This document contains questions and answers related to a solicitation for upgrading the Environmental Control System at Launch Complex 39B at NASA's Kennedy Space Center. The solicitation seeks proposals to modify the existing ECS to support crewed Artemis missions on the Space Launch System. Key details include that the scope of work involves replacing an existing cooling tower, relocating ductwork, heaters and instrumentation, adding new high pressure ducts and heaters, replacing filter housings and valves, revising gaseous nitrogen piping from aluminum to stainless steel, modifying controls systems, installing new humidifiers, and related incidental work. The questions and answers provide clarification on technical requirements, schedules, and specifications to inform offeror proposals for the solicitation.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE PROPOSAL QUESTIONS AND ANSWERS 80KSC020R0024
No
Reference for Question (Section
Paragraph/Page) QUESTIONS ANSWERS Amendment
Number
I Series Drawings Per the I Series drawings, please provide the cable harness/sub assembly drawings for the following: 120E3400107, 120E3400122, 120E3400171, 120E3400082, 120E3400172, 120E3400099 & K0000082927.
See "All I Series Drawings" posted in beta.SAM.gov 0005
I Series Drawings Per the I Series drawings, please provide the following documents:
120E3100001 (Heavy Duty Cable Specification) 120E3100003 (Electrical Cable Fabrication Requirements)
See "All I Series Drawings" posted in beta.SAM.gov 0005
I Series Drawings Several of the remote I/O distributor cabinets indicate new cables (in bold) but the corresponding connector schedule shows them existing (not in bold). Example: Drawing I-505 oneline indicates cable designation 35423W13 is new. Drawing I-506 connector schedule shows this cable as existing. This is located on numerous cables throughout the I series drawings. Please confirm which drawing prevails.
List of consistancy corrections: Drawings I-519 thru I-524 RIO 35426 - cables for J54 and j61 are new…Drawings I-531 thru I- 536 RIO 35761 - cables for J36 through 43 are existing to remain, Drawings I-537 thru I-538 RIO 37568 -cables for J28, j61, j63, and 64 are existing to remain….Drawings I-539 thru I- 544 RIO 37462 - cables for J29 through J42, J47, through J60 are existing to remain.
Project Specific Requirements
Per Section J-B-15, please confirm the project superintendent will be required to complete OSHA 30 if his ceritficate is later than 5 years from the start of the project.
Yes. The project superintendent is required to complete the OSHA-40 if his or her certificate is later than 5 years from the start of the project.
5 Project Specific Requirements
Per Section J-B-16, please confirm no permits are required for this project.
No permits identified in J-B-16 are required for this project. 0004
6 Project Specific Requirements
Is a full time Site Safety & Health Officer required in addition to the project superintendent?
No, a full time SSHO is not a requirement. 0004
Project Specific Requirements
Is a full time QA/QC Manager needed in addition to the project superintendent?
A full time QA/QC manager is required in addition to the project superintendent. The QA/QC manager may fulfull other roles.
Bid Due Date With the July 4th holiday week there are vendors and trade partners that may be on vacation the week of July 6th. Would the government consider extending the bid date to the following week to ensure best pricing and coverage.
Proposal due date has changed. Verify the date and time on the most recent Amendment.
See conformed solicitation, page 1.
L.18 Non-Price Factors (Jan 2018); (b) Technical Experience Sub-Factor;
Pages 63 - 64
We understand that the page limitations for this Sub-Factor are limited to
(2) pages per contract/project. Would the Government permit the Offerors to also include a (1) page introduction at the beginning of this Sub-Factor to highlight the technical experience requirments (as listed on pages 68 and 69) for each of the submitted projects?
Yes. A one page introduction and summary outlining the overall technical experience is acceptable. Solicitation updated, see conformed solicitation pages 58 and 64.
L.18 Non-Price Factors (Jan 2018); (b) Technical Experience Sub-Factor;
(2) "Major Subcontractors" & (3) " MEI Subcontratcors";
Pages 63 - 64
Both of these paragraphs state that the Offerors shall identify three contracts/projects by major subcontractors and/or MEI subcontractors. Is the limit for each of these paragraphs three contracts/projects TOTAL, or three contracts/projects PER SUBCONTRACTOR?
Three contracts/project per MAJOR Subcontractor.
There is a potential of 17 projects; 5 from the Prime Contractor, 3 from Major Subcontractor One, 3 from Major Subcontractor Two, 3 from Major Subcontractor Three, & 3 from MEI Subcontractor.
No
Reference for Question (Section
Paragraph/Page) QUESTIONS ANSWERS Amendment
Number
L.18 Non-Price Factors (Jan 2018); (c) Past Performance Sub-Factor
We understand that the Offerors are to submit completed PPQs for each of their five projects featured in the Techanical Experience Sub-Factor. Are the Offeror's subcontractors (whose projects are also featured in that Sub- Factor) to submit completed PPQs for their projects as well?
Yes. Please provide PPQs for the major subcontractors featured in the subfactors.
01 32 01.00 10 Project Schedule
Is there a time constraint as to when this project needs to be completed? As identified in the solicitation Section F.1 paragraph (c), all physical on site work for the project is to be completed within the 180-day or 150-day period following NTP for the post-Artemis 1 launch.
The Artemis 1 launch is currently scheduled for July 2021 but may be delayed up to Nov 2021. A second NTP to proceed with the post-Aretmis work is expected within 30 days after launch.
Page 412 Section 3.3.2 Please clarify the specific insulation material used for Exposed ECS duct, Rectangular and Round.
Per drawing details on M-610, M-611, M-612, and general note 34 on M-101, the duct insulation is to be 3" thick rigid phenolic, Superwool 607 HT (high temperature), or equal.
Page 403 Section 2.4.20 Please clarify what Jacket is used for duct insulation, rigid and flexible. Per spec section 23 07 00, 2.4.2.1, and details on drawings M- 610 and M-615, duct insulation jacket is to be white PVC. This spec section indicates the PVC jacket is to be 0.24 inches thick, which is incorrect. The PVC jacket thickness requirement will be revised to indicate "the pipe and fitting covers shall be white PVC, 1 or 2 piece, high impact strength, ultraviolet resistant rating, with minimum thickness of 0.030 inches".
15 Page 400 Section 2.2.1.4 Is there Phenolic Insulation as mentioned in this section for High temperatures?
Superwool 607 HT, or equal. This is for high temperature applications.
Drawing M-615 Can you clarify the specs on Pyrogel as mentioned on "Typical double wall duct flange insulation detail" specificaly the jacketing thickness.
The Pyrogel insulation is specified in detail MBY on sheet M-
615. The jacketing is to be white PVC per spec section 23 07 00,
2.4.2.1. This spec section indicates the PVC jacket is to be 0.24 inches thick, which is incorrect. The PVC jacket thickness requirement will be revised to indicate "the pipe and fitting covers shall be white PVC, 1 or 2 piece, high impact strength, ultraviolet resistant rating, with minimum thickness of 0.030 inches".
17 I Series Drawings Per I-537 drawing cable legend please provide cable type and manufacture for part number 29502.
Cable is a four conductorR, #12, Belden part number 29502 0005
No
Reference for Question (Section
Paragraph/Page) QUESTIONS ANSWERS Amendment
Number
Welding Requirements What are the welding requirements for 23 00 00 2.7.1.3, 2.7.1.4, 2.7.1.7 and 2.9. We would like to weld all ECS ductwork to D17.0 clause 9, paragraph option 2 and AWS D9.1 sheet metal code and inspection shall be per AWS D17.1 clause 9, paragraph 9.2 option 2, class c visual only.
As identified in 23 00 00 2.7.1, all ductwork is to be fabricated to ASME B31.3. In addition for all ECS pipe and pressure ductwork, magnetic particle or liquid penetrant for aluminum examinations shall be performed on 100 percent of multi-pass thickness, root and cap passes, and any 1/2 inch filler pass in-between.
Specs will be updated via Section C.2 update in next Amendment.
19 Access Ladder The access ladder does not have any details. Is this ladder to be standard un-caged access ladder?
Yes, the access ladder is an un-caged ladder similar to the current existing ladder.
Ref: I 702 and 703 Is the location for the new MIL-Spec connectors added to the enclosures a firm fixed location or is there flexibility in the locations? (ref sheets I-702 and I-703)
Yes the locations are flexible as constructability is the major factor in the connector locations. All connector relocations will need to be submitted in shop drawings for review
Sheet 1-702 Details for
RIO 3
On Sheet I-702 the right side detail for RIO 3 does not reflect existing conditions and cannot be located as indicated. Should these be moved to the top of the enclosure?
Yes. Locations can be adjusted as needed and shall be submitted in shop drawings.
1-613 I-613 shows a breaker added for each new connector on Enclosure 37568.
Note A indicates this is not to be connected to a power source. The reference drawing on I-703 does not show where the additional 22 breakers are to be installed. Please clarify the construction of this rail as to if it is to be a single rail configured for 1 source, or split for the 2 existing incoming sources as well as the impact to the testing requirements if the work indicated in note A is not completed prior to the start of this contract and the devices powered from these breakers are not functional.
The contractor to provide and install all circuit breakers, devices, and associated mounted hardware and cables. Cables configurations shall be per each cable identification labels. The breakers to be installed in side 37568. All end devices to be connected by dedicated cables shown on drawings. RIO 37568 is existing (two sources) . The power is existing and available, it should not be an issue for conducting the functional test.
Modification of the existing Source of power upstream is not part of this contract.
40 95 00, Section 3.3.1 Per 40 95 00, Section 3.3 .1 describes full loop calibration back to the PLC and validated at the HMI, but NASA is responsible for the PLC and any modifications to it. Section 3.3.3 provides exclusions of responsibility for the contractor but does not exclude errors due to PLC programming, HMI displays, or functionality controlled by the PLC. Please clarify the extent of the Controls testing required for this contract (It appears to be the intent for this contract to test to a prefunctional test level) and extent of the responsibility for functions/operations related to the PLC and
SCADA.
Controls testing will be limited to a pre-functional testing (i.e.
testing of the individual components to ensure functionality within the requirements identified in the contract documents).
The contractor will not have any responsibility for the PLC and
SCADA.
40 95 00 section 3.4 Per 40 95 00 Section 3.4 This contract requests a step by step procedure for system start-up as one of the required items. NASA is responsible for the programming, sequence of operations, and operation of the PLC and SCADA. Please clarify the contractor's responsibility under this Section.
System start up only as required for prefunctional testing. 0006
No
Reference for Question (Section
Paragraph/Page) QUESTIONS ANSWERS Amendment
Number
1-207 I-207 indicates Panel 35441 to be replaced and remains with modifications. Please confirm this is to be an entirely new enclosure with functionality as described on I-301 note C and I-302 note D and just reusing the enclosure number "35441" for the new panel.
Concur, new panel enclosure as described in drawings panel number being reused.
Drawing M-402, Note A, Note M-405 Note B
Is the contractor to use the existing supports on reloacted humidifiers? Is the same type of supports to be used on the new humidifiers? Note: No support details for humidifiers are shown on drawings.
If an existing humidifier is being relocated to the same location, then the existing support system may be re-used. Otherwise provide a new support system as indicated on the Humidifer Support Detail on drawing M-614 Detail MBW.
General Overall Phase 1 question
Please confirm during Phase 1 that there will be no work in the ECS building despite the many notes to the contrary on the drawings.
Only work that cannot impact the existing ECS can be included in Phase 1. Predominantly, this work is exterior of ECS building.
However, the contractor may identify work fronts that are believed to not have an impact to the existing ECS. The Government will review these work fronts and approval is required prior to start of work.
28 RFP page 67 para B Please clarify the evaluation of price proposals See updated and added paragraphs in solicitation section M.1 (c)(4).
Specifications We were unable to locate a specification for the cleanliness of the existing duct/removed and moved duct for this project. Are there specifications for this?
The ductwork is to be left in a "Generally Clean" condition as indicated on drawing M-101, Note 16 and Note 24. Also refer to spec section 23 00 00, 3.11 for vacuum clean and wipe clean.
RFP page 64 para F.1 c Contract Line Item 0002
Please confrim that the alternate proposal is to be completed for the entire PRE-ARTEMIS 1 launch scheduled for July 1st 2021 assuming a NTP will be issued by July 31, 2020 and not July 31st 2021 as stated.
Two NTPs will be issued. One shortly after contract award for the Pre-Artemis I launch work. The Pre-Artemis I launch work is to be completed prior to the launch of Artemis I. The Artemis I launch is currently scheduled for July 2021 but may be delayed up to Nov 2021.
The second NTP to proceed with the Post-Aretmis I work, will be issued, and is expected within 30 days, after the Artemis I Launch. As identified in the solicitation Section F.1 paragraph (c), all physical on site Post-Artemis I launch work for the project is to be completed within the 180-day or 150-day period following second NTP.
See update to solicitation section F.1 (c).
M-318 thru M-329 We have unable to locate an insulation specification for the duct work in the tunnel The insulation for the double wall ductwork in the tunnel shall be 3" thick phenolic, Superwool 607 HT or equal, as indicated on drawing M-611.
32 RFP pages 59-60, Section L.15
The RFP says "Any late propsals will be reviewed IAW FAR 15.208 (b)(1)(i)." Please confirm if a proposal is submitted on July 10th, before 2:00PM, say 7:50 AM, but doen't show up until after 2:00 PM, say 2:05 PM, if that proposal would be accepted since it was sent before the 2:00 PM due date and time.
No, it would be late and not accepted.
Proposals sent via email must be received at the initial point of entry to the Government infrastructure not later than 5:00 p.m.
one working day prior to the date specified for receipt of proposals.
No
Reference for Question (Section
Paragraph/Page) QUESTIONS ANSWERS Amendment
Number
33 Reference M-203, Zone A/4 & S-301
Zone A/4 shows a arrow stating 6” raised concrete pad. Is a new pad to be poured over the existing and or is the existing to be repaired only per details SAC, SAD & SAE on S-301? If a new pad is required, will it be poured on top of the existing pad up to existing cold water lines, drain and existing electrical panels?
6" raised concrete pad is the existing pad to be repaired per details on S-301.
34 Reference M-205, Detail
MSB
Detail MSB shows cross hatched lines for demo of the cooling tower. On each side it shows a slab that stays which is under some of the removed areas. How is the area to be finished ?
Chip below slab surface and trowel apply patch material similar
SAD/S-301.
35 Reference S-301 Detail SZ shows a typical house keeping pads and a detail for a curb.
Where do these details apply?
Although SW and SY/S-301 should cover all new pads required, SZ/S-301 is included for any other typical housekeeping pads that may be required.
36 Reference S-301
Detail SAB shows a typical reinforcement for wall pipe penetrations.
Where do these detail apply?
This detail will apply for any pipes that needed to be routed through walls and slab for detail SY/S-301. If pipes are to be routed through any other new concrete slab or wall, this detail shall apply.
37 Reference S-301 Detail SAA shows a typical corner bar for concrete wall construction.
Does this detail apply to Detail SY Transformer Pad Detail?
Yes. Provide corner bars shown in SAA/S-301 to SY/S-301. 0006
38 Reference M-313 & M-
M-313 zone HG/5 shows the demo of existing valve A199216 EX-MOV- 019 ¾”? M-322 zone AB/6 shows the relocation of the existing valve A199216, ¾” . It appears the size of ¾” is in error. What is the actual size of the existing valve A199216?
3/4" is the intended size of the valve. It is used for GN2 bleed for safety in compliance with DE-512
39 Reference M-322
M-322 zone AB/6 shows a new valve A601103, MOV-024, ¾” . It appears the size of ¾” is in error. What is the actual size of the existing valve A601103? Also, The new valve A601103, MOV-024 is not shown on any new valve schedules. Please provide valve information for pricing purposes?
3/4" is the intended size of the valve. It is used for GN2 bleed for safety in compliance with DE-512. The schedule for MOV-024 is in the GN2 component schedule on sheet M-508.
Reference Specification Section 22 15 13.16 40, GN2 PIPING, PIPING
COMPONENTS, AND
VALVES, STAINLESS,
3.1.2.1 Joints ensure that field weld-joints conform to the requirements of the AWS WHB-2.9 and ASME B31.3. ASME B31.3 requires a service call out in the specification and or on the drawings. No service call outs have been identified. Is the contractor to assume normal fluid service for the GN2 piping?
Normal fluid service is acceptable. 0006
Reference Specification Section 22 15 13.16 40, GN2 PIPING, PIPING
COMPONENTS, AND
VALVES, STAINLESS,
3.1.2.1 Joints second paragraph states “Piping systems rated at 350 psi and lower require butt weld joints made with backing rings”. If the welding is to be per ASME B31.3 normal fluid service or better then 5% x-ray at a minimum will be required. Weld joints with backing rings will not satisfactorily pass x-ray. Please advise
Radiographic testing per ASME BPV Code, Section 5, Article 2 does not require removal of backing. However, if radiographic testing is not feasible due to equipment limitations, ASME B31.3 allows the use of UT or in-process examination in accordance with paragraph 344.6 or 344.7, respectively.
42 Reference AA-102 AA-102 shows chilled water system in a dashed configuration. AA-101 Test results schedules do not reflect chilled water system for abatement. Is any work associated with the dashed lines?
On drawing AA-102, All chilled water piping was recently replaced and does not contain ACM, and is therefore not in the abatement scope of work.
No
Reference for Question (Section
Paragraph/Page) QUESTIONS ANSWERS Amendment
Number
43 Reference M-206, zones F/7,8 & D5,6&7, H/3
The following components are not shown on the new component Schedule on M-210. Please provide valve information for pricing purposes?
•A601046 •A601047 •A601048 •A601050 •A601051 •A601052
On drawing M-206, Some of the devices were incorrectly labeled. Changes are as follows: Zone F-7 - A number A601046 changes to A601106, A601047 changes to A601107 and A601048 changes to A601108. Zone D5/6 - A601050 changes to a601110, A601051 changes to A601111 and A601052 changes to A601112.
Reference M-210, New Condensor Water Schedule
The following components are not shown on the P&ID on M-206. Please advise to their locations :
•A601106 •A601107 •A601108 •A601109 •A601110 •A601111 •A601112 •A601113 •A601114
On drawing M-206, Some of the devices were incorrectly labeled. Changes are as follows: Zone F-7 - A number A601046 changes to A601106, A601047 changes to A601107 and A601048 changes to A601108. Zone D5/6 - A601050 changes to a601110, A601051 changes to A601111, A601052 changes to A601112 and A601053 changes to A601113. Zone H-3 - A601049 changes to A601109, and Zone F-3 - A601054 changes to A601114.
45 FA-101, FA-201, FA-301 Please rpovide exisitng system configured drawings for the systems shown on these sheets
Documents posted in beta.SAM.gov 0006
46 FA-201 Provide drawings showing exiting VESDA sampling pipe On drawing FA-201, the sampling tube is shown, see Flag Note A, zone H-2.
47 FA-201 Are all of the fire alarm devices in this room to be removed? On drawing FA-201, all existing devices are to remain and be recommissioned. See Flag Note B, zone H-2.
48 FA-201 Are all of the fire alarm devices in this room to be reinstalled? On drawing FA-201, all existing devices are to remain and be recommissioned. See Flag Note B, zone H-2.
49 M-508
Drawing M-508 provides a brief specification of the panel filters and says custom made by VACCO or approved equal. Must be B31.3 compliant.
The VACCO representative is declining to bid the project. Are comparable products from the following manufacturers be acceptable:
3B, Norman. Please concur or advise.
On drawing M-508 NEW GN2 FILTER SCHEDULE, the two cells under “DESCRIPTION/MODEL” column are changed to:
"100% EFFICIENT AT 70 MICRONS AND 98% EFFICIENT
AT 40 MICRONS, ASTM B31.3 COMPLIANT. BASIS OF
DESIGN IS CUSTOM MANUFACTURED FROM NORMAN
FILTER COMPANY OR APPROVED EQUAL. PROVIDE
WITH TWO S.S. TAPS AND DIFFERENTIAL PRESSURE
GAUGE (0-5PSI) AND 1/4” STAINLESS STEEL TUBING
AND TWO S.S.TUBING SHUT-OFF VALVES."
See updated Drawings via Solicitation Section C.2(b)(6).
No
Reference for Question (Section
Paragraph/Page) QUESTIONS ANSWERS Amendment
Number
50 Amendment 0006, Question 16
Please confirm that PVC jacket .030 is to be used on all double wall flange insulation kits over pyrogel for ECS ducts in the tunnel and above grade? Note: Detail MBY on M- 615 states use Stainless jacket over pyrogel. If stainless jacket is be used what is the thickness required?
Stainless steel jacketing is required for all flange insulation applications on double-wall aluminum and double-wall stainless steel ducts in the tunnels and above the bulkhead plate and shall be minimum 0.016” thick. PVC jacketing is allowed on the interior single-wall ducts only.