Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 80KSC020R0024
- Agency
- Kennedy Space Center National Aeronautics and Space Administration
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 238220 Plumbing, Heating, and Air-Conditioning Contractors
- Place of performance
- FL 32899 USA
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks proposals to upgrade the Environmental Control System at Launch Complex 39B for the National Aeronautics and Space Administration's Kennedy Space Center in Florida. The upgrade is required to provide conditioned purge air to support crewed Space Launch System Artemis II missions. Key requirements of the solicitation include replacing the existing cooling tower and ductwork, adding new high pressure ducts and heaters, replacing filter housings and valves, modifying gaseous nitrogen piping and controls systems hardware, and installing new humidifiers. Proposals will be evaluated using lowest price technically acceptable criteria, and are due by July 14, 2020.
There is no set-aside designation specified. The primary NAICS code is 237990 and PSC code R499 cover the environmental control work. Potential contractors include Precision Mechanical, Chrome Electric and Santis Engineering who attended the June 16, 2020 site visit. The place of performance is the Kennedy Space Center in Brevard County, Florida. The estimated value is under $150 million based on the scope of replacing major ECS components, and work must be completed within 180 days of the Artemis I launch notice to proceed on July 1, 2021.
Notice text
9 versions
Update #9 · Latest ·
NASA has a need to upgrade the Environmental Control (ECS) at Launch Complex (LC) 39B. The upgraded ECS is required to support the crewed Space Launch System (SLS) Artemis II mission. The project will include the following work:
The upgrade of the ECS at LC 39B. The modified ECS will provide conditioned clean purge air to various compartments of the new SLS vehicle supporting Artemis missions. The upgrade scope includes replacement of the existing cooling tower, relocation of existing ductwork, heaters, and instrumentation, addition of new heaters and high pressure ducts, replacement of filter housings and valves, revising existing gaseous nitrogen piping including replacement of heritage aluminum gaseous nitrogen piping with stainless steel, modification of existing controls systems hardware, installation of new humidifiers, and incidental related work.
Solicitaiton Amendment 0001 is released to:
A) Update the 1442, Section B.1, Section L.9, and Section L.10, see attached Slip Pages; 5 pages.
B) Include Section L Appendix 6 Badging Request Form (Includes TAA), see attached Appendix; 2 pages.
End of solicitation changes.
Solicitation Amendment 0002 is released to:
A) Update the email address in Section L.9 (e) to KSC-NE-Badging@mail.nasa.gov; see attached Slip Page; 1 page.
End of solicitation changes.
Solicitation Amendment 0003 is released to:
A) Provide the "Example Submittal Matrix" as described in Attachment J-A-2, paragraph (d); 1 page attached.
B) Provide the "ECS Site Visit Attendance," listing all participants present for the site visit on June 16, 2020; 1 page attached.
C) Correct Attachment J-A section numbering, from J-A-21 to J-A-17 and J-A-22 to J-A-18; see
attached Slip Pages; 2 pages.
D) Remove unintended and incomplete section at Attachment J-B-44, renumber remaining
sections J-B-44 to J-B-49; see attached Slip Pages; 3 pages.
End of solicitation changes.
Solicitation Amendment 0004 is released to:
A) Update proposal due date. Proposals are due July 14, 2020 by 2:00 PM EST, see attached "Slip Pages," 4 pages attached.
B) Provide Government answers to submitted questions; see attached "Questions & Answers 1," 1 page attached.
C) Update solicitation section F.1, paragraph (c); see attached "Slip Pages," 4 pages attached.
D) Update solicitation section L.13, paragraph (a); see attached "Slip Pages," 4 pages attached.
E) Update solicitation section L.18, paragraph (b)(4); see attached “Slip Pages,” 4 pages attached.
F) Corrected various spacing, punctuation, capitalization, and other typographical errors throughout the solicitation.
End of solicitation changes.
Solicitation Amendment 0005 is released to:
A) Provide Government answers to submitted questions; see attached "Questions & Answers 2," 1 page attached.
B) Update solicition Standard Form 1442 cover page page count;see attached “Slip Pages,” 5 pages attached.
C) Update solicitation section C.2 paragraph (b); see attached "Slip Pages," 5 pages attached.
D) Update solicitation and added multiple paragraphs in section M.1 (c)(4); see attached “Slip Pages,” 5 pages attached.
End of solicitation changes.
Solicitation Amendment 0006 is released to:
A) Provide Government answers to submitted questions; see attached "Questions & Answers 3," 3 pages attached.
B) Update solicition Standard Form 1442 cover page page count; see attached “Slip Pages,” 3 pages attached.
C) Update solicitation section C.2 paragraph (b); see attached "Slip Pages," 3 pages attached.
End of solicitation changes.
Solicitation Amendment 0007 is released to:
A) Provide updated Attachment J-C Wage Determination, dated July 3, 2020; 6 pages attached.
B) Update solicitation Section J table; see attached "Slip Page," 1 page attached.
End of solicitation changes.
Solicitation Amendment 0008 is released to:
A) Provide Government answers to submitted questions; see attached "Questions & Answers 4," 1 page attached.
B) Update solicitation section C.2 paragraph (b); see attached "Slip Page," 1 page attached.
End of solicitation changes.
Update #8 ·
NASA has a need to upgrade the Environmental Control (ECS) at Launch Complex (LC) 39B. The upgraded ECS is required to support the crewed Space Launch System (SLS) Artemis II mission. The project will include the following work:
The upgrade of the ECS at LC 39B. The modified ECS will provide conditioned clean purge air to various compartments of the new SLS vehicle supporting Artemis missions. The upgrade scope includes replacement of the existing cooling tower, relocation of existing ductwork, heaters, and instrumentation, addition of new heaters and high pressure ducts, replacement of filter housings and valves, revising existing gaseous nitrogen piping including replacement of heritage aluminum gaseous nitrogen piping with stainless steel, modification of existing controls systems hardware, installation of new humidifiers, and incidental related work.
Solicitaiton Amendment 0001 is released to:
A) Update the 1442, Section B.1, Section L.9, and Section L.10, see attached Slip Pages; 5 pages.
B) Include Section L Appendix 6 Badging Request Form (Includes TAA), see attached Appendix; 2 pages.
End of solicitation changes.
Solicitation Amendment 0002 is released to:
A) Update the email address in Section L.9 (e) to KSC-NE-Badging@mail.nasa.gov; see attached Slip Page; 1 page.
End of solicitation changes.
Solicitation Amendment 0003 is released to:
A) Provide the "Example Submittal Matrix" as described in Attachment J-A-2, paragraph (d); 1 page attached.
B) Provide the "ECS Site Visit Attendance," listing all participants present for the site visit on June 16, 2020; 1 page attached.
C) Correct Attachment J-A section numbering, from J-A-21 to J-A-17 and J-A-22 to J-A-18; see
attached Slip Pages; 2 pages.
D) Remove unintended and incomplete section at Attachment J-B-44, renumber remaining
sections J-B-44 to J-B-49; see attached Slip Pages; 3 pages.
End of solicitation changes.
Solicitation Amendment 0004 is released to:
A) Update proposal due date. Proposals are due July 14, 2020 by 2:00 PM EST, see attached "Slip Pages," 4 pages attached.
B) Provide Government answers to submitted questions; see attached "Questions & Answers 1," 1 page attached.
C) Update solicitation section F.1, paragraph (c); see attached "Slip Pages," 4 pages attached.
D) Update solicitation section L.13, paragraph (a); see attached "Slip Pages," 4 pages attached.
E) Update solicitation section L.18, paragraph (b)(4); see attached “Slip Pages,” 4 pages attached.
F) Corrected various spacing, punctuation, capitalization, and other typographical errors throughout the solicitation.
End of solicitation changes.
Solicitation Amendment 0005 is released to:
A) Provide Government answers to submitted questions; see attached "Questions & Answers 2," 1 page attached.
B) Update solicition Standard Form 1442 cover page page count;see attached “Slip Pages,” 5 pages attached.
C) Update solicitation section C.2 paragraph (b); see attached "Slip Pages," 5 pages attached.
D) Update solicitation and added multiple paragraphs in section M.1 (c)(4); see attached “Slip Pages,” 5 pages attached.
End of solicitation changes.
Solicitation Amendment 0006 is released to:
A) Provide Government answers to submitted questions; see attached "Questions & Answers 3," 3 pages attached.
B) Update solicition Standard Form 1442 cover page page count;see attached “Slip Pages,” 3 pages attached.
C) Update solicitation section C.2 paragraph (b); see attached "Slip Pages," 3 pages attached.
End of solicitation changes.
Solicitation Amendment 0007 is released to:
A) Provide updated Attachment J-C Wage Determination, dated July 3, 2020; 6 pages attached.
B) Update solicitation Section J table; see attached "Slip Page," 1 page attached.
End of solicitation changes.
Update #7 ·
NASA has a need to upgrade the Environmental Control (ECS) at Launch Complex (LC) 39B. The upgraded ECS is required to support the crewed Space Launch System (SLS) Artemis II mission. The project will include the following work:
The upgrade of the ECS at LC 39B. The modified ECS will provide conditioned clean purge air to various compartments of the new SLS vehicle supporting Artemis missions. The upgrade scope includes replacement of the existing cooling tower, relocation of existing ductwork, heaters, and instrumentation, addition of new heaters and high pressure ducts, replacement of filter housings and valves, revising existing gaseous nitrogen piping including replacement of heritage aluminum gaseous nitrogen piping with stainless steel, modification of existing controls systems hardware, installation of new humidifiers, and incidental related work.
Solicitaiton Amendment 0001 is released to:
A) Update the 1442, Section B.1, Section L.9, and Section L.10, see attached Slip Pages; 5 pages.
B) Include Section L Appendix 6 Badging Request Form (Includes TAA), see attached Appendix; 2 pages.
End of solicitation changes.
Solicitation Amendment 0002 is released to:
A) Update the email address in Section L.9 (e) to KSC-NE-Badging@mail.nasa.gov; see attached Slip Page; 1 page.
End of solicitation changes.
Solicitation Amendment 0003 is released to:
A) Provide the "Example Submittal Matrix" as described in Attachment J-A-2, paragraph (d); 1 page attached.
B) Provide the "ECS Site Visit Attendance," listing all participants present for the site visit on June 16, 2020; 1 page attached.
C) Correct Attachment J-A section numbering, from J-A-21 to J-A-17 and J-A-22 to J-A-18; see
attached Slip Pages; 2 pages.
D) Remove unintended and incomplete section at Attachment J-B-44, renumber remaining
sections J-B-44 to J-B-49; see attached Slip Pages; 3 pages.
End of solicitation changes.
Solicitation Amendment 0004 is released to:
A) Update proposal due date. Proposals are due July 14, 2020 by 2:00 PM EST, see attached "Slip Pages," 4 pages attached.
B) Provide Government answers to submitted questions; see attached "Questions & Answers 1," 1 page attached.
C) Update solicitation section F.1, paragraph (c); see attached "Slip Pages," 4 pages attached.
D) Update solicitation section L.13, paragraph (a); see attached "Slip Pages," 4 pages attached.
E) Update solicitation section L.18, paragraph (b)(4); see attached “Slip Pages,” 4 pages attached.
F) Corrected various spacing, punctuation, capitalization, and other typographical errors throughout the solicitation.
End of solicitation changes.
Solicitation Amendment 0005 is released to:
A) Provide Government answers to submitted questions; see attached "Questions & Answers 2," 1 page attached.
B) Update solicition Standard Form 1442 cover page page count;see attached “Slip Pages,” 5 pages attached.
C) Update solicitation section C.2 paragraph (b); see attached "Slip Pages," 5 pages attached.
D) Update solicitation and added multiple paragraphs in section M.1 (c)(4); see attached “Slip Pages,” 5 pages attached.
End of solicitation changes.
Solicitation Amendment 0006 is released to:
A) Provide Government answers to submitted questions; see attached "Questions & Answers 3," 3 pages attached.
B) Update solicition Standard Form 1442 cover page page count;see attached “Slip Pages,” 3 pages attached.
C) Update solicitation section C.2 paragraph (b); see attached "Slip Pages," 3 pages attached.
End of solicitation changes.
Update #6 ·
NASA has a need to upgrade the Environmental Control (ECS) at Launch Complex (LC) 39B. The upgraded ECS is required to support the crewed Space Launch System (SLS) Artemis II mission. The project will include the following work:
The upgrade of the ECS at LC 39B. The modified ECS will provide conditioned clean purge air to various compartments of the new SLS vehicle supporting Artemis missions. The upgrade scope includes replacement of the existing cooling tower, relocation of existing ductwork, heaters, and instrumentation, addition of new heaters and high pressure ducts, replacement of filter housings and valves, revising existing gaseous nitrogen piping including replacement of heritage aluminum gaseous nitrogen piping with stainless steel, modification of existing controls systems hardware, installation of new humidifiers, and incidental related work.
Solicitaiton Amendment 0001 is released to:
A) Update the 1442, Section B.1, Section L.9, and Section L.10, see attached Slip Pages; 5 pages.
B) Include Section L Appendix 6 Badging Request Form (Includes TAA), see attached Appendix; 2 pages.
End of solicitation changes.
Solicitation Amendment 0002 is released to:
A) Update the email address in Section L.9 (e) to KSC-NE-Badging@mail.nasa.gov; see attached Slip Page; 1 page.
End of solicitation changes.
Solicitation Amendment 0003 is released to:
A) Provide the "Example Submittal Matrix" as described in Attachment J-A-2, paragraph (d); 1 page attached.
B) Provide the "ECS Site Visit Attendance," listing all participants present for the site visit on June 16, 2020; 1 page attached.
C) Correct Attachment J-A section numbering, from J-A-21 to J-A-17 and J-A-22 to J-A-18; see
attached Slip Pages; 2 pages.
D) Remove unintended and incomplete section at Attachment J-B-44, renumber remaining
sections J-B-44 to J-B-49; see attached Slip Pages; 3 pages.
End of solicitation changes.
Solicitation Amendment 0004 is released to:
A) Update proposal due date. Proposals are due July 14, 2020 by 2:00 PM EST, see attached "Slip Pages," 4 pages attached.
B) Provide Government answers to submitted questions; see attached "Questions & Answers 1," 1 page attached.
C) Update solicitation section F.1, paragraph (c); see attached "Slip Pages," 4 pages attached.
D) Update solicitation section L.13, paragraph (a); see attached "Slip Pages," 4 pages attached.
E) Update solicitation section L.18, paragraph (b)(4); see attached “Slip Pages,” 4 pages attached.
F) Corrected various spacing, punctuation, capitalization, and other typographical errors throughout the solicitation.
End of solicitation changes.
Solicitation Amendment 0005 is released to:
A) Provide Government answers to submitted questions; see attached "Questions & Answers 2," 1 page attached.
B) Update solicition Standard Form 1442 cover page page count;see attached “Slip Pages,” 5 pages attached.
C) Update solicitation section C.2 paragraph (b); see attached "Slip Pages," 5 pages attached.
D) Update solicitation and added multiple paragraphs in section M.1 (c)(4); see attached “Slip Pages,” 5 pages attached.
End of solicitation changes.
Update #5 ·
NASA has a need to upgrade the Environmental Control (ECS) at Launch Complex (LC) 39B. The upgraded ECS is required to support the crewed Space Launch System (SLS) Artemis II mission. The project will include the following work:
The upgrade of the ECS at LC 39B. The modified ECS will provide conditioned clean purge air to various compartments of the new SLS vehicle supporting Artemis missions. The upgrade scope includes replacement of the existing cooling tower, relocation of existing ductwork, heaters, and instrumentation, addition of new heaters and high pressure ducts, replacement of filter housings and valves, revising existing gaseous nitrogen piping including replacement of heritage aluminum gaseous nitrogen piping with stainless steel, modification of existing controls systems hardware, installation of new humidifiers, and incidental related work.
Solicitaiton Amendment 0001 is released to:
A) Update the 1442, Section B.1, Section L.9, and Section L.10, see attached Slip Pages; 5 pages.
B) Include Section L Appendix 6 Badging Request Form (Includes TAA), see attached Appendix; 2 pages.
End of solicitation changes.
Solicitation Amendment 0002 is released to:
A) Update the email address in Section L.9 (e) to KSC-NE-Badging@mail.nasa.gov; see attached Slip Page; 1 page.
End of solicitation changes.
Solicitation Amendment 0003 is released to:
A) Provide the "Example Submittal Matrix" as described in Attachment J-A-2, paragraph (d); 1 page attached.
B) Provide the "ECS Site Visit Attendance," listing all participants present for the site visit on June 16, 2020; 1 page attached.
C) Correct Attachment J-A section numbering, from J-A-21 to J-A-17 and J-A-22 to J-A-18; see
attached Slip Pages; 2 pages.
D) Remove unintended and incomplete section at Attachment J-B-44, renumber remaining
sections J-B-44 to J-B-49; see attached Slip Pages; 3 pages.
End of solicitation changes.
Solicitation Amendment 0004is released to:
A) Update proposal due date. Proposals are due July 14, 2020 by 2:00 PM EST, see attached "Slip Pages," 4 pages attached.
B) Provide Government answers to submitted questions; see attached "Questions & Answers 1," 1 page attached.
C) Update solicitation section F.1, paragraph (c); see attached "Slip Pages," 4 pages attached.
D) Update solicitation section L.13, paragraph (a); see attached "Slip Pages," 4 pages attached.
E) Update solicitation section L.18, paragraph (b)(4); see attached “Slip Pages,” 4 pages attached.
F) Corrected various spacing, punctuation, capitalization, and other typographical errors throughout the solicitation.
End of solicitation changes.
Update #4 ·
NASA has a need to upgrade the Environmental Control (ECS) at Launch Complex (LC) 39B. The upgraded ECS is required to support the crewed Space Launch System (SLS) Artemis II mission. The project will include the following work:
The upgrade of the ECS at LC 39B. The modified ECS will provide conditioned clean purge air to various compartments of the new SLS vehicle supporting Artemis missions. The upgrade scope includes replacement of the existing cooling tower, relocation of existing ductwork, heaters, and instrumentation, addition of new heaters and high pressure ducts, replacement of filter housings and valves, revising existing gaseous nitrogen piping including replacement of heritage aluminum gaseous nitrogen piping with stainless steel, modification of existing controls systems hardware, installation of new humidifiers, and incidental related work.
Solicitaiton Amendment 0001 is released to:
A) Update the 1442, Section B.1, Section L.9, and Section L.10, see attached Slip Pages; 5 pages.
B) Include Section L Appendix 6 Badging Request Form (Includes TAA), see attached Appendix; 2 pages.
End of solicitation changes.
Solicitation Amendment 0002 is released to:
A) Update the email address in Section L.9 (e) to KSC-NE-Badging@mail.nasa.gov; see attached Slip Page; 1 page.
End of solicitation changes.
Solicitation Amendment 0003 is released to:
A) Provide the "Example Submittal Matrix" as described in Attachment J-A-2, paragraph (d); 1 page attached.
B) Provide the "ECS Site Visit Attendance," listing all participants present for the site visit on June 16, 2020; 1 page attached.
C) Correct Attachment J-A section numbering, from J-A-21 to J-A-17 and J-A-22 to J-A-18; see
attached Slip Pages; 2 pages.
D) Remove unintended and incomplete section at Attachment J-B-44, renumber remaining
sections J-B-44 to J-B-49; see attached Slip Pages; 3 pages.
End of solicitation changes.
Update #3 ·
NASA has a need to upgrade the Environmental Control (ECS) at Launch Complex (LC) 39B. The upgraded ECS is required to support the crewed Space Launch System (SLS) Artemis II mission. The project will include the following work:
The upgrade of the ECS at LC 39B. The modified ECS will provide conditioned clean purge air to various compartments of the new SLS vehicle supporting Artemis missions. The upgrade scope includes replacement of the existing cooling tower, relocation of existing ductwork, heaters, and instrumentation, addition of new heaters and high pressure ducts, replacement of filter housings and valves, revising existing gaseous nitrogen piping including replacement of heritage aluminum gaseous nitrogen piping with stainless steel, modification of existing controls systems hardware, installation of new humidifiers, and incidental related work.
Solicitaiton Amendment 0001 is released to:
A) Update the 1442, Section B.1, Section L.9, and Section L.10, see attached Slip Pages; 5 pages.
B) Include Section L Appendix 6 Badging Request Form (Includes TAA), see attached Appendix; 2 pages.
End of solicitation changes.
Solicitation Amendment 0002 is released to:
A) Update the email address in Section L.9 (e) to KSC-NE-Badging@mail.nasa.gov; see attached Slip Page; 1 page.
End of solicitation changes.
Update #2 ·
NASA has a need to upgrade the Environmental Control (ECS) at Launch Complex (LC) 39B. The upgraded ECS is required to support the crewed Space Launch System (SLS) Artemis II mission. The project will include the following work:
The upgrade of the ECS at LC 39B. The modified ECS will provide conditioned clean purge air to various compartments of the new SLS vehicle supporting Artemis missions. The upgrade scope includes replacement of the existing cooling tower, relocation of existing ductwork, heaters, and instrumentation, addition of new heaters and high pressure ducts, replacement of filter housings and valves, revising existing gaseous nitrogen piping including replacement of heritage aluminum gaseous nitrogen piping with stainless steel, modification of existing controls systems hardware, installation of new humidifiers, and incidental related work.
Solicitaiton Amendment 0001 is released to:
A) Update the 1442, Section B.1, Section L.9, and Section L.10, see attached Slip Pages; 5 pages.
B) Include Section L Appendix 6 Badging Request Form (Includes TAA), see attached Appendix; 2 pages.
Update #1 ·
NASA has a need to upgrade the Environmental Control (ECS) at Launch Complex (LC) 39B. The upgraded ECS is required to support the crewed Space Launch System (SLS) Artemis II mission. The project will include the following work:
The upgrade of the ECS at LC 39B. The modified ECS will provide conditioned clean purge air to various compartments of the new SLS vehicle supporting Artemis missions. The upgrade scope includes replacement of the existing cooling tower, relocation of existing ductwork, heaters, and instrumentation, addition of new heaters and high pressure ducts, replacement of filter housings and valves, revising existing gaseous nitrogen piping including replacement of heritage aluminum gaseous nitrogen piping with stainless steel, modification of existing controls systems hardware, installation of new humidifiers, and incidental related work.
Attachments
Show all 47
Notice history
| Notice | Type | Posted |
|---|---|---|
| Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B | Award Notice | |
| Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B | Solicitation | |
| Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B | Pre-Solicitation | |
| Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity