Waka
| Engineer's QA Punch List - Electrical Work Items | |||||
| Location: | WAKA HEALTH CENTER | Date of Visit: | 21-Apr-15 | ||
| Must be completed immediately for substantial completion | |||||
| Already completed | |||||
| white | Must be completed within warranty period | ||||
| NOTE: | Uninstalled parts may need connections in ceilings and must be finished before start of waranty period due to safety reason. Any new installation and new material supplies need 1 year waranty after handing over. | ||||
| Detailed Punch List Items: | Clean-Up | ||||
| Location/Room | Punch List Comments | Rating | Comments | ||
| I) Delivery | |||||
| 1 | Labor | 1.1 | 4.1 Emergency light is not installed | Install UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes. | |
| 2 | Toilet (Post Natal) | 2.1 | Light switch installed is non water proof type | ||
| 2.2 | Water heater socket is viko brand and surface mount type. Viko is not approved for this project. Replace with approved WH socket brand. | ||||
| 3 | Post Natal | 3.1 | 4.1 Emergency light is not installed | Install UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes. | |
| 4 | Delivery | 4.1 | 4.1 Emergency light is not installed | Install UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes. | |
| 5 | Sluice | 5.1 | Light fixture power supply is not finished | ||
| 6 | Scrub | 6.1 | Water heater socket is viko brand and surface mount type. Viko is not approved for this project. Replace with approved WH socket brand. | ||
| 7 | Min Opn | 7.1 | 4.1 Emergency light is not installed | Install UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes. | |
| 8 | Toilet(Female ward) | 8.1 | Light switch is not water proof | ||
| 8.2 | Water heater socket is viko brand and surface mount type. Viko is not approved for this project. Replace with approved WH socket brand. | ||||
| III) Laboratory Block: | |||||
| 1 | Emergency | 1.1 | Type 4.1 Emergency light fixture installation is not finished | Install UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes. | |
| IV) ART Block: | |||||
| 1 | Ceiling | 1.1 | Wires and cable run with no conduit and touched roof sheet above LPP-D, exposed to high temperature during dry hot season | ||
| V) Pit Latrine Block: | |||||
| 1 | Pit Latrine | 1.1 | Outdoor light switch is not water proof | ||
| 1.2 | Grounding of roof structure should be done | ||||
| VI) General Site Work | |||||
| 1 | Site Work | 1.1 | Main 3 Phase EEPCO power supply is not provided, |
HC is to connect new 3-phase power line from power pole to the main electrical MH. Coordinate with EEPCO to install new power meter. Significant problem at the main electrical MH since there is no inlet conduit installed for the main power line. Install. Currently temporary wiring configuration from EPCO source to the power meter is blue - ground (must label), yellow green -neutral, black/brown/grey - phase, ground not completed. This configuration is incorrectly connected to HC 1-phase circuits.
This temporary configuration must be corrected to yellow green-ground, blue- neutral, black/brown/grey - phase. 3-phase/1-phase connection will be corrected to MDB.
| 1.2 | Earth cable is not connected to Earth rod | |
| 1.3 | Anchor the above grade conduit of the Registration Block power supply line according to design specifications. | |
| 1.4 | Solar powered compound light fixtures are not installed | |
| 1.5 | Complete testing should be done to all blocks' electrical works as per design specifications. | |
| Attachments: |
| Comments and observations are provided in this report for the use of the Client. Nothing in this report should be taken by the Contractor as a directive to modify the plans, specifications or completed work unless appropriate documentation is provided by the Client. | |
| Bizuayehu Tessema | |
| ---End of Report--- |