This federal solicitation seeks proposals to upgrade the Environmental Control System at Launch Complex 39B at Kennedy Space Center. The scope of work includes replacing the existing cooling tower and relocating ductwork, heaters and instrumentation. It also requires adding new heaters and high pressure ducts, replacing filter housings and valves, revising existing controls systems hardware, installing new humidifiers, and other incidental related work. The upgraded ECS will provide conditioned purge air to support Space Launch System Artemis missions. The solicitation was issued by NASA and proposals are due by the date specified in the solicitation document.
View the file
Other files for this federal contract opportunity
Show all 46
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NASA/KSC SOLICITATION 80KSC020R0024
ATTACHMENT J-B – KSC PROJECT SPECIFIC REQUIREMENTS
KENNEDY SPACE CENTER PROJECT SPECIFIC REQUIREMENTS APPLICABLE TO ALL
WORK PERFORMED UNDER THIS CONTRACT
The Kennedy Space Center project specific requirements supporting Contract Section I are identified in this Attachment J-B. Nothing contained in this Attachment J-B shall relieve the Contractor from complying with other requirements of this contract, which are not identified and described in this Attachment J-B. All costs associated with the requirements of this Attachment J-B are included in the firm-fixed price of this contract.
J-B-1 UTILITY OUTAGE, ENERGIZED ELECTRICAL WORK, ELECTRICAL HAZARD
ANALYSIS, AND EXCAVATION PERMITS (JAN 2017)
(a) Utility Outage Requests and Electrical Work Permits
(1) Utility Outage Requests: All outages required during the prosecution of work which affects utility systems, such as electrical, water, fire detection and protection systems and air handling systems will require permits. Work shall be scheduled to hold outages to a minimum. Request for utility outage permits shall be made in writing to the Contracting Officer at least fourteen working days in advance of the time required. The request shall state the system involved, area involved, approximate time of outage, and the nature of the work involved. The fact that the Contractor requests an outage for a specific time period does not necessarily mean that the outage will take place. Due to the nature of the operations at Kennedy Space Center, the Contractor probably will not know until the day before the requested date if the outage will take place as scheduled. All outages will take place outside regular working hours. The Contractor will not be entitled to additional payment for working irregular hours due to outages.
(2) Electrical Work Permits: Prior to beginning work on an electrical system under an approved outage, the Contractor shall obtain an executed Work Permit (KSC Form KSC-26-400NS) from the Base Operations and Spaceport Services (BOSS) Contractor, and then execute complex lockout/tag-out procedures for all Work Permit related work as follows:
(i) The Contractor’s employee in charge of the required lockout/tag-out shall be present at the time the Government switches high-, medium-, or low-voltage circuits under Government access control which are to be locked and tagged out by the Contractor. The Contractor shall coordinate with the Contracting Officer’s Representative (COR) for the required switching period time and date. Due to KSC operational considerations the switching period time and date may be at any time, and outside of normal working hours or work days.
(ii) Once Government switching is complete the Contractor’s employee in charge of the lockout/tag-out shall sign the Work Permit and immediately install the required OSHA compliant lockout / tag-out on the required switching device(s). Once installed the Contractor’s employee in charge of the lockout/tag-out shall individually note the locations of the locks and tags on the Work Permit form.
(iii) A lockout/tag-out lock box shall be used for all such lockout / tag-outs. The key(s) from the lock(s) installed by the Contractor’s employee in charge of the lockout/tag-out shall be placed in the box and the employee in charge shall place an additional personal lock on the lock box to secure the keys inside. The lock box shall be kept at the work site and all other Contractor employees shall attach their personal lockout/tag-out on this box at any time they are working on the applicable equipment.
(iv) At the start of the first standard work period following the lockout/tag-out of a
Government switched circuit for which a Work Permit is issued, the Contractor’s employee in charge of the lockout/tag-out shall complete the required lockout/tag-out (lock box) procedures. Immediately upon completing the lockout/tag-out the Contractor shall verify no voltage is present on all circuit conductors using suitable testing equipment, safe work practices, and all required personal protective equipment. All other circuit safeguards such as grounding shall occur immediately after the voltage test and each safeguard shall be individually recorded on the Work Permit.
(b) Energized Electrical Work and Hazard Analysis
(1) Live parts to which an employee might be exposed shall be put into an electrically safe work condition before an employee works on or near them, unless the employer can demonstrate that de-energizing introduces additional or increased hazards or is infeasible due to equipment design or operational limitations. If live parts are not placed in an electrically safe work condition (i.e., due to increased or additional hazards or infeasibility), work to be performed shall be considered energized electrical work. Safety plans, job hazard analysis, and work practices for work on or in proximity to energized parts shall be in accordance with KNPR 8715.7, KSC Construction Contractor Safety and Health Practices Procedural Requirements.
(2) Electrical Hazard Analysis:
Arc-flash and shock prevention personal protective equipment (PPE) is required for all energized electrical, work and where energized or exposed live parts may not be present, but a potential hazard exists including: manhole or cable vault/tray insulated cable inspections, circuit breaker or switch operation, and de-energized voltage checks to electrically safe equipment.
The Contractor shall provide a qualified electrical safety professional to perform an arc-flash and shock hazard analysis in accordance with NFPA 70E for all such electrical work. The analysis shall be submitted with the Contractor’s Site Specific Safety Plan (SSSP) and referenced in any applicable Job Hazard Analysis (JHA). The safety professional shall perform and review a power system analysis using computer software specifically designed for the purpose to determine short circuit levels and arc flash hazard incident energy at all locations to be worked on by the Contractor. Table 130.7(C) (9) in NFPA 70E may be used in lieu of calculations when all applicable general notes for the table apply. The Government will provide source short circuit levels and clearing times for Government operated electrical source equipment as well as any applicable design information. The analysis shall include a table summarizing the results of the analysis with the following information for each location or piece of equipment:
(i) Protective Device Name
(ii) Protective Device Clearing Time
(iii) Maximum Voltage
(iv) Calculated Bolted Three Phase Fault Level
(v) Calculated Bolted Ground Fault Level
(vi) Calculated Minimum Arcing Fault Level
(vii)Arc-Distance if applicable for the calculation
(viii) Employee Working Distance
(ix) Calculated Arc-Flash Boundary
(x) Calculated Maximum Arc-Flash Incident Energy
(xi) Arc-Flash PPE Category
(xii) Shock Prevention PPE Insulating Class
(xiii) Limited Approach Boundary
(xiv) Restricted Approach Boundary
(xv) Prohibited Approach Boundary
(3) Electrical Manhole / Vault Confined Space Requirements: Reference KNPR 8715.7, KSC Construction Contractor Safety and Health Practices Procedural Requirements. During the site specific safety plan submittal phase, the Contractor shall complete a hazard evaluation of confined space(s) ensuring all hazards associated with the space or that may be introduced to the space have been identified and mitigated. The Contractor's designated safety professional shall coordinate with the Contracting Officer’s Representative (COR) to complete a confined space hazard assessment (KSC Form 28-750NS) in accordance with KNPR 1840.19, KSC Industrial Hygiene Programs, for each confined space, and to schedule a job-site inspection meeting with KSC Environmental Health and Safety personnel. Within 35 calendar days after this meeting the COR will provide a confined space hazard assessment to the Contractor. This assessment must be complete prior to any manhole entry and will be used in generating the confined space entry permit(s) required for the project.
The contractor shall provide supplementary lighting for all manhole work.
(c) Excavation Permits:
The Contractor shall request and obtain excavation permit(s) prior to performing any excavation.
KSC Form 26-312V3 NS, Utility Locate/Excavation Permit Request, shall be prepared by the Contractor and submitted to the Government for approval at least 15 working days prior to the planned excavation date. The Contractor shall comply with the requirements of the Base Operations and Spaceport Services (BOSS) Contractor’s "Utility Locate / Excavation Permit Procedure” ENG-I- MP07 (latest revision), in the preparation, submission and use of the permit(s).
(End of Project Specific Requirement)
J-B-2 FIRE PROTECTION AND REQUIRED PERMITS (MAR 2014)
The KSC Fire Department will provide fire suppression, inspection and rescue services to the Contractor as necessary. The Contractor shall:
(a) Provide approved fire extinguishers of appropriate type for hazards involved.
(b) Report all fires to the Fire Service at 867-7911 or 867-1911.
(c) Comply with all requirements of KHB 1710.2C Section 504 (Heat Producing Devices) and NSS
1740.11 “NASA Safety Standard for Fire Protection” Section 702 and Chapter 8 for work performed at the Kennedy Space Center.
(d) Provide a fire watch in accordance with Federal OSHA Safety and Health Standards 29 CFR
1926.352/1910.252 when required by the welding and burning permitting official.
(e) Prevent false fire alarms by providing 24-hour advance notice to the Contracting Officer's
Representative (COR) when construction activities in areas protected by fire alarm and/or detection systems may produce airborne particulates (smoke or dust) caused by construction activities such as painting, stripping, cutting drywall or concrete, sandblasting, and/or removing raised floor panels.
(f) Request permits for all welding and burning operations. Requests for these permits shall be made in writing to the Government at least seven (7) working days in advance of the time required.
(g) Report in the Contractor’s Safety and Health Plan how it intends to comply with the above requirements.
J-B-3 PERMANENTLY INSTALLED SAFETY SYSTEMS (MAR 2014)
(a) The Contractor shall protect and in no way interrupt the service of any installed safety systems or personnel safety devices.
(b) In the event that the Contractor requires entrance into systems serving safety devices, the Contractor shall obtain prior approval from the Contracting Officer. In the event the Contractor determines that it is necessary to temporarily remove or render inoperable any personnel safety devices in order to accomplish contract requirements, the Contractor shall provide alternate means of protection prior to removing or rendering inoperable any permanently installed safety devices or equipment and shall obtain prior approval of the Contracting Officer.
J-B-4 TRAFFIC RESTRICTIONS (MAR 2014)
(a) The Contractor will not move oversized loads and/or slow moving vehicles on established roads within the Kennedy Space Center from 6:30 A.M. to 8:30 A.M. and 3:30 P.M. to 5:30 P.M. on week days. Other than the above restricted hours, the Contractor may move oversize and/or slow moving vehicles to the work site provided all requirements of the Florida State Highway Department have been met.
(b) Movement of any Contractor vehicle in excess of maximum width, height and length specified by
Florida Statues Chapter 316 shall be accompanied by the Contractor's designated Convoy
Commander. The Contractor's Convoy Commander shall be totally responsible for the oversized vehicular movement to include making a physical inspection for possible obstructions along the intended route and obtaining all required special permits.
J-B-5 STORAGE AND PROTECTION OF MATERIAL TO BE RE-USED (MAR 2014)
All items of material to be removed and re-installed by the Contractor shall be protected during removal and stored in a manner such that the material will not be damaged during removal or storage. Any material designated for re-use, which is not suitable due to the Contractor's damage, will be replaced by the Contractor at no additional cost to the Government.
J-B-6 MAINTENANCE OF GOVERNMENT EQUIPMENT (MAR 2014)
(a) Government systems and equipment in the Contractor's work area may require servicing, maintenance, or modification by Government support contractors during the contract performance period. This maintenance activity may include work on systems, including underground utilities, that connect with Contractor installed systems and equipment. The Contractor shall allow the Government support contractors into his work area to perform the maintenance work.
(b) Existing systems and equipment require periodic maintenance that cannot be readily defined in terms of frequency and duration. This maintenance will be coordinated with the Contractor through the Contracting Officer, and will be performed on a non-interference basis as much as possible. The Contractor shall notify the Contracting Officer regarding any uncoordinated maintenance activity.
(c) The Contractor shall arrange and conduct a joint pre-operations briefing with Government support contractor personnel on each occasion that the support contractor requires access to the contractor’s work area. The Contractor shall take the following steps as required to prevent collateral damage to, or interference with, Contractor installed systems and equipment.
(1) Verify the scope and limits of the support contractor’s planned maintenance activity.
(2) Advise the support contractor regarding the scope of the Contractor’s work that may be affected by the maintenance activity, including specific locations and dimensions of planned or installed facilities, systems and equipment. Notify the Contracting Officer immediately regarding any resulting conflicts or interferences.
(3) Ensure that temporary barriers or protective measures are provided as needed to protect
Contractor installed work and preserve job-site safety.
The Contractor shall notify the Contracting Officer immediately regarding any issues that cannot be resolved with the support contractor.
J-B-7 AVIATION OBSTRUCTION LIGHTS (MAR 2014)
The Contractor will provide at least two Aviation Red Obstruction Lights or two High Intensity White Obstruction Lights on all structures over 100 feet above ground level. All construction cranes/booms shall be lighted regardless of height. Lights must be constructed and installed in accordance with U.S. Department of Transportation, Federal Aviation Administration publication AC 70/7460-1F (as revised), Chapter 4, paragraph 15, subparagraph e. Lights will be operated during all periods of reduced visibility, between sunset and sunrise, and as directed by the Contracting Officer.
J-B-8 INTERFERENCES AND COORDINATION OF WORK (MAR 2014)
(a) The Contractor shall coordinate construction layout, systems configuration and work scheduling to avoid interference’s between the various construction trades and their installations. Interferences and obstructions resulting from lack of Contractor coordination shall be corrected by the Contractor as approved by the Contracting Officer. All components, fittings and reworking necessary for such corrections shall be provided by the Contractor at no additional cost to the government. Dimensions shown for existing work, and all dimensions required for work that is to connect to existing work, shall be verified by the Contractor by actual field measurement of the existing work. Any work at variance with that specified or shown in the drawings shall not be performed by the Contractor until approved in writing by the Contracting Officer.
(b) To the extent possible, the as-built dimensions of all new work shall be verified by actual field measurement prior to ordering or fabricating mechanical, electrical, or specialty equipment and materials to be installed. If such field measurement is not possible, then the contract drawings and applicable shop drawings shall be checked by the contractor for dimensional accuracy prior to ordering or fabricating equipment and materials to ensure proper fit for field installation.
(c) The Contractor shall be responsible for correction of all field fitup problems and interferences which could have been avoided by field measurement or drawing checks prior to equipment fabrication.
J-B-9 RESTORATION OF GRASSED AREAS DISTURBED BY CONSTRUCTION (MAR 2014)
The Contractor shall, prior to completion of the contract, grass all areas disturbed by construction activities by seeding and mulching or, when erosion may occur, by sodding, except where specifically directed otherwise in the drawings and specifications.
J-B-10 TEMPORARY CONSTRUCTION TRAILERS (MAR 2014)
(a) The Government will provide a location for temporary office and/or storage facilities if needed for performance of on-site work under this contract. Specific location(s) at or reasonably close to the work site will be identified at the pre-work conference. The contractor is responsible for providing his own telephone service and for making his own connections to KSC utility services, if provided.
(b) All temporary facilities must be structurally sound, in roadworthy condition, and shall be installed and anchored in accordance with KSC-PLN-1904, Trailer/Equipment Tie Down Plan for the John F.
Kennedy Space Center; or Rules of Department of Highway Safety and Motor Vehicles, Division of Motor Vehicles Chapter 15C-1, whichever is more stringent. Copies of the standards will be made available to the contractor at the pre-work conference. The contractor shall provide written certification of compliance for all temporary facilities to the Contracting Officer within three days of installation. Any facilities that fail to meet these requirements shall be immediately removed from Government property.
(c) All temporary facilities shall be removed from government property within two weeks following final acceptance of work performed under this contract.
J-B-11 CONFINED SPACE WORK REQUIREMENTS (MAY 2019)
(a) Special requirements, coordination, and precautions will apply to any contract work taking place in confined spaces. Each contractor contracted to perform work in confined spaces is required to provide a written program for such work as part of its health and safety plan which is consistent with the requirements of 29 CFR 1910.146. For work in telecommunications manholes, provisions of 29 CFR 1910.268(o) are also applicable. The contractor shall coordinate any such work in confined spaces with the KSC Environmental Health Support Contractor, KSC Fire Services Support Contractor, and any other resident government or contractor organization whose employees may have access to the work location. The provision of environmental health services by the government does not prohibit the contractor from providing their own atmospheric testing. Government provided services include environmental health monitoring and consultation support for testing of atmospheres in confined spaces as well as fire rescue and emergency medical services.
(b) Entry into and work in confined spaces shall be in accordance with the requirements of KNPR
8715.7, KSC Construction Contractor Safety and Health Practices Procedural Requirements, and all other applicable clauses of this contract.
(c) Confined spaces, which contain water, shall be pumped out by the contractor prior to scheduling a confined space entry check. Prior to pumping water out, the contractor must verify that water does not show any signs of contamination (sheen or smell of petroleum). If contamination is suspected, stop work and notify the Contracting Officer.
(d) In addition to the requirements set forth above, the Contractor shall notify and obtain approval from the Power Coordinator, telephone 321-867-7300, and/or from Communications Control, telephone 321-867-4141, respectively, prior to performing work in electrical and/or communications manholes.
J-B-12 AFFIRMATIVE PROCUREMENT (MAY 2019)
(a) Affirmative Procurement (AP) is the purchase of environmentally friendly products and services (i.e.
products made from recycled or recovered materials). Federal agencies, their Contractors and subcontractors are required to maximize the purchase materials on the list of “EPA Designated Guideline Items” with the minimum recycled or recovered materials content whenever practicable according to RCRA 6002 and EO 13101. The requirements of RCRA 6002 include the following language:
“The decision not to procure such items shall be based on a determination that such procurement items:
(A) are not reasonably available within a reasonable period of time
(B) fail to meet the performance standards set forth in the applicable specifications or fail to meet the reasonable performance standards of the procuring agencies and/or
(C) are only available at an unreasonable price
Any determination under subparagraph (B) shall be made on the basis of the guidelines of the National Institute of Standards and Technology in any case in which such material is covered by such guidelines.”
(b) The Contractor shall provide AP approved items as specified within the contract documents.
Submittals for AP items shall be provided for approval in accordance with Shop Drawing provisions.
If the Contractor proposes to substitute an item that does not conform with AP requirements, the applicable Shop Drawing shall be accompanied by KSC Form 8-69, Contractor Request to Use Nonconforming Parts or Material (Deviation/Waiver Request, identifying the reason for the proposed substitution.
(c) Non-conforming items without approved D/W’s will be rejected and the contractor shall be responsible for any costs and schedule impacts associated with replacing such non-conforming items at no additional cost to the Government.
(d) At the conclusion of the project, the Contractor shall provide the Contracting Officer (CO) with a report itemizing all AP items used.
(e) Detailed information on the EPA AP specified/approved products and manufacturers providing these products is available at www.epa.gov/cpg/products.htm.
J-B-13 SPILLS (MAY 2019)
(a) The Contractor shall make all reasonable and safe efforts to contain and control any spills or releases that may occur. The Contractor shall immediately report (by phone) any occurrence of a pollution incident or spill, first to the Emergency 911 (321-867-7911 from a non 867/861 exchange), then to the Contracting Officer (CO). The Contractor shall document the incident or spill on KSC Form 21- 555, "Pollution Incident Report," and submit it to the CO and NASA Environmental Assurance Branch within 24 hours of the incident.
(b) The Contractor shall provide spill response materials to contain and control spills including, but not limited to, containers, absorbent material, shovels, and personal protective equipment. Spill response materials shall be available at all times in which materials/wastes are being handled or transported.
Spill response materials shall be compatible with the type of material being handled.
(c) The KSC Spill Cleanup Team will be responsible for the final cleanup and validation of a spill or release.
(d) The Contractor’s prompt action to minimize the impacted area and to timely report any occurrence will increase the Spill Cleanup Team’s ability to complete the spill cleanup and therefore reduce the Contractor’s liability for a larger cleanup.
J-B-14 REGULARLY SCHEDULED STATUS MEETINGS (JAN 2017)
The Contractor shall attend weekly progress/status meetings to be scheduled by the Contracting Officer for the purpose of determining progress status, delay factors, material delivery schedules, status of shop drawing submittals, and any other pertinent issues. In addition, a representative of each first tier subcontractor may be required to be present for the meeting.
J-B-15 SUPERINTENDENT ASSIGNMENT
ALTERNATE 2
SUPERINTENDENT ASSIGNMENT – FULL TIME (DEC 2016)
Pursuant to clause 52.236-6, entitled "Superintendence by the Contractor," the contractor shall assign a superintendent, on the contractor’s payroll, who will be 100 percent committed to superintending the work required by this contract. The superintendent shall not fill any other positions in performance of this contract or any other concurrent contract. One or more alternate superintendents, each with full authority to supervise the work, shall be designated in writing and approved by the Contracting Officer. The superintendent or an alternate shall be physically present at each work site at all times during performance of the contract and until the work is completed and accepted.
The individual(s) appointed as superintendent(s) shall complete the OSHA 30 hour Construction Course prior to starting any field work on the project. The class shall be taught by an authorized provider of the course (e.g., United Safety Council, Florida Safety Council) and be attended in person. The appointed superintendent(s) shall provide the course completion certificate to the government stating the required training and testing was satisfactorily completed and the date of completion. The course completion date shall not be greater than 5 years from the start of the contract.
J-B-16 PERMIT REQUIREMENTS (MAY 2019)
(a) No on-site work will be allowed until the appropriate authority issues all required permits. Permits may include, but are not limited to: air construction, dewatering, borrow pit, potable water, sanitary sewer, stormwater, National Pollutant Discharge Elimination system (NPDES), and wetlands. The following permits are known to be required for this project:
None
(b) The Contractor is responsible for obtaining the following permits, if required, before beginning work on the subject systems:
FDEP/Brevard County Onsite Sewage Treatment and Disposal System Construction/Permit Abandonment
FDEP/Brevard County Well Construction/Abandonment Permit.
National Pollutant Discharge Elimination System (NPDES) Construction General Permit (CGP)
Dewatering Permits (Florida Department of Environmental Protection [FDEP] and St. Johns
River Water Management District [SJRWMD]
FDEP Air Construction Permit
(c) The Contractor shall comply with the terms and conditions of these permits. The Contractor shall provide copies of these permits as well as copies of all documentation submitted as part of the application process to the NASA Environmental Assurance Branch (EAB) through the Contracting Officer (CO) as delineated in contract documents or as directed by the CO.
(d) The Contractor shall not begin construction before receiving all Federal, State, and local construction permits as indicated in this section. Included in adherence thereto is compliance with all conditions of the permit as well as requirements given in the laws, ordinances, and regulations. The Contractor shall be responsible for payment of any fines from government agencies resulting from the Contractor's failure to adhere to all identified permit conditions and agency regulations. These shall include, but are not limited to, material and construction standards, environmental protection, certifications, notifications, and monitoring requirements.
(e) Upon issuance of the Notice to Proceed, the CO shall make copies of all Government provided permits with conditions related thereto available to the Contractor. The Contractor shall keep copies of the permits and related materials such as drawings.
J-B-17 HAND EXCAVATION (MAR 2014)
Due to numerous existing underground utilities, all excavation in the areas listed below will be dug carefully, using hand tools ONLY. Contractor shall hand dig a pilot trench to locate existing utilities before motorized equipment is used in the areas listed below. Excavation in areas within 5 feet of all existing utilities shall be by hand.
Fill in: Drawing Sheet Zone
79K40792 UM-202 F7-C7
J-B-18 AIR MONITORING DURING CONSTRUCTION (MAR 2014)
The Contractor shall not allow any person to store, pump, handle, process, load, unload or use in any process or installation volatile organic compounds (VOC) or organic solvents (OS) without applying known and existing vapor emission control devices or systems deemed necessary and ordered by the Florida Department of Environmental Protection (FDEP). To comply, procedures to minimize pollutant emissions shall include the following:
(a) Tightly cover or close all VOC containers when they are not in use.
(b) Tightly cover, where possible, all open troughs, basins, baths, tanks, etc. when they are not in use.
(c) Maintain all piping, valves, fittings, etc. in good operating condition.
(d) Prevent excessive air turbulence across exposed VOCs.
(e) Immediately confine and clean up VOC spills and make sure volatile emitting wastes are placed in closed containers for reuse, recycling, or proper disposal in accordance with KSC Specific Project Requirement titled “Hazardous Wastes” and “Spills.”
J-B-19 BIOLOGICAL SURVEYS (MAY 2019)
The Contractor shall notify the Contracting Officer (CO) to request that NASA Environmental Assurance Branch (EAB) perform a biological survey, fourteen (14) days prior to start of work. The Contractor shall not begin land clearing, equipment laydown, or site disturbance activities, including exterior lighting and roof work, before receiving written approval from the CO stating that the biological survey is completed and all mitigation action (e.g. Threatened and Endangered (T&E) species relocation/protection, identification and protection of plant species of special concern) to be performed by the Government or Contractor has been completed.
J-B-20 CONCRETE WASTEWATER (MAR 2014)
The following checked paragraphs are applicable to this acquisition:
CONCRETE WASHOUT
The Contractor shall not allow wastewater from standard concrete construction activities (such as on-site material processing, concrete curing, foundation and concrete clean-up, water used in concrete trucks, forms, directional drilling, etc.) to enter waterways or to be discharged before being treated to remove pollutants.
The Contractor shall dispose of the construction-related concrete wastewater and concrete excess by collecting and placing it in a contractor constructed settling pond where suspended material can be settled out and/or the water can evaporate to separate solids from the water. The location of the settling pond shall be coordinated with and approved by the Contracting Officer (CO). The Contractor shall remove and dispose of the residue left in the pond and restore site to original condition. Disposal of solidified concrete shall be performed in accordance with the Solid Waste KSC Project Specific Requirement.
LIGHTWEIGHT CONCRETE
Reference contract KSC Project Specific Requirement entitled “Hazardous Wastes”. The use of light-weight concrete materials has been confirmed to have the potential to be hazardous due to pH but may also exhibit other hazardous characteristics depending upon processes and products used. The contractor shall not allow wastewater from light-weight concrete construction activities (such as on-site material processing; concrete curing; concrete clean-up; and water used in concrete trucks, forms, etc.) to enter waterways or to be discharged on the ground before being analyzed for hazardous waste characteristics. A representative sample shall be collected from the first "flush" of light-weight concrete wash water waste at the time of generation, and will be analyzed by the government for hazardous waste characteristics. Pending completion of this analysis, all such waste water shall be containerized, labeled, and handled in accordance with the “Unknown Wastes” in “Hazardous Wastes” KSC Project Specific Requirement.
If the waste wash water from light-weight concrete usage is determined to be hazardous, it shall be handled, stored, labeled, and managed as hazardous waste in accordance with RCRA regulatory requirements and applicable contract provisions.
If the analysis shows the wash water is not hazardous, this wash water waste and any additional wash water waste generated at the same job using the same product and process may be handled as described under “Concrete Washout” paragraph above.
J-B-21 HISTORICAL, ARCHAEOLOGICAL, AND CULTURAL RESOURCES (MAY 2019)
(a) If known historical or archaeological resources have been identified within the Contractor’s work area, and are designated on the contract drawings, the Contractor shall install protection for these resources as shown on the drawings and shall be responsible for their preservation during the contract and shall have a Florida State-certified archaeologist on-site during all excavations.
(b) If during excavation or other construction activities, any previously unidentified or unanticipated historical, archaeological, and cultural resources are discovered or found, all activities that may damage or alter such resources shall be temporarily suspended. Resources covered by this paragraph include but are not limited to any human skeletal remains or burials; artifacts; shell, midden, bone, charcoal, or other deposits; rock or coral alignments, pavings, wall, or other constructed features; and any indication of agricultural or other human activities. Upon such discovery or find, the Contractor must immediately notify the Contracting Officer (CO) or the COR and NASA Environmental Management Branch (EMB).
J-B-22 STORAGE TANK REPORTING/SPCC (MAY 2019)
(a) Onsite temporary storage tanks must be Underwriter’s Laboratory (UL) Southwest Research Institute (SWRI) or Steel Tank Institute (STI) approved for the product stored. Temporary storage tanks shall comply with applicable requirements of the National Fire Protection Association (NFPA) Standard 30: Flammable and Combustible Liquids Code. These tanks shall be located/sited in a location that will minimize impacts to the environment in the event of a leak (not near swales, storm water systems, surface waters, wetlands, or storm drains or inlets). They shall be equipped with secondary containment to catch drips and leaks from the tank, or be double walled. Construction operations are not covered in the overall KSC Spill Prevention, Control and Countermeasures (SPCC) Plan due to their temporary nature. Each construction Contractor is required to create a project specific SPCC Plan for their activities on KSC if oil is stored in excess of an aggregate aboveground container capacity greater than 1,320 gallons (only containers greater than or equal to 55 gallons are counted).
The SPCC Plan must be signed (self-certified) by a Contractor Responsible Authority, adhere to the requirements of 40 CFR 112, and be delivered to the Contracting Officer (CO) before bringing any storage tanks that are subject to this KSC Specific Project Requirement on site. KSC Form 21-555, KSC Pollution Incident Reporting and Notification, shall be required for all releases of hazardous materials.
(b) Permanent storage tanks greater than 550 gallons containing petroleum products, or water mixed with petroleum products, must be registered with the Florida Department of Environment Protection (FDEP). The Contractor shall fill out a storage tank facility registration form for an Underground Storage Tank (UST) and/or Aboveground Storage Tank (AST) and submit the form to the CO and the NASA Environmental Assurance Branch (EAB), prior to final inspection before tank is placed into service. The EAB will sign and send the registration to the Florida Department of Environmental Protection (FDEP). The Contractor shall notify the CO forty-five (45) days prior to installation of any registered tank so that a written notice of tank installation can be provided to the regulatory authority, by the EAB at least thirty (30) days prior to tank installation as required. In addition, the EAB shall be notified 5 days before any of the following activities in order to schedule inspections with the Brevard County Natural Resource Management Office (BCNRMO):
(1) Delivery of the tank to KSC/CCAFS.
(2) Completed installation inspection request for BCNRMO allowing the tank to be fueled and placed into service.
(3) Final operational inspection request for BCNRMO to verify system is operating.
(c) AST registration and regulations are covered in Florida under FAC 62-762. Notifications of installation, upgrading, internal inspections, testing, incidents, discharge, and closure are detailed under 62-762.451. The EAB shall be notified 45 days before initiating the removal of any registered underground storage tank system. An additional notification to EAB is required 5 days before tank removal so a BCNRMO inspection can be scheduled if necessary.
J-B-23 TOXIC METALS (MAR 2014)
Representative samples of painted surfaces within the project area have been identified to contain toxic metals. The Contractor shall assess hazards and brief government of their proposed methods of removal and disposal of building materials identified as having toxic coatings and hazardous materials. The Contractor’s hazard assessment shall be conducted by a competent health and safety professional. The Contractor shall notify the Contracting Officer of hazard mitigation activities and abatement procedures 14 days prior to disruption to any suspected area.
J-B-24 PCB MANAGEMENT (MAY 2019)
Polychlorinated Biphenyls (PCB) wastes may include, but are not limited to, oil-filled transformers, oil-contaminated transformer concrete pads, light ballasts, capacitors, electric motors, pumps and paint coatings.
PCB wastes shall be managed in accordance with 40 CFR 761. PCB waste management and disposal shall be coordinated through the Contracting Officer (CO), a KSC Form 26-551 "Process Waste Questionnaire" (PWQ) and Technical Response Package (TRP) shall be prepared and processed in accordance with KSC Project Specific Requirement titled “Hazardous Wastes”.
Government Assistance – KSC has established procedures for the handling, storage and disposal of PCB contaminated waste streams generated on the Center. To aide with proper compliance of site-specific requirements, the Government will assign a NASA Environmental Point of Contact (EPOC) for each project.
The establishment of the NASA provided EPOC in no way relieves the contractor for compliance with requirements defined in 40 CFR 761.
LIQUIDS CONTAMINATED WITH PCBs
PCB containers storing liquid PCBs at concentrations of 50 parts per million (ppm) or greater shall be removed from the generator accumulation site within 24 hours from the date the PCB item was removed from service. This support shall be coordinated through the Contracting Officer for waste pickup scheduling before removal from service. The Contractor shall contact the Contracting Officer for pick-up and removal of all PCB related waste. The Contractor shall not remove any oil filled transformers from KSC. Unless analysis results determine PCB content in oil less than 2 ppm, the contractor shall coordinate any disposal of liquid PCBs through the Contracting officer.
(a) For Equipment containing PCB concentration in OIL >= 500 ppm
LIQUIDS: Drained oil must be stored in a DOT approved container and marked with a PCB label (with the date the equipment was removed from service). Containerized liquid PCB waste must be moved to PCB storage facility immediately (within 24 hours). Coordinate effort through EPOC - 5 day notice prior to removal from service is required.
CARCASS or CONTAINER: Drained equipment must be marked with a PCB label (with the date the equipment was removed from service), stored on an impervious surface, covered from rain, and moved offsite within 30 calendar days.
(b) For Equipment containing PCB concentration in OIL >50 ppm but < 500 ppm
LIQUIDS: Drained oil must be stored in an adequate container on an impervious surface, covered from rain, labeled, and moved offsite immediately (within 24 hours).
CARCASS or CONTAINER: Drained equipment must be stored on an impervious surface, covered from rain, dated and moved offsite as soon as practicable (not to 180 exceed days). If carcass paint is analyzed for PCBs and results < 50 ppm - No storage, marking, or dating requirement are required under TSCA regulations. Provide analysis results to RRMF along with KSC Form 7-49 to recycle.
All protective coatings that contain PCB shall be handled in accordance with the requirements of this section.
Where Safety Data Sheets for protective coatings are available and indicate the presence of PCBs, sampling is not required. Sampling and analysis for PCBs shall be conducted for coatings where presence of PCBs has not been determined based on age of coating and/or prior analysis results of same or like coatings.
The following waste generator standards will be used for the accumulation and storage of PCB waste materials:
(a) PCB wastes listed below may be stored temporarily at a waste generator accumulation site for up to thirty (30) days from the date removed from service. The container and labeling shall comply with the TRP. The date the PCB item was removed from service shall be marked on the container label per the TRP.
(1) Non-leaking articles and equipment. PCB articles are manufactured articles containing PCBs whose surfaces have been in direct contact with PCBs. These articles include capacitors, transformers, electric motors, and pumps.
(2) Leaking articles and equipment placed in non-leaking PCB containers with sufficient materials to absorb any liquid PCBs remaining in the item. PCB containers are any devices used to contain PCBs or PCB articles whose surfaces have been in direct contact with PCBs.
(3) PCB containers storing non-liquid PCB wastes such as contaminated soil and debris.
(b) PCB containers storing liquid PCBs at concentrations of 50 parts per million (ppm) or greater shall be removed from the generator accumulation site to the PCB Storage Building (K7-115) within 24 hours from the date the PCB item was removed from service. Support shall be coordinated through designated KSC Waste Management personnel for waste pickup before removal from service date to allow for waste pickup scheduling and to avoid regulatory violations. The Contractor shall contact KSC Waste Management for pick-up and removal of hazardous/PCB waste. Documentation including the waste type, quantity, locations, and organization responsible for the waste shall be provided on KSC Form 28-809 “Waste Support Request” to KSC Waste Management when requesting waste disposal. The Contractor shall fax the waste support request to KSC Waste Management at fax 867-9466.
The Contractor shall not remove any oil filled transformers from KSC. The Contractor shall only take drained transformers to the Reutilization, Recycling and Marketing Facility (RRMF) (M6-1671) at Ransom Road. Within the six (6) month period prior to delivery to RRMF, transformers shall have an oil analysis showing PCB content. At the request of the Contractor, the CO will arrange for all sampling and testing to determine the proper handling and disposal of the transformers. If the oil sample is greater than 50 ppm, the transformer cannot be managed through the RRMF and must be managed through KSC Waste Management per application Process Waste Questionnaire Technical Response Package (PWQTRP) instructions. Within 48 hours of having the transformer ready for disposal, the Contractor shall contact the EPOC assigned to the project to coordinate with KSC Waste Management for pick-up and removal of hazardous/PCB waste. The EPOC will submit the waste pickup request through the on-line Waste Management System. At the request of the NASA Project Manager, the EPOC will arrange for all sampling and testing to determine the proper handling and disposal of the stained or painted concrete. Lab analysis that is older than six months will not be considered valid analysis and re-sampling must be completed.
PCB BULK PRODUCT WASTE (SOLIDs)
PCB Bulk Product Waste is defined in 40 CFR 761.3 as waste derived from manufactured products containing PCBs in a non-liquid state at any concentration, where the concentration of PCBs at the time of designation for disposal is greater than or equal to (≥)50 ppm. The contractor shall dispose of all coated waste with a PCB concentration over the 50 ppm limit in the Schwartz Road landfill (see Schwartz Road Landfill KSC Project Specific Requirement) if not determined to be a hazardous waste. NASA requires all contractors generating metal-based waste containing PCB contaminated coatings with PCBs ≤50 ppm to recycle this material (see Recycling and Salvaging KSC Project Specific Requirement). If these materials cannot be recycled due to excessive cost in segregation or handling, the contractor shall dispose of this waste in the same manner as PCB Bulk Product Waste.
J-B-25 HAZARDOUS WASTES (MAY 2019)
Hazardous and controlled waste shall be managed in accordance with all applicable statutes, rules, orders, and regulations which may include but are not limited to 40 CFR Parts 260 - 268, 273, 279, 761 and KNPR
8500.1 KSC Environmental Management Requirements. All hazardous waste generated during the execution of this contract shall be disposed of by the Government. Unless directed by the Contracting officer, in no case shall the Contractor or the Contractor’s representative transport hazardous waste from KSC. KSC Form 26-551, Process Waste Questionnaire (PWQ), shall be prepared and processed for all waste streams generated during execution of this project.
(a) The Contractor shall be responsible for identifying processes and operations and the location and nature of all potentially hazardous and controlled waste and their containers, as defined in 40 CFR Parts 261, 273, 279, or 761. KSC has established policies and procedures in place to assist the contractor for characterization, handling and storage of wastes generated on KSC. Any request for assistance shall be in writing and submitted to the Contracting officer.
(b) Contractor personnel generating and managing the waste shall have hazardous waste training per 40
CFR 262.17 and KNPR 8500.1, Hazardous Waste Storage section. The Contracting Officer may at any time during the course of the contract performance period require the Contractor to provide individual training records for any employee involved in the performance of this contract, and the contents of the course or courses completed to satisfy the training requirements. Attendance at KSC Training Course QG-211 "Hazardous Waste Management" will satisfy the above training requirements.
(c) The Contractor shall prepare copies of Safety Data Sheets (SDS) for each material utilized on the project and provide copies to the Contracting Officer (CO) thirty (30) days before the start of the waste generation process. No substances shall be delivered to KSC without the appropriate Safety Data Sheets.
GOVERNMENT ASSISTANCE
KSC has established procedures for the handling, storage and disposal of hazardous waste. To aide with proper compliance of site-specific requirements, the Government will assign a NASA Environmental Point of Contact (EPOC) for each project. The EPOC shall, upon request, assist with waste hazard determination, packaging, labeling, and disposal requirements for waste generated on KSC. The establishment of the NASA EPOC in no way relieves the contractor for compliance with requirements defined in 40 CFR Parts 261, 273, 279, or 761.
WASTE CONTAINERS
The Government will provide DOT compliant storage containers and labels upon request. The Contractor shall request the storage containers, by providing quantity and type needed, in writing to the Contracting Officer a minimum of one week before the required need date. For projects that will be generating large quantities of waste (>500 gallon or 75 cu feet), a two week notice must be provided to the CO to ensure availability of waste containers.
SATELLITE WASTE ACCUMULATION AREA (SAA)
The Contractor shall establish an on-site Satellite Waste Accumulation Area (SAA) within 50 feet of and within sight of any point where hazardous or controlled wastes may be generated. If an SAA must be more than 50 feet from the point of generation, or out of sight of the generator, the Contractor shall provide a written request to the CO fourteen (14) days before the start of the waste generating process. The CO will send a notification to the NASA Environmental Assurance Branch (EAB) for their review and concurrence. The EAB will then request approval for a non-routine Satellite Waste Accumulation Area from Florida Department of Environmental Protection. The Contractor shall not place the SAA in service before receiving written approval of the variance from the CO. The Contractor shall store potential or identified hazardous and/or controlled wastes in the appropriate properly labeled containers inside the SAA in accordance with KNPR 8500.1 (as revised).
HAZARDOUS WASTE SATELLITE ACCUMULATION AREAS
This clause applies to FDEP/EPA SAA that are the responsibility of the contractor. See KNPR 8500.1 latest revision for more information. For these areas, the following apply (request examples of documentation from the contracting officer, if needed):
(a) A contingency plan is required to be submitted to the NASA Environmental Assurance Branch through the Contracting Officer for review at least 30 calendar days prior to establishing a SAA and posted at the site
(b) Waste must be managed in accordance with 40 CFR 260-279, Protection of Environment
(c) The SAA is required to be roped off with signs saying, “Danger – Unauthorized Personnel Keep
Out,” posted on each side of the roped off area. The sign must also include name and phone number for the contractor’s responsible person(s)
(d) No smoking signs are required to be posted conspicuously on each side of this roped off area
(e) At least 7 calendar days prior to creating the SAA, the contractor shall hold a training for all personnel who could generate a waste to include but not limited to - how to know they have generated a hazardous waste; know the waste must be…