80KSC020R0024 ECS Solicitation.pdf

PDF 297 KB Posted

Attached to
Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B Federal contract opportunity
Solicitation number
80KSC020R0024
Issued by
National Aeronautics and Space Administration Kennedy Space Center

About this file

This solicitation is for the upgrade of the Environmental Control System at Launch Complex 39B at the Kennedy Space Center. The project involves replacing the existing cooling tower and relocating ductwork, heaters and instrumentation. It also includes adding new heaters, high pressure ducts, filter housings, valves and modifying controls systems hardware. New humidifiers will be installed and other incidental work performed. The National Aeronautics and Space Administration is the contracting agency. The solicitation is a full and open, lowest price technically acceptable procurement. Offerors must submit pricing by the response deadline of July 10, 2020. The period of performance involves pre-Artemis I launch work to be completed by the scheduled Artemis I launch of July 1, 2021, as well as post-Artemis I launch work to be finished within 180 calendar days of notice to proceed.

View the file

Other files for this federal contract opportunity

Other files attached to Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B, newest first.
File Type Posted
80KSC020R0024 LC39B ECS Amendment 08 Slip page.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 to 4.pdf PDF
80KSC020R0024 Amendment 0008 with Attachments.pdf PDF
Questions And Answers 4.pdf PDF
80KSC020R0024 Amendment 0008 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0007 Conformed Solicitation.pdf PDF
80KSC020R0024 LC39B ECS Amendment 07 Slip Page.pdf PDF
80KSC020R0024 Amendment 0007 with Attachments.pdf PDF
80KSC020R0024 Attachment J-C Wage Determination.pdf PDF
80KSC020R0024 Amendment 0006 with Attachments.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 to 3.pdf PDF
80KSC020R0024 LC39B ECS Amendment 06 Slip Pages.pdf PDF
Questions And Answers 3.pdf PDF
80KSC020R0024 Amendment 0006 Conformed Solicitation.pdf PDF
Questions And Answers 2.pdf PDF
80KSC020R0024 Amendment 0005 with Attachments.pdf PDF
80KSC020R0024 LC39B ECS Amendment 05 Slip Pages.pdf PDF
80KSC020R0024 Amendment 0005 Conformed Solicitation.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 and 2.pdf PDF
80KSC020R0024 LC39B ECS Amendment 04 Slip Pages.pdf PDF
Questions And Answers 1.pdf PDF
80KSC020R0024 Amendment 0004 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0004 with Attachments.pdf PDF
80KSC020R0024 J-B Amend 0003 Conformed.pdf PDF
80KSC020R0024 J-A Amend 0003 Conformed.pdf PDF
80KSC020R0024 Amendment 0003 with Attachments.pdf PDF
ECS Site Visit Attendence.pdf PDF
Example Submittal Matrix.xlsx XLSX spreadsheet
80KSC020R0024 LC39B ECS Amendment 01 Slip Pages.pdf PDF
Section L Appendix 6 Badging Request Form (Includes TAA).docx DOCX document
80KSC020R0024 Amendment 0002.pdf PDF
80KSC020R0024 LC39B ECS Amendment 02 Slip Page.pdf PDF
80KSC020R0024 Amendment 0002 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0001 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0001.pdf PDF
Section L Appendix 3 Pre-Proposal Inquiry Form.xlsx XLSX spreadsheet
Section L Appendix 1 KSC Form 28-889 Visitor Badge Request.pdf PDF
80KSC020R0024 Attachment J-A Deliverables.pdf PDF
80KSC020R0024 Attachment J-G Badging ID Process.pdf PDF
Section L Appendix 5 Small Business Subcontracting Goals.docx DOCX document
Section L Appendix 4 PPQs.docx DOCX document
80KSC020R0024 Attachment J-B Project Requirements.pdf PDF
80KSC020R0024 Attachment J-J JOFOC.pdf PDF
Section L Appendix 2 Acceptable Identity Guide.pdf PDF
80KSC020R0024 Attachment J-D Progress Payments.pdf PDF
80KSC020R0024 Attachment J-C Wage Determination.pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

80KSC020R0024

TBD

John F. Kennedy Space Center, NASA Procurement Office Code: OP-CS Kennedy Space Center, FL 32899

The contractor shall furnish all labor, equipment, materials, and related activities necessary to upgrade the Environmental Control System at Launch Complex 39-B at Kennedy Space Center, Florida.

This is a Full and Open, Lowest Price Technically Acceptable (LPTA) procurement.

Offeror MUST enter their cage code and DUNS number in block 14, page 2 of the SF 1442.

Offeror MUST be registered SAM and VETS-4212.

Offeror MUST submit electronic offer as specified in section L.15.

KSC-IDIQbids@mail.nasa.gov Attn: C. M. Julius Williams John F. Kennedy Space Center, NASA Procurement Office Code: OP-CS Bldg M7-0301, Room: 5416A Kennedy Space Center, FL 32899

4200729166

OP-CS

C. M. Julius Williams, Contracting Officer (321) 861-2661

99263

1 7306/01/2020

07/10/2020

2:00 PM

*Section F.1

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

OP-CS

John F. Kennedy Space Center, NASA Procurement Office Code: OP-CS Kennedy Space Center, FL 32899

NASA Shared Services Center (NSSC) Financial Management Division (FMD) - Accounts Payable Bldg. 1111, Jerry Hlass Road, Stennis Space Center, MS 39529

NASA/KSC SOLICITATION 80KSC020R0024

TABLE OF CONTENTS

SECTION A SOLICITATION/CONTRACT FORM (SF1442)

SECTION B SUPPLIES OR SERVICES AND PRICE/COSTS

SECTION C

DESCRIPTION/SPECIFICATIONS/STATEMENT

OF WORK

SECTION D PACKAGING AND MARKING

SECTION E INSPECTION AND ACCEPTANCE

SECTION F DELIVERIES OR PERFORMANCE

SECTION G CONTRACT ADMINISTRATION DATA

SECTION H SPECIAL CONTRACT REQUIREMENTS

SECTION I CONTRACT CLAUSES

SECTION J LIST OF ATTACHMENTS

SECTION K

REPRESENTATIONS, CERTIFICATIONS, AND

OTHER STATEMENTS OF OFFERORS OR

RESPONDENTS

SECTION L

INSTRUCTIONS, CONDITIONS, AND NOTICES

TO OFFERORS OR RESPONDENTS

SECTION M EVALUATION FACTORS FOR AWARD

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 CONSTRUCTION SERVICES AND PRICES

Line Item Description Unit Total

0001 Upgrade ECS, LC-39B, Pre and Post Artemis I work with a 180 calendar day Post Artemis I performance schedule

JOB $ TBD

0002 Alternate Proposal, Upgrade ECS, LC-39B Pre and Post Artemis I work with a 150 calendar day Post Artemis I performance schedule

JOB $ TBD

TOTAL $ TBD

(End of Clause)

B.2 NFS 1852.216-78 FIRM FIXED PRICE (DEC 1988)

The total firm fixed price of this contract is TBD.

B.3 PROJECT DELIVERABLES (JAN 2018)

Contract deliverables (manuals, reports, plans, and other written documentation) to be provided under this contract are identified in Section J, Attachment J-A, Project Deliverables. The costs associated with providing the data in Attachment J-A are included in the firm-fixed price of the awarded contract. Nothing contained in Attachment J-A shall relieve the Contractor from furnishing data called for by, or under the authority of, other provisions of this contract, which are not identified and described in Attachment J-A.

SECTION C – DESCRIPTION/SPECIFICATION/WORK STATEMENT

C.1 SCOPE OF WORK (JAN 2018)

The Contractor shall furnish all management, supervision, labor, transportation, facilities, materials, tools, equipment, disposal, and documentation (except any property, including utilities, specified in the Schedule to be Government-Furnished) to perform all work for the Task(s) named below, and defined in the contract drawings, maps, specifications, and/or statements of work.

Line Item Description

0001 Upgrade ECS, LC-39B, Pre and Post Artemis I work with a 180 calendar day Post Artemis I performance schedule

0002 Alternate Proposal, Upgrade ECS, LC-39B Pre and Post Artemis I work with a 150 calendar day Post Artemis I performance schedule

C.2 CONTRACT DRAWINGS, MAPS, SPECIFICATIONS, AND/OR STATEMENTS OF WORK

(JAN 2018)

(a) Five sets of full scale contract drawings, maps, specifications, and/or statements of work (excluding publications incorporated into the technical provisions by reference), plus one CD or DVD containing electronic, portable document format (PDF) versions, and an electronic copy of the 3D model, will be furnished at award to the Contractor without charge. The work shall conform to the following contract drawings, maps, specifications, and/or statements of work, attached to this contract.

Drawing Number 79K40792, titled “Upgrade ECS at LC-39B,” dated 04/13/2020, sheets 1 through 240.

Specification Number 79K40793, titled “Upgrade ECS at LC-39B,” dated 04/13/2020, pages 1 through 797.

(b) Addenda to Drawings, Maps, Specifications, and/or Statements of Work: N/A

(c) "Or Equal" Items”

Throughout the technical specifications and drawings of this contract, where certain manufacturers’ trade names and model numbers are specified and followed by the term "or equal," the manufacturer's name and data as specified shall represent the minimum standard type, quality, and capacity acceptable for incorporation into the work covered by this contract. The products of other manufacturers will be considered as being acceptable, provided that such products fully meet or exceed all minimum structural or use and operational features of the particular manufacturers’ items as specified, and provided that the other manufacturers’ items are easily interchangeable and can be adequately incorporated within the allocated space in the building or structure. In all cases, the acceptability of "or equal" items shall be at the Contracting Officer's discretion, based upon data submitted by the Contractor in accordance with the requirements under the Shop Drawings Clause.

(d) Omissions from the drawings or specifications, or the omission or misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or

SECTION C – DESCRIPTION/SPECIFICATION/WORK STATEMENT

which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work but they shall be performed as if fully and correctly set forth and described in the drawings and specifications.

(e) The Contractor shall check all drawings furnished him immediately upon their receipt and shall promptly notify the Contracting Officer of any discrepancies. Figures marked on drawings shall in general be followed in preference to scale measurements. Large scale drawings shall in general govern small scale drawings. The Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.

SECTION D – PACKAGING AND MARKING

NOT APPLICABLE TO THIS SOLICITATION/CONTRACT

SECTION E - INSPECTION AND ACCEPTANCE

E.1 FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

INCORPORATED BY REFERENCE

FAR 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

E.2 BASIC INSPECTION SYSTEM (JAN 2018)

Pursuant to FAR Clause 52.246-12, Inspection of Construction, or FAR Clause 246-13, Inspection – Dismantling, Demolition, or Removal of Improvements:

The Contractor shall maintain and implement a basic inspection system as identified below:

(a) Definitions:

"Inspection" means examining and testing supplies or services (including, when appropriate, raw materials, components, and intermediate assemblies) to determine whether they conform to contract requirements.

"Testing" means that element of inspection that determines the properties or elements, including functional operation of supplies or their components, by the application of established scientific principles and procedures.

"Independent Testing Laboratory" means an independent organization, accepted by the Contracting Officer, engaged to perform specific inspections or tests of the work, either at the site or elsewhere, and report the results of these inspections or tests.

(b) The inspection system shall be documented to ensure and provide objective evidence of quality control in the form of records of inspections and test results. The system shall also ensure that nonconforming articles or materials are discovered, documented, and controlled through effective remedial and preventive actions.

The Contractor may use, at his option, in whole or in part, his existing higher level inspection system or quality assurance program provided such system is revised and identified to the requirements below.

(c) The Contractor shall provide a narrative description of an inspection system which provides for compliance with the quality requirements and technical criteria of the contract.

(1) The description shall be submitted for review by the Contracting Officer not later than 7 days after contract award.

(2) The description shall address each of the Basic Inspection System Requirements identified in paragraph (d) below. This submittal shall address both the general inspection system that will be used during the performance of all work under the contract, including but not limited to those items identified under paragraphs d(1), d(2)(iv), d(2)(v), and d(2)(vi) below.

(d) Basic Inspection System Requirements: The Contractor shall describe how each of the following requirements is to be satisfied and what records will be maintained, both on-site and offsite.

(1) The Contractor shall identify the individual responsible for on-site contact and communication relative to implementation and operation of the inspection system. The name of this individual shall be provided, in writing, to the Contracting Officer’s Representative

(COR).

(2) Standard requirements:

(i) A purchasing control system which ensures that all purchasing documents, including those of subcontractors and suppliers, are traceable to the drawings, specifications, and approved submittal requirements.

(ii) A receiving inspection system with documented evidence of Contractor inspection traceable to the procurement documents.

(iii) A system of controls and records for handling, recording, identification and disposition of nonconforming articles and materials.

(iv) A system of identification of inspections required by each specific section of the specifications and drawings and what records will be maintained.

(v) Identification of tests to be performed, including test procedures, test records, and the independent testing organization(s) be utilized.

(vi) Additional requirements (if included in the drawings, specifications, or contract provisions):

(A) Certification or recertification of personnel and qualification of procedures.

(B) Management and accountability of Government furnished equipment, components, or materials.

(C) Calibration of inspection test gages, tools, measuring instruments, and independent laboratories to be utilized.

E.3 SYSTEMS ACCEPTANCE AND TESTING (JAN 2018)

Pursuant to FAR 52.246-12, Inspection of Construction:

Systems tests shall be performed as described below:

(a) SYSTEMS

Systems tests shall be performed on fire protection, fire suppression, HVAC, compressed air and all other assemblies of components which must be tested as an inter-related whole to verify proper functioning.

(b) SYSTEM TEST PROCEDURES

A test procedure and a recording form which documents every step of the system test shall be submitted for approval under the terms of the "Shop Drawings" clause of this contract. Test procedures must be approved prior to requesting a date for testing. Each step in the test procedure shall be witnessed by the Contracting Officer's Representative who shall then date and sign the approved recording form for each step witnessed.

The procedure shall consist of step by step instructions for testing all specified system parameters, system components, and proper overall functioning of the system.

(c) SYSTEM TESTING AND ACCEPTANCE

The following tests shall be performed by the Contractor in strict accordance to the approved test procedure described above.

(1) Functional Test -- This shall be an "in house" test to verify proper installation and functioning of the system and its components. This functional test shall be performed in the presence of Government inspectors and shall be repeated until the Contractor can perform one full test without device or system malfunction.

(2) System Acceptance Test -- After successful completion of the functional testing the system shall be tested formally with full documentation using the previously approved recording form. The Contractor shall notify the Contracting Officer, in writing, forty eight (48) hours prior to system acceptance testing. The appointed Contracting Officer Representative will witness, date and stamp each test in the procedure. Acceptance of the system will be based upon the written approval of the Contracting Officer’s Representative.

Note: For work involving fire detection and suppression systems, additional testing & acceptance requirements are described in project technical specifications

The contractor shall use the following form for transfer of fire alarm / fire suppression systems from the government to the contractor:

KSC - TRANSFER OF RESPONSIBILITY

FROM:

BOSS FIRE PROTECTIVE SYSTEMS – KSC, K6-1446A / KSC-326 Ph. 321-861-4681 / 4683

TO: __________________COMPANY: ____________________ EFFECTIVE DATE: ________________

ADDRESS ___________________________________________ PHONE # __________________________

EMERGENCY CONTACT: ____________________________ PHONE # __________________________

SYSTEM: __________________________________________________________________________________

WON #: ____________________________________________________________________________________

SYSTEM STATUS: OPERATIONAL * PARTIALLY FUNCTIONAL * OUT OF SERVICE

(* Indicate Below)

TRANSFER OF: ENTIRE SYSTEM *PARTIAL (Explain Below)

REASON FOR TRANSFER:

CONDITIONS OF TRANSFER: The assignee agrees to the responsibility of the following:

Coordination of work on the transferred system described above with the COR. Assignee is responsible for documenting existing system condition prior to transfer. Assignee also agrees to implement safety plans and alternate workaround procedures that facilitate reporting of emergency/fire/security situations, when applicable. The assignee will assure that any and all modifications, installations and changes to the system are in compliance with the contract documents.

The assignee assumes responsibility for returning the system/equipment in an operationally ready state and agrees to demonstrate through functional test, that the system has been installed in accordance with contract specifications and drawings.

Name: _______________________ Signature: _______________________ Dated: _______________________ [Assignee]

Name: _______________________ Signature: _______________________ Dated: _______________________ [BOSS Fire Protective Systems Representative]

Name: _______________________ Signature: _______________________ Dated: _______________________

[COR]

NOTE: A COPY OF THIS TRANSFER SHALL BE POSTED IN OR ATTACHED TO THE

SYSTEM/EQUIPMENT BEING TRANSFERRED.

The contractor shall use the following form to communicate readiness for Preliminary Fire Alarm Testing:

CONTRACTOR READINESS AFFIRMATION – For “Preliminary” Fire Alarm Testing NASA Contract Number: _______________________________

Instructions: The Prime Contractor is responsible to ensure the fire alarm system is “ready” for formal preliminary testing. Circle the proper response and write the date completed. Any ‘No’ response would typically prevent submission of the form.

CONTRACT #: ______________ LOCATION/FACILITY:__________________FACILITY #____________

(circle) Date

Yes No N/A ______ Conduit & wiring is complete. Includes continuity/insulation resistance tests & wiring labeling.

Yes No N/A ______ All fire alarm devices are installed.

Yes No N/A ______ Auxiliary functions are connected and known to be operational. Example: AHU shutdown

Yes No N/A ______ Fire alarm panel program, specific to this job, is loaded and operational.

Yes No N/A ______ All troubles, ground faults, etc. have been removed; system is effectively NORMAL.

Yes No N/A ______ Fire alarm vendor/subcontractor conducted a “contractor checkout” of the fire alarm system, with completion on this date: ___________________ which included testing of a sample of inputs and outputs. Example: rang bells to verify operation in temporal-three pattern, tested 5% of all devices, verified AHU shutdown, verified FACP switched to battery upon loss of 120VAC, etc.

Yes No N/A ______ NFPA 72 Record of Completion form is started for the installation.

Yes No N/A ______ System drawings are available for addition of “red-lines”

Yes No N/A ______ Support needed for successful completion of the Preliminary Test has been identified in writing to the Contracting Officer. Examples: support to test existing fire suppressions systems, elevator crew support, HVAC crew support, security system crew support to verify mag-locks are de-energized, etc.

The undersigned attests that the subject fire alarm system is ready for PRELIMINARY TEST;

Name: __________________________________ Signature:__________________________________________ [Prime Contractor Representative]

Form Completion Date: __________________ Proposed Preliminary Test Date(s):_____________________

Transmit this form per submittal schedule in the contract.

Nothing in this clause shall relieve the contractor from the requirements of FAR 52.246-12, "Inspection of Construction."

E.4 FINAL INSPECTION AND ACCEPTANCE (JAN 2018)

Final inspection and acceptance of all work under this contract will be conducted by the Contracting Officer’s Representative (COR). Upon satisfactory completion of the contract, the Contractor shall be paid the fixed-price value of the contract, less the amount of any progress payments made under FAR Clause 52.232.5, Payments Under Fixed-Price Construction Contracts, or FAR Clause 52.237-4, Payment by Government to Contractor.

NOTE: The contractor shall include a line item in the schedule of values and progress schedule for completion of punch-list items, site clean-up, demobilization and final construction (as-built) drawings. The amount of this line item shall be equal to 10% of the modified contract value at the time of the punch list. The Government will not pay final invoices for this amount until all punch-list, site clean-up, and demobilization activities are complete; final construction drawings are delivered; and final acceptance is made on DD Form 250, Material Inspection and Receiving Report.

SECTION F – DELIVERIES OR PERFORMANCE

F.1 FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984)

Fill-Ins:

(a) The Contractor shall be required to (a) commence work under this contract immediately after the date the Contractor receives the notice to proceed.

(c) See table below:

Contract Line Item Time Stated for Completion

Base Proposal (180 day Post-Artemis 1 Launch Performance Period)

Complete the entire Pre-Artemis I launch work as defined in the contract drawings and specifications for use not later than the Artemis 1 Launch which is currently scheduled for July 1, 2021. The completion date is based on the assumption that the successful offeror will receive the Pre- Artemis 1 Launch notice to proceed by July 31, 2021.

Complete the physical on site Post-Artemis 1 Launch work as defined in the contract drawings and specification for use not later than 180 calendar days after the date the contractor receives the Post-Artemis Launch notice to proceed. NTP for Post-Artemis 1 Launch is anticipated to be issued on or about July 1, 2021.

Alternate Proposal (150 day Post- Artemis 1 Launch Performance Period)

Complete the entire Pre-Artemis I launch work as defined in the contract drawings and specifications for use not later than the Artemis 1 Launch which is currently scheduled for July 1, 2021. The completion date is based on the assumption that the successful offeror will receive the Pre- Artemis 1 Launch notice to proceed by July 31, 2021.

Complete the physical on site Post- Artemis 1 Launch work as defined in the contract drawings and specification for use not later than 150 calendar days after the date the contractor receives the Post-Artemis 1 Launch notice to proceed. NTP for the Post-Artemis 1 Launch work is anticipated to be issued on or about July 1, 2021.

FAR 52.242-14 SUSPENSION OF WORK (APR 1984)

F.2 WORK PERIOD

The contractor will determine the work schedule best suited for completion of the identified tasks in the timeframe allotted. The contractor shall coordinate work hours with the Contracting Officer prior to implementation. All mandatory inspections by the Government are to be scheduled during normal work hours. Any other work period outside the coordinated work hours will require special/ written approval from the Contracting Officer seven (7) days in advance of proposed change in work periods.

F.3 PLACE OF PERFORMANCE (JAN 2018)

This is a firm-fixed price construction contract for PCN 99263 Upgrade ECS System at Launch

Complex 39B on Kennedy Space Center, FL.

F.4 DOWNTIME AND EXCAVATION HOLDS (JAN 2018)

For the purposes of this contract, the Contractor shall assume a maximum of 30 days for the entirety of the project during which all construction activities will be prohibited. Down days are to be split between Pre-Artemis 1 and Post-Artemis 1 with 20 down days for Pre-Artemis I and 10 days for Post-Artemis I. In addition the Contractor shall assume a maximum of 20 days during which all excavation and other subsurface activities will be prohibited but other construction activities will be allowed.

F.5 OPERATIONAL WORK AREA ACCESS CONSTRAINTS (JAN 2018)

Access to the Launch Complex 39B construction site(s) will be limited due to ongoing operational requirements. No work will be allowed on the work site(s) except during assigned work windows.

(a) DEFINITIONS:

Work Window: A block of time, established by the Government, during which it is anticipated that scheduled launch or payload processing operations will permit on-site construction. The Contractor is responsible for completing construction tasks, including punch list items, within established work windows.

Downtime: A period of time within a work window when the Government must temporarily deny the Contractor access to the work site. The Government will provide twenty-four hour notice each time these restrictions are invoked. (Requests to excavate on days designated as “no dig days” must be submitted on KSC Form 50-1, Excavation Category Waiver, 7-10 days in advance of the designated “no dig days”.) Downtime days will be assessed when (1) a work window is active, and (2) the Government requires the Contractor to temporarily vacate the work site.

Days: Any reference to “days” shall be construed to mean calendar days.

(b) CONSTRAINTS:

(1) Access to the work sites for pre-construction activities occurring before the construction work window, such as field measurements and field investigations, must be coordinated with the Contracting Officer at least 7 days prior to desired access date.

(2) The Government shall notify the Contractor at least 7 days in advance of a work window.

Multiple work windows may occur. Each work window will be at least 7 days in duration. If the project involves work in more than one operational area, the contractor shall schedule all work activities in each area independently.

(3) Work windows may occur any time during the contract performance period. The Government will schedule each work window depending on the availability of access to the areas affected.

(c) ADDITIONAL REQUIREMENTS TO WORK WITHIN LAUNCH COMPLEX 39B

(1) Launch Complex 39B Access

(i) LC-39B is an Access Controlled Area within KSC. In addition to the security requirements in FAR 52.204-9, the following security controls apply:

All contractor personnel shall request a personal orange safety badge at the badging station located on SR 405 when receiving their initial KSC access/identification badges.

If previously badged, the employee shall request a personal orange safety badge from the badging station. This orange safety badge may be required to be deposited in a badge board to facilitate an active headcount of personnel on site after entering the LC 39B perimeter.

In order to receive “unescorted temporary area access” to the LC 39B perimeter and be able to escort up to five (5) personnel, at a minimum a person must take and pass the following training courses in SATERN (https://satern.nasa.gov) or live (as applicable), and retaken at the intervals noted in parentheses:

(A) QF110KSC, KSC General Hazards Familiarization (3-years)

(B) QF130KSC, Pad 39B Area Access Orientation (3-years)

(C) QG012KSC, General PSM - Process Safety Management (1-year)

(D) QG013KSC, SLS Limited Rights Training (No Expiration)

(E) QG014KSC, Class 1, Division 2 Familiarization (3-years)

(F) QE-WBT-243, Cleanliness & Contamination Control Overview (1-year)

(G) QE-WBT-244, Control of Foreign Object Debris (1-year)

(H) QG07CKSC, ELSA Training (1-year, Live Training Only—Schedule through COR)

The above training applies to all personnel (civil servant and contractor) at KSC requiring unescorted access to LC 39B. Lack of completion of the above training at the required intervals prior to badge expiration will result in denial of unescorted access to LC 39B. As noted in KSC 52.204-9, it is the contractor’s responsibility to keep training records of all personnel and have required training completed prior to expiration for each person. PLEASE NOTE: It typically takes 48-hours for training to update in the area access system, which may result in temporary revocation of access.

The government does not provide escorts for contractor personnel. The contractor is responsible for properly escorting personnel in compliance with security procedures.

As noted above, a person granted “unescorted temporary area access” may escort up to five (5) personnel who have been issued “to be escorted temporary area access.” The escorted personnel must remain in visual contact with the escort at all times, within reason (for example, the escorted personnel may use a restroom or work in a confined space with single entry like an electrical manhole, while the escort remains directly outside). Repeated reports of improperly escorted personnel by security personnel typically results in revocation of “unescorted temporary area access” for the escort and possible disciplinary actions.

(2) Entering Launch Complex 39B

All personnel entering Launch Complex 39B are required to be processed through LC-39B main gate. Personnel will be required to have approved access through the KSC NASA Access Management System (NAMS) prior to entry and coordinated with the COR.

Personnel will be approved for either unescorted or escorted access. Any personnel approved for unescorted access must have an escort with unescorted access approval.

All personnel approved for escorted access must be escorted at all times by personnel approved for unescorted access. Personnel approved for unescorted access may escort up to 5 personnel at any time unless specifically directed otherwise by the Contracting Officer.

Escorted personnel must remain within sight of the escort at all times.

(3) Driving within Launch Complex 39B Perimeter – Official Business Only

Non-government vehicles shall remain outside of the LC-39B perimeter. Non-government vehicles on official business that need to enter the LC-39B perimeter shall coordinate entry with the main gate prior to arrival on site. Access will only be allowed for official business associated with this contract. All non-government vehicles entering into the LC-39B perimeter shall have the company’s name prominently displayed on the vehicle.

(4) Field Office Trailer

Placement of any field office trailers shall be coordinated with the Contracting Officer or their representative. 120/240 volt power may not be located in the vicinity of the selected site. If electrical power is desired, the contractor will be responsible for extending and connecting power to the field office trailer from the closest available connection point. Field office trailers must be structurally sound and comply with hurricane wind loading requirements in the vicinity of KSC. Trailers shall be installed and anchored in accordance with KSC-PLN- 1904, Trailer/Equipment Tie Down Plan for the John F. Kennedy Space Center. The field office trailer cannot be installed within the LC39B perimeter until the post Artemis 1 work is to begin.

(5) Construction Laydown Area for LC39B

The construction contractor is required to closely coordinate a laydown area with the COR.

Lay down area may be located outside the perimeter of LC39B.

Prior to site mobilization, the contractor shall perform a laydown area walk down with the contracting officer or COR. During the walk down the contractor shall take pictures and document the state of the area. The pictures and documentation shall be put into a report and provided to the COR, for use in verifying that the site has been returned to the original condition at contract closeout.

SECTION G – CONTRACT ADMINISTRATION DATA

G.1 NASA FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 18) CLAUSES

NFS 1852.223-71 AUTHORIZATION FOR RADIO FREQUENCY USE (APR 2015)

G.2 NFS 1852.232-80 SUBMISSION OF VOUCHERS/INVOICES FOR PAYMENT (APR 2018)

(a) The designated payment office is the NASA Shared Services Center (NSSC) located at FMD

Accounts Payable, Bldg. 1111, Jerry Hlass Road, Stennis Space Center, MS 39529.

(b) Except for classified vouchers, the Contractor shall submit all vouchers and invoices using the steps described at NSSC’s Vendor Payment information web site at:

https://www.nssc.nasa.gov/vendorpayment. Please contact the NSSC Customer Contact Center at 1-877-NSSC123 (1-877-677-2123) with any additional questions or comments.

(c) Payment requests.

(1) The payment periods are stipulated in the payment clause(s) contained in this contract.

(2) Vouchers submitted under cost-type contracts and invoices submitted under fixed-price contracts shall include the items delineated in FAR 32.905(b) supported by relevant back-up documentation. Back-up documentation shall include at a minimum, the following information:

(i) Vouchers.

(A) Breakdown of billed labor costs and associated contractor generated supporting documentation for billed direct labor costs to include rates used and number of hours incurred.

(B) Breakdown of billed other direct costs (ODCs) and associated contractor generated supporting documentation for billed ODCs.

(C) Indirect rate(s) used to calculate the amount of billed indirect expenses.

(D) Progress reports, as required.

(ii) Invoices.

(A) Description of goods and services delivered as part of the contract’s terms and conditions, including the dates of delivery/performance.

(B) Progress reports, as required.

(C) Date goods and services were performed.

(iii) Fee vouchers.

(A) Listing of all provisionally-billed fee by period or date earned since contract award.

(B) A reconciliation of all billed and earned fee.

(C) A clear explanation of the fee calculations.

(d) Non-electronic payment requests. The Contractor may submit a non-electronic voucher/invoice using the steps for non-electronic payment requests described at https://www.nssc.nasa.gov/vendorpayment, when any of the following conditions are met:

(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor.

(2) The contract includes provisions allowing the contractor to submit vouchers or invoices using the steps for non-electronic payment requests. In such instances the Contractor agrees to submit non-electronic payment requests using the method or methods specified in Section G of the contract.

(e) Improper vouchers/invoices. The NSSC Payment Office will notify the contractor of any apparent error, defect, or impropriety in a voucher/invoices within seven calendar days of receipt by the NSSC Payment Office. Inquiries regarding requests for payment should be directed to the NSSC as specified in paragraph (b) of this section.

(f) Other payment clauses. In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payment requests.

(g) In the event that amounts are withheld from payment in accordance with provisions of this contract, a separate payment request for the amount withheld will be required before payment for that amount may be made.

(End of clause)

G.3 NFS 1852.245-82 OCCUPANCY MANAGEMENT REQUIREMENTS (SEP 2017)

(a) In addition to the requirements of the clause at FAR 52.245–1, Government Property, as included in this contract, the Contractor shall comply with the following in performance of work in and around Government real property:

(1) NPD 8800.14, Policy for Real Estate Management.

(2) NPR 8831.2, Facilities Maintenance and Operations Management.

(b) The Contractor shall obtain the written approval of the Contracting Officer before installing or removing Contractor-owned property onto or into any Government real property or when movement of Contractor-owned property may damage or destroy Government-owned property.

The Contractor shall restore damaged property to its original condition at the Contractor’s expense.

(c) The Contractor shall not acquire, construct or install any fixed improvement or structural alterations in Government buildings or other real property without the advance, written approval of the Contracting Officer. Fixed improvement or structural alterations, as used herein, means any alteration or improvement in the nature of the building or other real property that, after completion, cannot be removed without substantial loss of value or damage to the premises. Title to such property shall vest in the Government.

(d) The Contractor shall report any real property or any portion thereof when it is no longer required for performance under the contract, as directed by the Contracting Officer.

G.4 NFS 1852.245-83 REAL PROPERTY MANAGEMENT REQUIREMENTS (JAN 2011)

(a) In addition to the requirements of the FAR Government Property Clause incorporated in this contract (FAR 52.245–1), the Contractor shall comply with the following in performance of any maintenance, construction, modification, demolition, or management activities of any Government real property:

(1) NPD 8800.14, Policy for Real Estate Management.

(2) NPR 8831.2, Facilities Maintenance and Operations Management.

(b) Within 30 calendar days following award, the Contractor shall provide a plan for maintenance of Government real property provided for use under this contract. The Contractor’s maintenance program shall enable the identification, disclosure, and performance of normal and routine preventative maintenance and repair. The Contractor shall disclose and report to the Contracting Officer the need for replacement and/or capital rehabilitation. Upon acceptance by the Contracting Officer, the program shall become a requirement under this contract.

(c) Title to parts replaced by the Contractor in carrying out its normal maintenance obligations shall pass to and vest in the Government upon completion of their installation in the facilities. The Contractor shall keep the property free and clear of all liens and encumbrances.

(d) The Contractor shall keep records of all work done to real property, including plans, drawings, charts, warranties, and manuals. Records shall be complete and current. Record of all transactions shall be auditable. The Government shall have access to these records at all reasonable times, for the purposes of reviewing, inspecting, and evaluating the Contractor’s real property management effectiveness. When real property is disposed of under this contract, the Contractor shall deliver the related records to the Government.

(e) The Contracting Officer may direct the Contractor in writing to reduce the work required by the maintenance program authorized in paragraph (b) of this clause at any time.

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1 NASA FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 18) CLAUSES

NFS 1852.223-70 SAFETY AND HEALTH MEASURES AND MISHAP REPORTING (DEC

2015)

NFS 1852.223-75 MAJOR BREACH OF SAFETY OR SECURITY (FEB 2002)

NFS 1852.242-72 DENIED ACCESS TO NASA FACILITIES (OCT 2015)

H.2 NFS 1852.225-70 EXPORT LICENSES (FEB 2000)

(a) The Contractor shall comply with all U.S. export control laws and regulations, including the International Traffic in Arms Regulations (ITAR), 22 CFR Parts 120 through 130, and the Export Administration Regulations (EAR), 15 CFR Parts 730 through 799, in the performance of this contract. In the absence of available license exemptions/exceptions, the Contractor shall be responsible for obtaining the appropriate licenses or other approvals, if required, for exports of hardware, technical data, and software, or for the provision of technical assistance.

(b) The Contractor shall be responsible for obtaining export licenses, if required, before utilizing foreign persons in the performance of this contract, including instances where the work is to be performed on-site at NASA’s Kennedy Space Center, where the foreign person will have access to export-controlled technical data or software.

(c) The Contractor shall be responsible for all regulatory record keeping requirements associated with the use of licenses and license exemptions/exceptions.

(d) The Contractor shall be responsible for ensuring that the provisions of this clause apply to its subcontractors.

H.3 NFS 1852.243-72 EQUITABLE ADJUSTMENTS (APR 1998)

(a) The provisions of all other clauses contained in this contract which provide for an equitable adjustment, including those clauses incorporated by reference with the exception of the "Suspension of Work" clause (FAR 52.242-14), are supplemented as follows:

Upon written request, the Contractor shall submit a proposal for review by the Government. The proposal shall be submitted to the contracting officer within the time limit indicated in the request or any extension thereto subsequently granted. The proposal shall provide an itemized breakdown of all increases and decreases in the contract for the Contractor and each subcontractor in at least the following detail: material quantities and costs; direct labor hours and rates for each trade; the associated FICA, FUTA, SUTA, and Workmen's Compensation Insurance; and equipment hours and rates.

(b) The overhead percentage cited below shall be considered to include all indirect costs including, but not limited to, field and office supervisors and assistants, incidental job burdens, small tools, and general overhead allocations. "Commission" is defined as profit on work performed by others. The following percentages for overhead, profit, and commission are negotiated for this contract according to the nature, extent, and complexity of the work involved and shall not be exceeded on any equitable adjustments. These rates are negotiable, downward only, if the nature, extent, and complexity of the work involved on an equitable adjustment are not commensurate with the basic contract.

Overhead (Percent) Profit (Percent) Commission

To Contractor on work performed by other than its own forces

----- ----- 10 percent

To first tier subcontractor on work performed by its subcontractors

----- ----- 10 percent

To Contractor and/or subcontractors on work performed with their own forces

10 percent 10 percent -----

(c) Not more than four percentages for overhead, profit, and commission shall be allowed regardless of the number of subcontractor tiers.

(d) The Contractor or subcontractor shall not be allowed overhead or commission on the overhead, profit, and/or commission received by its subcontractors.

(e) Equitable adjustments for deleted work shall include credits, limited to the same percentages for overhead, profit, and commission in paragraph (b) of this clause.

(f) On proposals covering both increases and decreases in the amount of the contract, the application of the overhead, profit, and commission shall be on the net change in direct costs for the Contractor or the subcontractor performing the work.

(g) After receipt of the Contractor's proposal, the contracting officer shall act within a reasonable period, provided that when the necessity to proceed with a change does not permit time to properly check the proposal, or in the event of a failure to reach an agreement on a proposal, the contracting officer may order the Contractor to proceed on the basis of the price being determined at the earliest practicable date. In such a case, the price shall not be more than the increase or less than the decrease proposed.

H.4 KSC 52.222-6 SPECIAL ENCLAVE STATUS FOR KENNEDY SPACE CENTER (JUL 2018)

Pursuant to FAR 52.222-6, Construction Wage Rate Requirements:

The Kennedy Space Center (KSC) is part of a special enclave within Brevard County which includes the geographic area consisting of KSC, Cape Canaveral Air Force Station, and Patrick Air Force Base, as specified in the attached wage determination. The Department of Labor (DOL) designated KSC as a part of this special enclave in the 1960's during construction of the launch complex. The labor classifications and prevailing wages differ significantly from those contained in wage determinations for the surrounding areas and the process of determining the proper labor classifications for work to be performed may differ significantly from that in a non-enclave environment. Offerors should contact the DOL for instructions concerning selection of proper labor classifications for all KSC construction projects within this special enclave. The DOL local office phone numbers are (321) 242-1851/office and (321) 614-8823/mobile.

The selection of the proper labor classifications from the solicitation's wage determination for the pricing of bids/proposals is the responsibility of the offeror in consultation with the DOL. Post award the contractor should continue to be aware of any potential impact KSC's special enclave status might have during contract performance (e.g. contract modifications). It is incumbent upon the offeror to make potential subcontractors aware of KSC's special enclave status and to instruct them to contact DOL for instructions for choosing the proper labor classifications. The Agency will not make any official determination as to the proper labor classifications for work described in this solicitation.

The successful offeror shall be solely responsible for the employment of workers with the proper skills and payment of them in accordance with FAR 52.222-6, Construction Wage Rate Requirements, and the solicitation's wage determination. The Agency will monitor contractor compliance in accordance with 29 CFR 5.5. Non-compliance will be reported to the DOL. DOL will determine compliance with the Act and decide on enforcement actions. Any disputes concerning labor standards requirements will be handled by the DOL in accordance with FAR 52.222-14, Disputes Concerning Labor Standards.

H.5 KSC 52.223-121 REPORTING OF INCIDENTS INVOLVING WORKPLACE VIOLENCE

(JUL 2018)

The contractor shall conduct training on and develop procedures for recognizing, managing and responding to incidents and threats of workplace violence as defined in NASA Policy Directive (NPD) 1600.3, Policy on Prevention of and Response to Workplace Violence. Contractors shall also promptly report all incidents involving workplace violence to the Protective Services Office. If the NASA Threat Assessment Team (TAT) Chair and Co-Chair determine it is appropriate for the contractor to participate in a TAT meeting, the contractor shall comply with the TAT request. The contractor is also responsible for reporting disposition of the incident reported to the NASA TAT.

This requirement shall flow down to the subcontractors, however the subcontractors shall report up through the prime contractor.

H.6 KSC 52.242-90 CONTROLS APPLICABLE TO CONTRACTORS’ ACTIVITIES (JUL 2018)

The Contractor shall comply with the publications listed and those checked as applicable below, and subsequent revision thereof, that the Contracting Officer has indicated as being incorporated in this contract by reference. These publications prescribe regulatory and procedural criteria which are applicable to this contract. The contractor shall promptly take corrective action upon notice of noncompliance from the Contracting Officer or his/her authorized representative(s) with any provision of the publications listed below.

The Contractor shall comply with the following publication, which can be found at https://nodis3.gsfc.nasa.gov/displayDir.cfm?t=NPR&c=1600&s=4A:

NPR 1600.4A, Identity and Credential Management

The Contractor shall comply with the following publications and those publications checked as applicable below. These documents can be found at http://procurement.ksc.nasa.gov/PPD/documents:

KNPR 8715.2, Comprehensive Emergency Management Plan (CEMP) KNPR 1600.1, KSC Security Procedural Requirements KNPR 8500.1, KSC Environmental Management Requirements KNPR 8715.3, KSC Safety Procedural Requirements KNPD 1600.3, Use of Alcoholic Beverages on Kennedy Space Center (KSC) Property

Check if applicable:

[ ] KNPD 1810.1 KSC Occupational Medicine Program [ ] KNPR 1860.1 KSC Ionizing Radiation Protection Program [ ] KNPR 1860.2 KSC Nonionizing Radiation Protection Program [X ] KNPR 1820.3 KSC Hearing Loss Prevention Program [X ] KNPR 1820.4 SC Respiratory Protection Program [X ] KNPR 1840.19 KSC Industrial Hygiene Programs [ ] 45SWI40-201 45th Space Wing Instruction 40-201 Radiation Protection Program [X ] KNPR 1840.1 KSC Hazard Communication Program [ ] KNPR 1870.1 KSC Sanitation and Public Health Program [ ] KNPR 2570.1 KSC Radio Frequency Spectrum Management Procedural Requirements [ ] KNPR 4000.1 Supply and Equipment System Manual [ ] KNPR 6000.1 KSC Transportation Support System [X] KNPR 8715.7 KSC Construction Contractor Safety and Health Practices Procedural

Requir…

This is the start of the file's text. The full file is on GovTribe.