Questions And Answers 2.pdf

PDF 13 KB Posted

Attached to
Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B Federal contract opportunity
Solicitation number
80KSC020R0024
Issued by
National Aeronautics and Space Administration Kennedy Space Center

About this file

This document contains pre-proposal questions and answers for solicitation number 80KSC020R0024 to upgrade the Environmental Control System at Launch Complex 39B at NASA's Kennedy Space Center. NASA requires the upgraded ECS to support the crewed Space Launch System Artemis II mission. The scope of work includes replacing the existing cooling tower, relocating ductwork, heaters and instrumentation, adding new heaters and high pressure ducts, replacing filter housings and valves, revising gaseous nitrogen piping from aluminum to stainless steel, modifying controls systems hardware, installing new humidifiers, and related incidental work. The questions and answers provide clarification on drawings, specifications, support details, pricing evaluation, duct cleanliness standards, and insulation requirements for the ductwork in the tunnel area.

View the file

Other files for this federal contract opportunity

Other files attached to Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B, newest first.
File Type Posted
80KSC020R0024 LC39B ECS Amendment 08 Slip page.pdf PDF
Questions And Answers 4.pdf PDF
80KSC020R0024 Amendment 0008 Conformed Solicitation.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 to 4.pdf PDF
80KSC020R0024 Amendment 0008 with Attachments.pdf PDF
80KSC020R0024 LC39B ECS Amendment 07 Slip Page.pdf PDF
80KSC020R0024 Amendment 0007 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0007 with Attachments.pdf PDF
80KSC020R0024 Attachment J-C Wage Determination.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 to 3.pdf PDF
80KSC020R0024 LC39B ECS Amendment 06 Slip Pages.pdf PDF
80KSC020R0024 Amendment 0006 with Attachments.pdf PDF
Questions And Answers 3.pdf PDF
80KSC020R0024 Amendment 0006 Conformed Solicitation.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 and 2.pdf PDF
80KSC020R0024 Amendment 0005 with Attachments.pdf PDF
80KSC020R0024 LC39B ECS Amendment 05 Slip Pages.pdf PDF
80KSC020R0024 Amendment 0005 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0004 with Attachments.pdf PDF
80KSC020R0024 LC39B ECS Amendment 04 Slip Pages.pdf PDF
Questions And Answers 1.pdf PDF
80KSC020R0024 Amendment 0004 Conformed Solicitation.pdf PDF
80KSC020R0024 J-A Amend 0003 Conformed.pdf PDF
80KSC020R0024 J-B Amend 0003 Conformed.pdf PDF
Example Submittal Matrix.xlsx XLSX spreadsheet
80KSC020R0024 Amendment 0003 with Attachments.pdf PDF
ECS Site Visit Attendence.pdf PDF
80KSC020R0024 LC39B ECS Amendment 01 Slip Pages.pdf PDF
Section L Appendix 6 Badging Request Form (Includes TAA).docx DOCX document
80KSC020R0024 Amendment 0002.pdf PDF
80KSC020R0024 LC39B ECS Amendment 02 Slip Page.pdf PDF
80KSC020R0024 Amendment 0002 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0001.pdf PDF
80KSC020R0024 Amendment 0001 Conformed Solicitation.pdf PDF
Section L Appendix 3 Pre-Proposal Inquiry Form.xlsx XLSX spreadsheet
Section L Appendix 1 KSC Form 28-889 Visitor Badge Request.pdf PDF
80KSC020R0024 ECS Solicitation.pdf PDF
80KSC020R0024 Attachment J-A Deliverables.pdf PDF
Section L Appendix 2 Acceptable Identity Guide.pdf PDF
80KSC020R0024 Attachment J-D Progress Payments.pdf PDF
80KSC020R0024 Attachment J-C Wage Determination.pdf PDF
80KSC020R0024 Attachment J-G Badging ID Process.pdf PDF
Section L Appendix 5 Small Business Subcontracting Goals.docx DOCX document
Section L Appendix 4 PPQs.docx DOCX document
80KSC020R0024 Attachment J-B Project Requirements.pdf PDF
80KSC020R0024 Attachment J-J JOFOC.pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE PROPOSAL QUESTIONS AND ANSWERS 80KSC020R0024

Amendment 0005

No

Reference for Question (Section

Paragraph/Page) QUESTIONS ANSWERS Amendment

Number

I Series Drawings Per the I Series drawings, please provide the cable harness/sub assembly drawings for the following: 120E3400107, 120E3400122, 120E3400171, 120E3400082, 120E3400172, 120E3400099 & K0000082927.

See "All I Series Drawings" posted in beta.SAM.gov 0005

I Series Drawings Per the I Series drawings, please provide the following documents:

120E3100001 (Heavy Duty Cable Specification) 120E3100003 (Electrical Cable Fabrication Requirements)

See "All I Series Drawings" posted in beta.SAM.gov 0005

Page 412 Section 3.3.2 Please clarify the specific insulation material used for Exposed ECS duct, Rectangular and Round.

Per drawing details on M-610, M-611, M-612, and general note 34 on M-101, the duct insulation is to be 3" thick rigid phenolic, Superwool 607 HT (high temperature), or equal.

15 Page 400 Section 2.2.1.4 Is there Phenolic Insulation as mentioned in this section for High temperatures?

Superwool 607 HT, or equal. This is for high temperature applications.

17 I Series Drawings Per I-537 drawing cable legend please provide cable type and manufacture for part number 29502.

Cable is a four conductorR, #12, Belden part number 29502 0005

19 Access Ladder The access ladder does not have any details. Is this ladder to be standard un-caged access ladder?

Yes, the access ladder is an un-caged ladder similar to the current existing ladder.

Ref: I 702 and 703 Is the location for the new MIL-Spec connectors added to the enclosures a firm fixed location or is there flexibility in the locations? (ref sheets I-702 and I-703)

Yes the locations are flexible as constructability is the major factor in the connector locations. All connector relocations will need to be submitted in shop drawings for review

Sheet 1-702 Details for

RIO 3

On Sheet I-702 the right side detail for RIO 3 does not reflect existing conditions and cannot be located as indicated. Should these be moved to the top of the enclosure?

Yes. Locations can be adjusted as needed and shall be submitted in shop drawings.

1-207 I-207 indicates Panel 35441 to be replaced and remains with modifications. Please confirm this is to be an entirely new enclosure with functionality as described on I-301 note C and I-302 note D and just reusing the enclosure number "35441" for the new panel.

Concur, new panel enclosure as described in drawings panel number being reused.

Drawing M-402, Note A, Note M-405 Note B

Is the contractor to use the existing supports on reloacted humidifiers? Is the same type of supports to be used on the new humidifiers? Note: No support details for humidifiers are shown on drawings.

If an existing humidifier is being relocated to the same location, then the existing support system may be re-used. Otherwise provide a new support system as indicated on the Humidifer Support Detail on drawing M-614 Detail MBW.

28 RFP page 67 para B Please clarify the evaluation of price proposals See updated and added paragraphs in solicitation section M.1 (c)(4).

Specifications We were unable to locate a specification for the cleanliness of the existing duct/removed and moved duct for this project. Are there specifications for this?

The ductwork is to be left in a "Generally Clean" condition as indicated on drawing M-101, Note 16 and Note 24. Also refer to spec section 23 00 00, 3.11 for vacuum clean and wipe clean.

M-318 thru M-329 We have unable to locate an insulation specification for the duct work in the tunnel The insulation for the double wall ductwork in the tunnel shall be 3" thick phenolic, Superwool 607 HT or equal, as indicated on drawing M-611.

File details come from the government source that posted it. Updated .