Batu
| Engineer's QA Punch List - Electrical Work Items | |||||
| Location: | BATU HEALTH CENTER | Date of Visit: | 17-Apr-15 | ||
| Must be completed immediately for substantial completion | |||||
| Already completed | |||||
| white | Must be completed within warranty period | ||||
| NOTE: | Uninstalled parts may need connections in ceilings and must be finished before start of warranty period due to safety reason. Any new installation and new material supplies need 1 year warranty after handing over. | ||||
| Detailed Punch List Items: | Clean-Up | ||||
| Location/Room | Punch List Comments | Rating | Comments | ||
| I)Delivery | |||||
| 1 | Toilet 1 | 1.1 | Light switch is not water proof | ||
| 2 | Toilet 2 | 2.1 | Light switch is not water proof | ||
| 3 | Sluice | 3.1 | Socket outlet under sink needs cover | ||
| 4 | Corridor | 4.1 | Wires in light fixtures are against code, blue is used as phase , neutral and ground | ||
| 4.2 | Insulation tape used for wire extension in light fixtures, change it by cap insulation | ||||
| 5 | Min Opn, Deliv, Post Natal, Labor | 5.1 | Fluorescent tubes of installed Type 4.1 light fixtures are frequently burning, there voltage fluctuation in the town | Install UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes. | |
| 6 | Ceiling | 6.1 | Light fixture supports:-fixtures are screwed to the plastic ceiling tile. |
should be:- 1.supported to the truss by galvanized wire or 2.screwed to wooden trusses
| II)OPD Block | ||||
| 1 | Dispensary | 1.1 | Sockets detached from wall | |
| 2 | OPD 1 | 2.1 | 1 light fixture is not closed properly | |
| 3 | ER | 3.1 | Type 4.1 light fixture is not installed | Install UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes. |
| 4 | Toilet | 4.1 | Water heater socket is not installed | |
| 4.2 | Switch is not installed | |||
| 4.3 | Mirror socket installation is under progress | |||
| 5 | Verandah, ER side | 5.1 | Light switch is not tight | |
| 5.2 | Light switch is not weather proof | |||
| 6 | Verandah, Inpatient side | 6.1 | Light switch is not weather proof, need chucking | |
| 7 | Verandah, Office side | 7.1 | Junction box of power supply cable to LPP-C is not covered | |
| 7.2 | Tele box is not completely covered | |||
| 7.3 | Light switches are not weather proof | |||
| 8 | Store | 8.1 | Type 5 light fixture is installed in place of Type 1 | |
| 9 | Inpatient | 9.1 | Change position of switch at gate | |
| 9.2 | 3 light fixtures are not working | |||
| 10 | Laboratory | 10.1 | Water heater power plug is tensioned, should make 15cm loop | |
| 11 | Offices | 11.1 | 3 socket outlets are not installed, no conduit and wire are installed | |
| 11.2 | Only 1 tele outlet is working. Install additional connections as per design drawings. | |||
| 12 | Ceiling | 12.1 | Ø20mm elbow used for Ø16mm conduit, the joint is not good | |
| 12.2 | Conduits are not supported | |||
| 12.3 | Conduits are not finished to light fixtures and junction boxes | |||
| 12.4 | Junction boxes are not covered | |||
| 12.5 | Wires run with no conduit to light points | |||
| 12.6 | Elbows and joints are not used to conduits connection | |||
| III) General Site Work | ||||
| 1 | Site Work | 1.1 | Main Circuit breaker in MSB-B is 16 Amp, change it by 32Amp per schedule | |
| 1.2 | EEPCO's circuit breakers above main electric meter are old types and can't hold the 16 sq mm cable, need to be changed by new 3X32A single phase circuit breakers | |||
| 1.3 | The electrical drawings inside doors of MSBs and LPP-C are not complete. All drawings should be labeled in the distribution boards | |||
| 1.4 | Loose connections should be tight in all distribution boards | |||
| 1.5 | Pump circuit breaker in MSB-B is failed and it is not labeled. It needs to be replaced by new one | |||
| 1.6 | Solar compound flood lights are not installed. Install. | |||
| 1.7 | J-box of feeder cable to LPP-C is not covered beneath the board | |||
| 1.8 | Power supply is provided through the new cable from EEPCO before insulation test is done and it is found short circuited. Now OPD block does not have power supply. Very few sockets are energized by power source from neighboring compound. New cables should be provided to both blocks and megger tested to confirm compliance with design specifications. | |||
| 1.9 | The feeder cables from EEPCO source to OPD MSB-B and Delivery MSB-A run in one PVC pipe. Separate pipes should be used to prevent short circuit and megger tested to confirm compliance with design specifications. | |||
| 1.10 | Insulation test is not done to the light fixture lines in both blocks, only the socket outlet lines are meggered and found good. (~200MOhm) | Conduct megger test of all light fixture lines in OPD and Delivery Blocks as per design specifications. Correct any deficiencies. | ||
| Attachments: |
| Comments and observations are provided in this report for the use of the Client. Nothing in this report should be taken by the Contractor as a directive to modify the plans, specifications or completed work unless appropriate documentation is provided by the Client. | |
| Bizuayehu Tessema | |
| ---End of Report--- |