Section L Appendix 4 PPQs.docx

DOCX document 24 KB Posted

Attached to
Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B Federal contract opportunity
Solicitation number
80KSC020R0024
Issued by
National Aeronautics and Space Administration Kennedy Space Center

About this file

This document contains a past performance questionnaire for a federal solicitation. NASA is seeking to upgrade the Environmental Control System at Launch Complex 39B at the Kennedy Space Center in Florida to support crewed Space Launch System Artemis II missions. The upgrade work includes replacing the existing cooling tower and ductwork, adding new heaters and high pressure ducts, replacing filter housings and valves, modifying gaseous nitrogen piping and controls systems hardware, and installing new humidifiers. Offerors must provide this past performance questionnaire to references to assess their project management, technical performance, safety, and contract administration on similar past projects. Completed questionnaires must be returned to NASA by the proposal submission deadline.

View the file

Other files for this federal contract opportunity

Other files attached to Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B, newest first.
File Type Posted
80KSC020R0024 LC39B ECS Amendment 08 Slip page.pdf PDF
Questions And Answers 4.pdf PDF
80KSC020R0024 Amendment 0008 Conformed Solicitation.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 to 4.pdf PDF
80KSC020R0024 Amendment 0008 with Attachments.pdf PDF
80KSC020R0024 Amendment 0007 Conformed Solicitation.pdf PDF
80KSC020R0024 LC39B ECS Amendment 07 Slip Page.pdf PDF
80KSC020R0024 Amendment 0007 with Attachments.pdf PDF
80KSC020R0024 Attachment J-C Wage Determination.pdf PDF
80KSC020R0024 Amendment 0006 with Attachments.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 to 3.pdf PDF
80KSC020R0024 LC39B ECS Amendment 06 Slip Pages.pdf PDF
Questions And Answers 3.pdf PDF
80KSC020R0024 Amendment 0006 Conformed Solicitation.pdf PDF
Questions And Answers 2.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 and 2.pdf PDF
80KSC020R0024 Amendment 0005 with Attachments.pdf PDF
80KSC020R0024 LC39B ECS Amendment 05 Slip Pages.pdf PDF
80KSC020R0024 Amendment 0005 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0004 with Attachments.pdf PDF
80KSC020R0024 LC39B ECS Amendment 04 Slip Pages.pdf PDF
Questions And Answers 1.pdf PDF
80KSC020R0024 Amendment 0004 Conformed Solicitation.pdf PDF
80KSC020R0024 J-B Amend 0003 Conformed.pdf PDF
80KSC020R0024 J-A Amend 0003 Conformed.pdf PDF
Example Submittal Matrix.xlsx XLSX spreadsheet
80KSC020R0024 Amendment 0003 with Attachments.pdf PDF
ECS Site Visit Attendence.pdf PDF
80KSC020R0024 LC39B ECS Amendment 01 Slip Pages.pdf PDF
Section L Appendix 6 Badging Request Form (Includes TAA).docx DOCX document
80KSC020R0024 Amendment 0002.pdf PDF
80KSC020R0024 LC39B ECS Amendment 02 Slip Page.pdf PDF
80KSC020R0024 Amendment 0002 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0001.pdf PDF
80KSC020R0024 Amendment 0001 Conformed Solicitation.pdf PDF
Section L Appendix 3 Pre-Proposal Inquiry Form.xlsx XLSX spreadsheet
Section L Appendix 1 KSC Form 28-889 Visitor Badge Request.pdf PDF
80KSC020R0024 ECS Solicitation.pdf PDF
80KSC020R0024 Attachment J-A Deliverables.pdf PDF
Section L Appendix 2 Acceptable Identity Guide.pdf PDF
80KSC020R0024 Attachment J-D Progress Payments.pdf PDF
80KSC020R0024 Attachment J-C Wage Determination.pdf PDF
80KSC020R0024 Attachment J-G Badging ID Process.pdf PDF
Section L Appendix 5 Small Business Subcontracting Goals.docx DOCX document
80KSC020R0024 Attachment J-B Project Requirements.pdf PDF
80KSC020R0024 Attachment J-J JOFOC.pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NASA/KSC SOLICITATION 80KSC020R0024

SECTION L - APPENDIX 4

PAST PERFORMANCE QUESTIONNAIRE

Upgrade Environmental Control System (ECS), Launch Complex 39B (LC 39B) at Kennedy Space Centers (KSC), FL

NASA Kennedy Space Center’s solicitation requires offerors to provide this Past Performance Questionnaire to customers to complete and return to NASA. Past performance raters are requested to submit the completed questionnaires to the contracting officer identified below via e-mail, to arrive not later than the proposal submission date.

Completed questionnaires should be sent to:

Name:C. M. Julius Williams
Email:Christopher.M.Williams@nasa.gov
Address:NASA John F. Kennedy Space Center

Mail Stop: OP-CS Kennedy Space Center, Florida 32899

Raters are requested to complete the questionnaire forms as written since altered or substituted questionnaires may not adequately address the information NASA will be evaluating.

SECTION I. THIS SECTION TO BE COMPLETED BY THE OFFEROR

Name of Contractor Being Evaluated:

Name of Project and Contract/Order Number:

Period of Contract Performance (dates):

Place of Contract Performance:

Contract Value at Award:

Contract Value at Completion or Current Contract Amount:

Contract Status (Prime or Subcontract?):

Point of Contact: (Rater) Name/Address/Office Phone Number/E-Mail Address:

THIS SECTION TO BE COMPLETED BY THE RATER

(THIS QUESTIONNAIRE, WHEN COMPLETED, SHALL NOT BE DISCLOSED TO ANYONE OUTSIDE THE GOVERNMENT)

Name of Contractor Being Evaluated:

Name of Project and Contract/Order Number:

Period of Contract Performance (dates) :

Place of Contract Performance:

Contract Value at Award:

Contract Value at Completion or Current Contract Amount:

Contractor’s Status (Prime or Subcontractor?):

Percentage and Dollar Value of Work Performed by the Contractor:

Dates of Rater’s Involvement in Program/Contract:

Brief Description of Work Performed:

Point of Contact: (Rater) Name/Address/Office Phone Number/E-Mail Address:

RATING DEFINITIONS:

On a scale of 1 to 5, with 1 being unsatisfactory and 5 being exceptional, please rate the contractor on the past performance areas included in this questionnaire. A rating of N/A should be used if the question is not applicable or the answer is unknown. Space is provided for any additional comments raters may want to provide. The definitions associated with the 1 to 5 ratings are provided below:

1. UNSATISFACTORY: Performance does (did) not meet most contractual requirements and recovery is not likely (did not occur). The contractual performance contains (contained) serious problem(s) for which the contractor’s corrective actions appear ineffective (were ineffective).

2. MARGINAL: Performance does (did) not meet some contractual requirements. The contractual performance reflects (reflected) serious problem(s) for which the contractor has not yet identified acceptable corrective actions (did not provide acceptable corrective actions).

3. SATISFACTORY: Performance meets (met) contractual requirements. The contractual performance reflects (reflected) some minor problems. Corrective actions being taken by the contractor appear to be effective (Corrective actions taken were effective).

4. VERY GOOD: Performance meets (met) contractual requirements and exceeds (exceeded) some of the Government’s expectations. The contractual performance reflects (reflected) some minor problems and corrective actions being taken by the contractor appear to be effective (Corrective actions taken were effective).

5. EXCEPTIONAL: Performance meets (met) contractual requirements and exceeds (exceeded) many of the Government’s expectations. The contractual performance reflects (reflected) few minor problems and corrective actions taken by the contractor appear to be highly effective (corrective actions taken were effective).

N/A: Not applicable or rater has not observed performance in this area.

CONTRACTOR’S TECHNICAL PERFORMANCE QUESTIONS

1. The effectiveness of the Contractor’s overall project management ability (including but not limited to project managers, quality control managers, trade integrators, safety managers, and superintendents); labor (skilled and unskilled workers); equipment; supplies; tools; and financial resources to successfully perform, provide contract deliverables and complete work in a safe and timely manner.

1
2
3
4
5
NA

Comments:

2. The Contractor’s ability to provide timely and effective contractor management attention at the job site and partner with the owner to resolve technical and schedule issues.

1
2
3
4
5
NA

Comments:

3. The Contractor’s ability to provide quality engineering shop drawings and accurate and complete as-built documentation.

1
2
3
4
5
NA

Comments:

4. The Contractor’s ability to complete work within the required timeframe(s).

1
2
3
4
5
NA

Comments:

5. The Contractor’s ability to provide and adhere to a detailed 2, 3, or 4-week look ahead schedule throughout project for increased team coordination.

1
2
3
4
5
NA

Comments:

6. The Contractor’s ability to provide professional, clean, high quality computer aided drafting (CAD) / BIM based shop drawings including but not limited to dimensioned coordination, fabrication, installation and as-built drawings.

1
2
3
4
5
NA

Comments:

7. The Contractor’s ability to provide fully marked-up product data cut sheets; highlighting the particular model # / part #s, sizes, options and other applicable data to allow for concise detailing of components to be installed.

1
2
3
4
5
NA

Comments:

8. The contractor’s ability to coordinate, communicate, and team with the owner and other on-site personnel in shared work locations.

1
2
3
4
5
NA

Comments:

9. The contractor’s ability to provide certified welders and all associated documentation including clear weld records demonstrating quality of each weld.

1
2
3
4
5
NA

Comments:

CONTRACTOR’S SAFETY PERFORMANCE QUESTION

10. The Contractor’s ability to report and take corrective actions on safety accidents/incidents in a timely manner.

1
2
3
4
5
NA

Comments:

CONTRACTOR’S CONTRACT ADMINISTRATION PERFORMANCE QUESTIONS

11. The contractor’s ability to provide prompt payment of employees, subcontractors, and suppliers for services and supplies performed/delivered under the contract.

1
2
3
4
5
NA

Comments:

12. The contractor’s compliance with Department of Labor requirements and resolution of reported violations/discrepancies.

1
2
3
4
5
NA

Comments:

13. The contractor’s compliance with contract subcontracting plan goals for small disadvantaged business (SDB) concerns (see FAR 19.7), monetary targets for SDB participation (see FAR 19.1202), and notifications submitted under FAR 19.1202-4(b). (Applicable only to Large Business Offerors)

1
2
3
4
5
NA

Comments:

14. Has the contractor’s performance required the issuance of any cure notices, show cause letters, or terminations for cause/default? (Please circle Yes or No)

Yes
No

Comments:

CONTRACTOR’S OVERALL CONTRACT PERFORMANCE

15. Would you select this contractor again? (Please circle Yes or No)

Yes
No

Comments:

THIS COMPLETED QUESTIONNAIRE WILL NOT BE DISCLOSED TO ANYONE OUTSIDE THE GOVERNMENT. THANK YOU FOR TAKING THE TIME TO COMPLETE THIS QUESTIONNAIRE.

File details come from the government source that posted it. Updated .