Attachment_5.1_-_CLIN-004_Gimbichu_General_Punch_List.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
Completion of Five Health Centers Renovation near Awassa Project in the communities of Arsi Negele, Batu, Durame, Gimbichu, and Waka
Solicitation number
SOL-663-15-000028
Issued by

About this file

Attachment_5.1_-_CLIN-004_Gimbichu_General_Punch_List

View the file

Other files

File Type Posted
CLIN_-_005_RFI_00002-ElecCondClr.pdf PDF
Attachment_7.5_-_CLIN-005_Waka_BOQ.pdf PDF
Attachment_1.4_-_CLIN-004_Gimbichu_Design_Drawings.pdf PDF
Attachment_1.1_-_CLIN-001_Arsi_Negelle_Design_Drawings.pdf PDF
CLIN_-_003_RFI_00021-PitLatSink.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_001_RFI_00002_fixing_PVCCeiling.pdf PDF
CLIN_-_003_RFI_00016-ExtPVLight.pdf PDF
Attachment_3.1-_CLIN-002_Batu_General_Punch_List.xlsx XLSX spreadsheet
Attachment_3.2_-_CLIN-002_Batu_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_4.1_-_CLIN-003_Durame_General_Punch_List.xlsx XLSX spreadsheet
Attachment_7.4_-_CLIN-004_Gimbichu_BOQ.pdf PDF
Attachment_1.4.a_-_CLIN-004_Gimbichu_Soak_Away_Pit_Drawing_Details.pdf PDF
CLIN_-_003_RFI_00001-Various.pdf PDF
CLIN_-_004_RFI_00021_-FlexibleConduits.pdf PDF
CLIN_-_005_RFI_00023-ExtPVLight.pdf PDF
Attachment_6.2_-_CLIN-005_Waka_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_7.3_-_CLIN-003_Durame_BOQ.pdf PDF
CLIN_-_003_RFI_00090-AntirustElectrode.pdf PDF
Attachment_1.5_-_CLIN-005_Waka_Design_Drawings.pdf PDF
CLIN_-_003_RFI-00011-WaterSupplyLines.pdf PDF
CLIN_-_005_RFI_00003_Various2.pdf PDF
CLIN_-_002_RFI_00023-ExtPVLight.pdf PDF
SOL-663-15-000028.pdf PDF
Attachment_2.2_-_CLIN-001_Arsi_Negele_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_5.2_-CLIN-004_Gimbichu__Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_1.3_-_CLIN-003_Durame_Design_Drawings.pdf PDF
CLIN_-_005_RFI_00014_SiteElectrical.pdf PDF
CLIN_-_004_RFI-00009_Various.pdf PDF
Attachment_7.2_-_CLIN-002_Batu_BOQ.pdf PDF
CLIN_-_003_RFI_00009-SanitaryManholes.pdf PDF
Attachment_4.2_-_CLIN-003_Durame_Electrical_Punch_List.xlsx XLSX spreadsheet
CLIN_-_002_RFI__00020_ElectricManhole-HoldingTank.pdf PDF
CLIN_-_002_RFI_00007_WtrSuppLinesDelivBlock.pdf PDF
CLIN_-_004_RFI_00011_-_EpoxyFlrFin.pdf PDF
Attachment_7.1_-_CLIN-001_Arsi_Negele_BOQ.pdf PDF
CLIN_-_001_RFI_00007-GalvStlWaterSvcPiping.pdf PDF
Attachment_1.2_-_CLIN-002_Batu_Design_Drawings.pdf PDF
CLIN_-_001_RFI-00011-PumpPowerSupply.pdf PDF
CLIN_-_004_RFI_00008-ElecCondClr.pdf PDF
Attachment_1.0_-_Final_Spec_Health_Centers_Renovation.pdf PDF
CLIN_-_003_RFI_00006-IDStair.pdf PDF
CLIN_-_004_RFI_00026-PitLatrineFFL.pdf PDF
CLIN_-_004_RFI_00005_Various.pdf PDF
CLIN_-_002_RFI_00022_-_FlexibleConduits.pdf PDF
CLIN_-_004_RFI_00022-ExtPVLight.pdf PDF
Attachment_6.1_-_CLIN-005_Waka_General_Punch_List.xlsx XLSX spreadsheet
CLIN_-_001_RFI_00008-WallCerTile.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_003_RFI_00019-PitLatHPL.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gimbichu

Engineer's QA Punch List - Site Renovation Work
Location:GIMBICHU HEALTH CENTERDate of Visit:20-Apr-15
Must be completed immediately for substantial completion
Already completed
whiteMust be completed within warranty period
Detailed Punch List Items:Clean-Up
Location/RoomPunch List CommentsRatingComments
1) Outdoor Items
1.1All stair railings to Delivery Block, ART Block, TB Block, Registration Block and OPD Block must be completed to design drawing requirements. Stair rails are not fixed, ramp rail CHS tube ends are open
1.2Install correct site locator signage across all Blocks.
1.3New sanitary holding tank must be sealed inside with flexcoat as per design specifications.
1.4Construct new Type 1 circular soak away pit and connect to new sanitary holding tank as per design drawings CX-575 and CX-576.
2) Delivery Block
1Indoor Item
1.1New locking hardware on all metal doors is loose. Window hardware on main entrance door is missing.
2Labor Toilet
2.1Install two grab bars
2.2Finish door hardware. Door hardware loose and not completed.
2.3Tissue holder is loose
2.4Existing metal door sticks and does not lock.
4Sluice Room
4.1Sluice sink tap must properly operate according to manufacturer guidelines with cold/warm/hot water transitions along the full tap turning range. Tap performance across the range of water temperatures will be inspected for correct results during the next QA site visit. Adjust tap performance according to manufacturer recommendations (see product submittal book). 15440-2.6, 3.2; SN-003; 15440 Plumbing Fixtures, product Submittal Book;
5Delivery Room
5.13 cm gap between wooden doors and frames. No glazing above doors. Must adjust doors in frames.
5.2Delivery door‐ missing door hinges (one on each door missing).Missing hinges taken off and used to secure other doors in Delivery Block. Correct.
6Waiting Area
6.1Main metal door top window hardware not fixed, glass putty is

not sufficient, door painting correction

7Postnatal Toilet
7.1Fixtures and fittings installed. Three grab bars missing. Door hardware loose.
8Labor Room
8.1Missing wooden door hinges - (one on each door missing).Missing hinges taken off and used to secure other doors in Delivery Block. Correct.
9Ramp
9.1Complete downpipes to minimize drainage onto access ramps.
3) Registration Block
1TB Room
1.1Window missing hardware.
2Dispensary
2.1Window missing hardware.
3HC Head and Finance
3.1Finish installing data and phone wiring as per design requirements. Currently only the outlet boxes are present. Connection is not completed (refer EL punch list).
4Ramp
4.1Grading at base of stairs must be completed to drain. Rail CHS end is not closed.
4.2Stair railings not started.
4.5TB clinic handrails not completed.
4) ART Block
1Stairs
1.1Stairs completed but hand rails are not fixed.
5) OPD Block
1Laboratory
1.1Correct poor epoxy floor finish at doorway, complete door installation, metal door does not close (needs adjustment, one hinge is broken), top

glazing insufficient glass putty, internal wooden door is not fixed."

2Ramp
2.1Stair railings not started.
3ANC
3.1Install door glazing and door threshold.
6) Pit Latrine
1Pit Latrine
1.1Fascia boards not primed and painted, poor end

and butt joints. End plates welded for fascia board fixing are finished with very poor and insufficient site welding, Install missed roof J‐bolts.

1.2No HWBs. Only stub-up of water lines.
1.3Gable flyscreens not completed.
1.4Sanitary vent pipe anchors are not fixed, vent caps

and fly screens are not fixed.

1.5Doors and locks are missing screws on door lock, door painting not completed.
1.6Inside all pits must be smooth plastered.
1.7Gutters are not fixed, the EGA sheets are too short to drain

water to the gutters.

1.8Handicap grab bars not installed.
1.9Floor epoxy correction at door threshold.
1.10Pit manhole covers are not sealed. Storm water from the roof will

collect and enter the manholes.

1.11Tighten / adjust loose HPL partition panels.
7) Electrical Items:
7.1See Tetra Tech electrical QA report for listing of electrical issues identified during this QA site visit
8) Additional Comments:
8.1Conduct performance pressure/ leak test of entire rennovated water piping network for the site as per design specifications section 02600 and 15991.Rennovated water network has failed previous pressure testing events.
Attachments:
Comments and observations are provided in this report for the use of the Client. Nothing in this report should be taken by the Contractor as a directive to modify the plans, specifications or completed work unless appropriate documentation is provided by the Client.
C. Farkos
---End of Report---