in accordance with reference, TP 25571-3-300KTR.
/ EXSA N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P43701 KEY OP: T01
File details come from the government source that posted it. Updated .