Attachment_3.2_-_CLIN-002_Batu_Electrical_Punch_List.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
Completion of Five Health Centers Renovation near Awassa Project in the communities of Arsi Negele, Batu, Durame, Gimbichu, and Waka
Solicitation number
SOL-663-15-000028
Issued by

About this file

Attachment_3.2_-_CLIN-002_Batu_Electrical_Punch_List

View the file

Other files

File Type Posted
CLIN_-_005_RFI_00002-ElecCondClr.pdf PDF
Attachment_7.5_-_CLIN-005_Waka_BOQ.pdf PDF
Attachment_1.4_-_CLIN-004_Gimbichu_Design_Drawings.pdf PDF
Attachment_1.1_-_CLIN-001_Arsi_Negelle_Design_Drawings.pdf PDF
CLIN_-_003_RFI_00021-PitLatSink.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_001_RFI_00002_fixing_PVCCeiling.pdf PDF
CLIN_-_003_RFI_00016-ExtPVLight.pdf PDF
Attachment_3.1-_CLIN-002_Batu_General_Punch_List.xlsx XLSX spreadsheet
Attachment_4.1_-_CLIN-003_Durame_General_Punch_List.xlsx XLSX spreadsheet
Attachment_7.4_-_CLIN-004_Gimbichu_BOQ.pdf PDF
Attachment_1.4.a_-_CLIN-004_Gimbichu_Soak_Away_Pit_Drawing_Details.pdf PDF
CLIN_-_003_RFI_00001-Various.pdf PDF
CLIN_-_004_RFI_00021_-FlexibleConduits.pdf PDF
CLIN_-_005_RFI_00023-ExtPVLight.pdf PDF
Attachment_6.2_-_CLIN-005_Waka_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_7.3_-_CLIN-003_Durame_BOQ.pdf PDF
CLIN_-_003_RFI_00090-AntirustElectrode.pdf PDF
Attachment_1.5_-_CLIN-005_Waka_Design_Drawings.pdf PDF
CLIN_-_003_RFI-00011-WaterSupplyLines.pdf PDF
CLIN_-_005_RFI_00003_Various2.pdf PDF
CLIN_-_002_RFI_00023-ExtPVLight.pdf PDF
SOL-663-15-000028.pdf PDF
Attachment_2.2_-_CLIN-001_Arsi_Negele_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_5.2_-CLIN-004_Gimbichu__Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_1.3_-_CLIN-003_Durame_Design_Drawings.pdf PDF
CLIN_-_005_RFI_00014_SiteElectrical.pdf PDF
CLIN_-_004_RFI-00009_Various.pdf PDF
Attachment_7.2_-_CLIN-002_Batu_BOQ.pdf PDF
CLIN_-_003_RFI_00009-SanitaryManholes.pdf PDF
Attachment_4.2_-_CLIN-003_Durame_Electrical_Punch_List.xlsx XLSX spreadsheet
CLIN_-_002_RFI__00020_ElectricManhole-HoldingTank.pdf PDF
CLIN_-_002_RFI_00007_WtrSuppLinesDelivBlock.pdf PDF
CLIN_-_004_RFI_00011_-_EpoxyFlrFin.pdf PDF
Attachment_7.1_-_CLIN-001_Arsi_Negele_BOQ.pdf PDF
CLIN_-_001_RFI_00007-GalvStlWaterSvcPiping.pdf PDF
Attachment_1.2_-_CLIN-002_Batu_Design_Drawings.pdf PDF
CLIN_-_001_RFI-00011-PumpPowerSupply.pdf PDF
CLIN_-_004_RFI_00008-ElecCondClr.pdf PDF
Attachment_1.0_-_Final_Spec_Health_Centers_Renovation.pdf PDF
CLIN_-_003_RFI_00006-IDStair.pdf PDF
CLIN_-_004_RFI_00026-PitLatrineFFL.pdf PDF
CLIN_-_004_RFI_00005_Various.pdf PDF
CLIN_-_002_RFI_00022_-_FlexibleConduits.pdf PDF
CLIN_-_004_RFI_00022-ExtPVLight.pdf PDF
Attachment_6.1_-_CLIN-005_Waka_General_Punch_List.xlsx XLSX spreadsheet
CLIN_-_001_RFI_00008-WallCerTile.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_003_RFI_00019-PitLatHPL.pdf PDF
CLIN_-_003_RFI_00008_GalvStlWaterSvcPiping.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Batu

Engineer's QA Punch List - Electrical Work Items
Location:BATU HEALTH CENTERDate of Visit:17-Apr-15
Must be completed immediately for substantial completion
Already completed
whiteMust be completed within warranty period
NOTE:Uninstalled parts may need connections in ceilings and must be finished before start of warranty period due to safety reason. Any new installation and new material supplies need 1 year warranty after handing over.
Detailed Punch List Items:Clean-Up
Location/RoomPunch List CommentsRatingComments
I)Delivery
1Toilet 11.1Light switch is not water proof
2Toilet 22.1Light switch is not water proof
3Sluice3.1Socket outlet under sink needs cover
4Corridor4.1Wires in light fixtures are against code, blue is used as phase , neutral and ground
4.2Insulation tape used for wire extension in light fixtures, change it by cap insulation
5Min Opn, Deliv, Post Natal, Labor5.1Fluorescent tubes of installed Type 4.1 light fixtures are frequently burning, there voltage fluctuation in the townInstall UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes.
6Ceiling6.1Light fixture supports:-fixtures are screwed to the plastic ceiling tile.

should be:- 1.supported to the truss by galvanized wire or 2.screwed to wooden trusses

II)OPD Block
1Dispensary1.1Sockets detached from wall
2OPD 12.11 light fixture is not closed properly
3ER3.1Type 4.1 light fixture is not installedInstall UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes.
4Toilet4.1Water heater socket is not installed
4.2Switch is not installed
4.3Mirror socket installation is under progress
5Verandah, ER side5.1Light switch is not tight
5.2Light switch is not weather proof
6Verandah, Inpatient side6.1Light switch is not weather proof, need chucking
7Verandah, Office side7.1Junction box of power supply cable to LPP-C is not covered
7.2Tele box is not completely covered
7.3Light switches are not weather proof
8Store8.1Type 5 light fixture is installed in place of Type 1
9Inpatient9.1Change position of switch at gate
9.23 light fixtures are not working
10Laboratory10.1Water heater power plug is tensioned, should make 15cm loop
11Offices11.13 socket outlets are not installed, no conduit and wire are installed
11.2Only 1 tele outlet is working. Install additional connections as per design drawings.
12Ceiling12.1Ø20mm elbow used for Ø16mm conduit, the joint is not good
12.2Conduits are not supported
12.3Conduits are not finished to light fixtures and junction boxes
12.4Junction boxes are not covered
12.5Wires run with no conduit to light points
12.6Elbows and joints are not used to conduits connection
III) General Site Work
1Site Work1.1Main Circuit breaker in MSB-B is 16 Amp, change it by 32Amp per schedule
1.2EEPCO's circuit breakers above main electric meter are old types and can't hold the 16 sq mm cable, need to be changed by new 3X32A single phase circuit breakers
1.3The electrical drawings inside doors of MSBs and LPP-C are not complete. All drawings should be labeled in the distribution boards
1.4Loose connections should be tight in all distribution boards
1.5Pump circuit breaker in MSB-B is failed and it is not labeled. It needs to be replaced by new one
1.6Solar compound flood lights are not installed. Install.
1.7J-box of feeder cable to LPP-C is not covered beneath the board
1.8Power supply is provided through the new cable from EEPCO before insulation test is done and it is found short circuited. Now OPD block does not have power supply. Very few sockets are energized by power source from neighboring compound. New cables should be provided to both blocks and megger tested to confirm compliance with design specifications.
1.9The feeder cables from EEPCO source to OPD MSB-B and Delivery MSB-A run in one PVC pipe. Separate pipes should be used to prevent short circuit and megger tested to confirm compliance with design specifications.
1.10Insulation test is not done to the light fixture lines in both blocks, only the socket outlet lines are meggered and found good. (~200MOhm)Conduct megger test of all light fixture lines in OPD and Delivery Blocks as per design specifications. Correct any deficiencies.
Attachments:
Comments and observations are provided in this report for the use of the Client. Nothing in this report should be taken by the Contractor as a directive to modify the plans, specifications or completed work unless appropriate documentation is provided by the Client.
Bizuayehu Tessema
---End of Report---