80KSC020R0024 Amendment 0007 with Attachments.pdf

PDF 680 KB Posted

Attached to
Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B Federal contract opportunity
Solicitation number
80KSC020R0024
Issued by
National Aeronautics and Space Administration Kennedy Space Center

About this file

This document contains an amendment to a federal solicitation and the related solicitation opportunity. The amendment provides an updated Department of Labor wage determination and modifies the solicitation's attachment listing. The solicitation is for upgrade of the Environmental Control System at Launch Complex 39B for NASA's Kennedy Space Center. The project scope includes replacement and relocation of various ECS components such as a cooling tower, ductwork, heaters, instrumentation, filter housings and valves. It also involves modifying gaseous nitrogen piping, control systems hardware, addition of humidifiers, and other incidental work. The National Aeronautics and Space Administration is the contracting agency. The upgraded ECS is required to support crewed Space Launch System Artemis II missions. No changes were made to the proposal due date of July 14, 2020.

View the file

Other files for this federal contract opportunity

Other files attached to Upgrade Environmental Control System (ECS), Launch Complex (LC) 39B, newest first.
File Type Posted
80KSC020R0024 LC39B ECS Amendment 08 Slip page.pdf PDF
80KSC020R0024 Amendment 0008 with Attachments.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 to 4.pdf PDF
Questions And Answers 4.pdf PDF
80KSC020R0024 Amendment 0008 Conformed Solicitation.pdf PDF
80KSC020R0024 LC39B ECS Amendment 07 Slip Page.pdf PDF
80KSC020R0024 Amendment 0007 Conformed Solicitation.pdf PDF
80KSC020R0024 Attachment J-C Wage Determination.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 to 3.pdf PDF
80KSC020R0024 LC39B ECS Amendment 06 Slip Pages.pdf PDF
80KSC020R0024 Amendment 0006 with Attachments.pdf PDF
Questions And Answers 3.pdf PDF
80KSC020R0024 Amendment 0006 Conformed Solicitation.pdf PDF
Questions And Answers 2.pdf PDF
80KSC020R0024 Amendment 0005 with Attachments.pdf PDF
80KSC020R0024 LC39B ECS Amendment 05 Slip Pages.pdf PDF
80KSC020R0024 Amendment 0005 Conformed Solicitation.pdf PDF
80KSC020R0024 ECS at LC39B Questions And Answers 1 and 2.pdf PDF
80KSC020R0024 Amendment 0004 Conformed Solicitation.pdf PDF
Questions And Answers 1.pdf PDF
80KSC020R0024 LC39B ECS Amendment 04 Slip Pages.pdf PDF
80KSC020R0024 Amendment 0004 with Attachments.pdf PDF
80KSC020R0024 J-A Amend 0003 Conformed.pdf PDF
80KSC020R0024 J-B Amend 0003 Conformed.pdf PDF
80KSC020R0024 Amendment 0003 with Attachments.pdf PDF
ECS Site Visit Attendence.pdf PDF
Example Submittal Matrix.xlsx XLSX spreadsheet
80KSC020R0024 LC39B ECS Amendment 01 Slip Pages.pdf PDF
Section L Appendix 6 Badging Request Form (Includes TAA).docx DOCX document
80KSC020R0024 Amendment 0002.pdf PDF
80KSC020R0024 LC39B ECS Amendment 02 Slip Page.pdf PDF
80KSC020R0024 Amendment 0002 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0001 Conformed Solicitation.pdf PDF
80KSC020R0024 Amendment 0001.pdf PDF
Section L Appendix 3 Pre-Proposal Inquiry Form.xlsx XLSX spreadsheet
80KSC020R0024 ECS Solicitation.pdf PDF
80KSC020R0024 Attachment J-A Deliverables.pdf PDF
Section L Appendix 1 KSC Form 28-889 Visitor Badge Request.pdf PDF
80KSC020R0024 Attachment J-G Badging ID Process.pdf PDF
Section L Appendix 5 Small Business Subcontracting Goals.docx DOCX document
Section L Appendix 4 PPQs.docx DOCX document
80KSC020R0024 Attachment J-B Project Requirements.pdf PDF
80KSC020R0024 Attachment J-J JOFOC.pdf PDF
80KSC020R0024 Attachment J-C Wage Determination.pdf PDF
Section L Appendix 2 Acceptable Identity Guide.pdf PDF
80KSC020R0024 Attachment J-D Progress Payments.pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

STANDARD FORM 30 BLOCK 14 CONTINUATION PAGE 80KSC020R0024

Amendment 0007

B) Update solicitation Section J table; see attached "Slip Page;" 1 page attached.

C) Proposal due date and time remain unchanged at July 14, 2020 by 2:00 PM EST.

Note: For Reference, a conformed copy of the full solicitation (76 pages) is individually and separately uploaded to beta.SAM.gov and the updated Attachment J-C Wage Determination, Mod 05, dated July 3, 2020 has replaced the Attachment J-C Wage Determination, Mod 04, dated May 15, 2020.

///End of Block 14. DESCRIPTON OF AMENDMENT/MODIFICATION///

"General Decision Number: FL20200001 07/03/2020

Superseded General Decision Number: FL20190001

State: Florida

Construction Types: Building, Heavy and Highway

County: Brevard County in Florida.

**CAPE CANAVERAL AIR STATION, PATRICK AIR FORCE BASE KENNEDY

SPACE CENTER AND MALABAR RADAR SITE IN BREVARD COUNTY BUILDING

CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and partments up to and including 4 stories) HEAVY AND HIGHWAY CONSTRUCTION

PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/03/2020 1 01/31/2020 2 02/21/2020 3 03/27/2020 4 05/15/2020 5 07/03/2020

ASBE0067-001 03/01/2020

Rates Fringes

Asbestos Workers/Insulator (Includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems).........................$ 28.93 16.68

ASBE0067-002 07/01/2017

Rates Fringes

HAZARDOUS MATERIAL HANDLER

(Includes preparation, wetting, stripping, removal, scrapping, vacuuming,bagging, and disposing of all insulation materials from mechanical systems, whether they contain asbestos or not).........$ 16.50 10.90

BOIL0433-001 03/01/2018

Rates Fringes

BOILERMAKER......................$ 30.07 22.71

BRFL0008-001 01/01/2018

Rates Fringes

BRICKLAYER (BRICKLAYERS,

BLOCKLAYERS, PLASTERERS,

TERRAZZO WORKERS, TILE

SETTERS AND CEMENT MASONS)

COMMERCIAL..................$ 22.68 6.31

INDUSTRIAL..................$ 26.08 6.31

INDUSTRIAL work includes: Bulk plants, power houses, chemical plants, missile sites including all work at Cape Canaveral Air Force Station and Kennedy Space Flight Center.

CARP1000-001 07/01/2014

Rates Fringes

MILLWRIGHT.......................$ 29.48 12.40

* CARP1905-002 06/01/2017

Rates Fringes

Carpenters:

*INDUSTRIAL:

CARPENTERS.................$ 25.25 7.55

PILEDRIVERMEN..............$ 21.75 8.65

COMMERCIAL:

CARPENTERS.................$ 23.11 9.85

PILEDRIVERMEN..............$ 21.75 8.65

ELEC0222-001 09/01/2016

Rates Fringes

Line Construction:

CABLE SPLICER...............$ 35.72 5.00+24.5%

GROUNDMAN...................$ 19.39 5.00+24.5%

LINEMAN; HEAVY EQUIPMENT

OPERATOR....................$ 34.02 5.00+24.5%

ELEC0756-001 09/03/2019

Rates Fringes

ELECTRICIAN

Cable Splicer...............$ 29.33 3%+12.74 Wireman.....................$ 29.33 3%+12.74

ELEV0139-001 01/01/2020

Rates Fringes

ELEVATOR MECHANIC................$ 44.12 34.765

FOOTNOTE:

A. Employer contributions 8% of regular hourly rate to vacation pay credit for employee who has worked in business more than 5 years; Employer contributions 6% of regular hourly rate to vacation pay credit for employee who has worked in business less than 5 years.

Paid Holidays: New Year's Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; The Friday after Thanksgiving Day; and Christmas Day.

ENGI0673-001 05/01/2013

Rates Fringes

Power equipment operators:

GROUP 1.....................$ 26.30 10.85

GROUP 2.....................$ 24.14 10.85

GROUP 3.....................$ 23.00 10.85

GROUP 4.....................$ 20.36 10.85

POWER EQUIPMENT OPERATORS

CLASSIFICATIONS GROUP 1: Tower Crane, Locomotive Crane, Crawler Crane, Truck Crane, Hydro Crane, Piledriver (incluidng auger and boring machine)

GROUP 2: Mechanic/Welder and operators of: Gantry Crane, Bridge Crane, Clam Shell, Dragline, Backhoe, Gradeall, Grader, Sideboom Cat, Hulti-Drum Hoist, Highlift (10' or higher), Locomotive Engineer, Tugboat Captain (150 hp or more), Concrete Pump with boom

GROUP 3: Bulddozers, Forklifts, Straddle Buggy, Single Drum Hoist, Winch Truck, Trenching Machine, Concrete Paver, Scraper, Loader, Asphalt Paving Machine, Lubricating Engineer, Fireman, Concrete Breaking Machine, Concrete Mixer

GROUP 4: Tractors, Wellpoint System Operator and Installer, Air Compressor, Pulver Mixer, Motor boat, Power Boat, Power Sweeper, Welding Machine, Oiler, Mechanic's Helper, Pump, Conveyor, Roller, Watertruck, Asphalt distributor, Concrete Pump (trailer type), Utility Operator

IRON0808-001 01/01/2019

Rates Fringes

IRONWORKER.......................$ 27.28 14.70

LABO0517-001 05/01/2017

Rates Fringes

Laborers:

Asbestos Abatement, Hazardous and Toxic Waste Removal Laborers; (On all mechaincal systems: Lead Base Paint Removal;pipes, boilers, ducts, flues, breechings, ect.; that are going to be scrapped, the removal of all insulating materials whether they contain asbestos or not shall be the exclusive work of the laborers;.......$ 19.45 7.85 Carpenter Tender, Cement Mason Tender, Block/ Bricklayer Tender Plasterer Tender............$ 19.20 7.85 Demolition Laborers.........$ 19.20 7.85 General Laborer.............$ 19.20 7.85 Pipelayer Laborer, Laborer engaged in the pouring of concrete, mortar mixers, masonry forklift operator, and operation of power tools.......................$ 19.20 7.85

PAIN0078-001 08/01/2019

Rates Fringes

GLAZIER..........................$ 24.71 13.50

PAIN0078-002 08/01/2019

Rates Fringes

PAINTER..........................$ 24.71 13.50

PLUM0295-001 01/01/2020

Rates Fringes

Plumber/Pipefitter/Steamfitter INDUSTRIAL: Bulk Plants, Power-houses, Chemical Plants, Missile Sites, (Including all Work at Cape Canaveral Air Force Station and Kennedy Space Flight Center but excluding work performed at Patrick Air Force Base and Malabar Radar Site), Oil Refineries, etc., and such other work which is related to and considered a part of the above type projects....................$ 35.20 20.37 Schools, Hospitals, Shopping Centers, and work not listed as Industrial....$ 35.20 20.37

ROOF0136-001 08/01/2019

Rates Fringes

ROOFER...........................$ 22.79 8.57

SFFL0821-002 01/01/2020

Rates Fringes

SPRINKLER FITTER

Commercial..................$ 29.18 19.75 Industrial..................$ 31.53 19.75

Industrial: Jobs covering sugar mills, power plants, trash burning plants, military installations and Cape Kennedy. All other work shall be commercial rate.

* SHEE0015-001 07/01/2020

Rates Fringes

SHEET METAL WORKER...............$ 26.89 8.89

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"

NASA/KSC SOLICITATION 80KSC020R0024

SECTION J – LIST OF ATTACHMENTS

J.1 LIST OF ATTACHMENTS

Attachment Title Date # of

Pages

J-A Project Deliverables No Date 17

J-B KSC Project Specific Requirements No Date 28

J-C Department of Labor Wage Determination Number FL20200001, Modification 0405

May 15July 3, J-D Certification Of Progress Payments Under Fixed-Price Construction Contracts Based On A Percentage Or Stage Of Completion

November 2014 6

J-E Technical Specifications 79K40793 April 13, 2020 797

J-F1 Drawings 79K40792, Sheets 1 through 40 April 13, 2020 40

J-F2 Drawings 79K40792, Sheets 41 through 80 April 13, 2020 40

J-F3 Drawings 79K40792, Sheets 81 through 160 April 13, 2020 80

J-F4 Drawings 79K40792, Sheets 161 through 240 April 13, 2020 80

J-G KSC Badging Issuance and Identity Verification Process, Rev: A-1

Undated 6

J-H Site Specific Safety and Occupational Health Plan TBD TBD

J-I Small Business Subcontracting Plan TBD TBD

J-J Brand Name Determination (JOFOC) No Date 3

J-K Project Execution Plan TBD TBD

topmostSubform[0]:
Page1[0]:
AmendmentNo[0]: 0007
Code[0]: KSC
Code[1]:
AccountingData[0]:
A13[0]:
C13[0]:
D13[0]:
NameandTitleSigner[0]:
NameandTitleOfficer[0]: C. M. Julius Williams, Contracting Officer
Description[0]: The purpose of Amendment 0007 is to:

A) Provide updated Attachment J-C Wage Determination, dated July 3, 2020; 6 pages attached.

Continued on page 2, "STANDARD FORM 30 BLOCK 14 CONTINUATION PAGE."

FacilityCode[0]:
Code[2]: KSC
IssuedBy[0]: NASA/John F. Kennedy Space Center

Office of Procurement Mail Code OP-CS

KENNEDY SPACE CENTER FL, 32899

NameandAddress[0]:
AdministeredBy[0]: NASA/John F. Kennedy Space Center

Office of Procurement Mail Code OP-CS

KENNEDY SPACE CENTER FL, 32899

ContractIDCode[0]:
ReqNumber[0]: 4200729166
AmendmentNo[1]: 80KSC020R0024
ModificationNo[0]:
ProjectNo[0]: 99263
Page[0]: 1
Pages[0]: 2
EffectiveDate[0]: July 8, 2020
Dated9B[0]: June 1, 2020
Dated10B[0]:
CheckBox9[0]: 1
CheckBox10[0]: Off
CheckBox11[0]: 1
CheckBox13A[0]: Off
CheckBox13B[0]: Off
CheckBox13C[0]: Off
CheckBox13D[0]: Off
IsNot[0]: Off
Is[0]: Off
Extended[0]: Off
NotExtended[0]: 1
2020-07-08T18:43:19-0400