This document contains pre-proposal questions and answers for an upgrade to the Environmental Control System at Launch Complex 39B at NASA's Kennedy Space Center. NASA requires upgrading the ECS to support the crewed Space Launch System Artemis II mission, including replacing the existing cooling tower, relocating ductwork, heaters and instrumentation, adding new heaters and high pressure ducts, replacing filter housings and valves, revising gaseous nitrogen piping from aluminum to stainless steel, modifying controls systems hardware, installing new humidifiers, and related incidental work. Questions from potential offerors are answered, clarifying that comparable filter products from manufacturers 3B and Norman are acceptable in place of the declined bid from VACCO, and that stainless steel jacketing 0.016 inches thick is required for flange insulation on aluminum and stainless steel ducts in tunnels and above bulkhead plates.

View the file

Other files for this federal contract opportunity

Other files attached to Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B, newest first.
File Type Posted
80KSC020R0024 ECS at LC39B Questions And Answers 1 to 4.pdf PDF
80KSC020R0024 Amendment 0008 with Attachments.pdf PDF
80KSC020R0024 LC39B ECS Amendment 08 Slip page.pdf PDF
80KSC020R0024 Amendment 0008 Conformed Solicitation.pdf PDF
80KSC020R0024 LC39B ECS Amendment 07 Slip Page.pdf PDF
80KSC020R0024 Amendment 0007 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0007 with Attachments.pdf PDF
80KSC020R0024 Attachment J-C Wage Determination.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 to 3.pdf PDF
80KSC020R0024 LC39B ECS Amendment 06 Slip Pages.pdf PDF
80KSC020R0024 Amendment 0006 with Attachments.pdf PDF
Questions And Answers 3.pdf PDF
80KSC020R0024 Amendment 0006 Conformed Solicitation.pdf PDF
Questions And Answers 2.pdf PDF
80KSC020R0024 Amendment 0005 with Attachments.pdf PDF
80KSC020R0024 LC39B ECS Amendment 05 Slip Pages.pdf PDF
80KSC020R0024 Amendment 0005 Conformed Solicitation.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 and 2.pdf PDF
80KSC020R0024 LC39B ECS Amendment 04 Slip Pages.pdf PDF
Questions And Answers 1.pdf PDF
80KSC020R0024 Amendment 0004 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0004 with Attachments.pdf PDF
80KSC020R0024 J-A Amend 0003 Conformed.pdf PDF
80KSC020R0024 Amendment 0003 with Attachments.pdf PDF
ECS Site Visit Attendence.pdf PDF
80KSC020R0024 J-B Amend 0003 Conformed.pdf PDF
Example Submittal Matrix.xlsx XLSX spreadsheet
80KSC020R0024 LC39B ECS Amendment 01 Slip Pages.pdf PDF
Section L Appendix 6 Badging Request Form (Includes TAA).docx DOCX document
80KSC020R0024 Amendment 0002.pdf PDF
80KSC020R0024 LC39B ECS Amendment 02 Slip Page.pdf PDF
80KSC020R0024 Amendment 0002 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0001 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0001.pdf PDF
80KSC020R0024 Attachment J-G Badging ID Process.pdf PDF
Section L Appendix 5 Small Business Subcontracting Goals.docx DOCX document
Section L Appendix 4 PPQs.docx DOCX document
80KSC020R0024 Attachment J-B Project Requirements.pdf PDF
80KSC020R0024 Attachment J-J JOFOC.pdf PDF
Section L Appendix 3 Pre-Proposal Inquiry Form.xlsx XLSX spreadsheet
Section L Appendix 1 KSC Form 28-889 Visitor Badge Request.pdf PDF
80KSC020R0024 ECS Solicitation.pdf PDF
80KSC020R0024 Attachment J-A Deliverables.pdf PDF
Section L Appendix 2 Acceptable Identity Guide.pdf PDF
80KSC020R0024 Attachment J-D Progress Payments.pdf PDF
80KSC020R0024 Attachment J-C Wage Determination.pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE PROPOSAL QUESTIONS AND ANSWERS 80KSC020R0024

Amendment 0008

No

Reference for Question (Section

Paragraph/Page) QUESTIONS ANSWERS Amendment

Number

49 M-508

Drawing M-508 provides a brief specification of the panel filters and says custom made by VACCO or approved equal. Must be B31.3 compliant.

The VACCO representative is declining to bid the project. Are comparable products from the following manufacturers be acceptable:

3B, Norman. Please concur or advise.

On drawing M-508 NEW GN2 FILTER SCHEDULE, the two cells under “DESCRIPTION/MODEL” column are changed to:

"100% EFFICIENT AT 70 MICRONS AND 98% EFFICIENT

AT 40 MICRONS, ASTM B31.3 COMPLIANT. BASIS OF

DESIGN IS CUSTOM MANUFACTURED FROM NORMAN

FILTER COMPANY OR APPROVED EQUAL. PROVIDE

WITH TWO S.S. TAPS AND DIFFERENTIAL PRESSURE

GAUGE (0-5PSI) AND 1/4” STAINLESS STEEL TUBING

AND TWO S.S.TUBING SHUT-OFF VALVES."

See updated Drawings via Solicitation Section C.2(b)(6).

50 Amendment 0006, Question 16

Please confirm that PVC jacket .030 is to be used on all double wall flange insulation kits over pyrogel for ECS ducts in the tunnel and above grade? Note: Detail MBY on M- 615 states use Stainless jacket over pyrogel. If stainless jacket is be used what is the thickness required?

Stainless steel jacketing is required for all flange insulation applications on double-wall aluminum and double-wall stainless steel ducts in the tunnels and above the bulkhead plate and shall be minimum 0.016” thick. PVC jacketing is allowed on the interior single-wall ducts only.