3819P25001T02_c0v0_TGI.pdf
PDF 95 KB Posted
- Solicitation number
- N6264925RA059-0008
About this file
This document is a WebAIM Short Form Task Group Instruction (TGI) for an operational test of the Forced Draft Blower System on the USS Blue Ridge, dated 14-APR-2025. The instruction is specifically for a Contractor (KTR) task with TGI number 25111-3-300KTR, associated with Project 19P and System 25111. The primary objective is to accomplish and document the operational test in accordance with reference document TP 25111-3-300KTR, with work to be performed by three groups: Contractor (V), Quality Assurance (G), and Shop/Support Function (S). The document includes sections for task description, references, and a material list, though no specific materials are listed in this instance. Key personnel include Harada Kazuya (Prepared By), Sean F. Irei (Approved By), and Yasuhiko Takahashi (Zone Manager).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
14-APR-2025 0900
20.14.15.2.9020 (September 2024) ICN: 3819P25001 KeyOp: T02
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 25111-3-300KTR TT T 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25111
CU PHASE TITLE: FORCED DRAFT BLOWER SYS 1A1 (OP), S/A 98081D - KTR
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 2
EXSAZC89
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
HARADA, KAZUYA 246.2 3152432048 26-MAR-2025
APPROVED BY: CODE: PHONE: DATE:
IREI, SEAN F. 246.2 3152437427 12-APR-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EXSA-ZC89
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
TAKAHASHI, YASUHIKO U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
250A0001
Operational Test for Forced Draft Blower System.
TGI Short Form
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
14-APR-2025 0900
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P25001 KeyOp: T02
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 25111-3-300KTR TT T 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25111
CU PHASE TITLE: FORCED DRAFT BLOWER SYS 1A1 (OP), S/A 98081D - KTR
FOUO Pg 2 of 2
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 TP 25111-3-300KTR FORCED DRAFT BLOWER
SYS (T & OP) - KTR
LAT Y
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
(V) Contractor work:
Accomplish/document the operational test in accordance with reference, TP 25111-3-300KTR.
(G) QA work:
Accomplish/document the operational test in accordance with reference, TP 25111-3-300KTR.
(S) S/F work:
Accomplish/document the operational test in accordance with reference, TP 25111-3-300KTR.
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P25001 KEY OP: T02
File details come from the government source that posted it. Updated .