Attachment_4.1_-_CLIN-003_Durame_General_Punch_List.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
Completion of Five Health Centers Renovation near Awassa Project in the communities of Arsi Negele, Batu, Durame, Gimbichu, and Waka
Solicitation number
SOL-663-15-000028
Issued by

About this file

Attachment_4.1_-_CLIN-003_Durame_General_Punch_List

View the file

Other files

File Type Posted
CLIN_-_005_RFI_00002-ElecCondClr.pdf PDF
Attachment_7.5_-_CLIN-005_Waka_BOQ.pdf PDF
Attachment_1.4_-_CLIN-004_Gimbichu_Design_Drawings.pdf PDF
Attachment_1.1_-_CLIN-001_Arsi_Negelle_Design_Drawings.pdf PDF
CLIN_-_003_RFI_00021-PitLatSink.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_001_RFI_00002_fixing_PVCCeiling.pdf PDF
CLIN_-_003_RFI_00016-ExtPVLight.pdf PDF
Attachment_3.1-_CLIN-002_Batu_General_Punch_List.xlsx XLSX spreadsheet
Attachment_3.2_-_CLIN-002_Batu_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_7.4_-_CLIN-004_Gimbichu_BOQ.pdf PDF
Attachment_1.4.a_-_CLIN-004_Gimbichu_Soak_Away_Pit_Drawing_Details.pdf PDF
CLIN_-_003_RFI_00001-Various.pdf PDF
CLIN_-_004_RFI_00021_-FlexibleConduits.pdf PDF
CLIN_-_005_RFI_00023-ExtPVLight.pdf PDF
Attachment_6.2_-_CLIN-005_Waka_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_7.3_-_CLIN-003_Durame_BOQ.pdf PDF
CLIN_-_003_RFI_00090-AntirustElectrode.pdf PDF
Attachment_1.5_-_CLIN-005_Waka_Design_Drawings.pdf PDF
CLIN_-_003_RFI-00011-WaterSupplyLines.pdf PDF
CLIN_-_005_RFI_00003_Various2.pdf PDF
CLIN_-_002_RFI_00023-ExtPVLight.pdf PDF
SOL-663-15-000028.pdf PDF
Attachment_2.2_-_CLIN-001_Arsi_Negele_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_5.2_-CLIN-004_Gimbichu__Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_1.3_-_CLIN-003_Durame_Design_Drawings.pdf PDF
CLIN_-_005_RFI_00014_SiteElectrical.pdf PDF
CLIN_-_004_RFI-00009_Various.pdf PDF
Attachment_7.2_-_CLIN-002_Batu_BOQ.pdf PDF
CLIN_-_003_RFI_00009-SanitaryManholes.pdf PDF
Attachment_4.2_-_CLIN-003_Durame_Electrical_Punch_List.xlsx XLSX spreadsheet
CLIN_-_002_RFI__00020_ElectricManhole-HoldingTank.pdf PDF
CLIN_-_002_RFI_00007_WtrSuppLinesDelivBlock.pdf PDF
CLIN_-_004_RFI_00011_-_EpoxyFlrFin.pdf PDF
Attachment_7.1_-_CLIN-001_Arsi_Negele_BOQ.pdf PDF
CLIN_-_001_RFI_00007-GalvStlWaterSvcPiping.pdf PDF
Attachment_1.2_-_CLIN-002_Batu_Design_Drawings.pdf PDF
CLIN_-_001_RFI-00011-PumpPowerSupply.pdf PDF
CLIN_-_004_RFI_00008-ElecCondClr.pdf PDF
Attachment_1.0_-_Final_Spec_Health_Centers_Renovation.pdf PDF
CLIN_-_003_RFI_00006-IDStair.pdf PDF
CLIN_-_004_RFI_00026-PitLatrineFFL.pdf PDF
CLIN_-_004_RFI_00005_Various.pdf PDF
CLIN_-_002_RFI_00022_-_FlexibleConduits.pdf PDF
CLIN_-_004_RFI_00022-ExtPVLight.pdf PDF
Attachment_6.1_-_CLIN-005_Waka_General_Punch_List.xlsx XLSX spreadsheet
CLIN_-_001_RFI_00008-WallCerTile.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_003_RFI_00019-PitLatHPL.pdf PDF
CLIN_-_003_RFI_00008_GalvStlWaterSvcPiping.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Durame

Engineer's QA Punch List - Site Renovation Work
Location:DURAME HEALTH CENTERDate of Visit:16-Apr-15
Must be completed immediately for substantial completion
Already completed
whiteMust be completed within warranty period
Detailed Punch List Items:Clean-Up
Location/RoomPunch List CommentsRatingComments
1) Outdoor Items
1.1Install missing downpipes and anchors at all Block locations as per design requirements.
1.2All new water lines penetrating through HCB walls shall include a gate valve, galvanized piping and wall sleeve to provide minimum 8 mm clearance in diameter around the pipe. Current water line penetrations do not include any sleeves. 15440-2.6, 3.5; SN-001
1.3Some new, 2 in GS main water lines across the site are above ground and incorrectly anchored. Several sections crossing walkways have been buried but the walkways have not been repaired. Correct as per SN-001, C-003, RFI 00017, October 8, 2014; October 21, 2014. And correctly anchor all above ground GS lines as per design specifications.
1.4Access ramps to Delivery Block, ID Block, and OPD Block must be completed with correct reinforcing to curb surface as per C-008. Curbs are currently partially casted with no reinforcing installed near surface level.
1.5Install all sanitary vents as per SN-002 and SN-005. Several vents are incomplete.
1.7Install all required fire extinguishers.
1.8Install site signage at all locations as per design drawings.Signs have been manufactured and are on site. None have been properly installed as per design requirements.
1.9All sanitary MHs in the new network shall have sealed MH covers. As the survey results for MH invert elevations below indicates:

• Invert elevations for inlet lines for MH-7 and MH-12 are above the invert elevations for the discharge lines. These must be corrected. USAID request for the schedule of invert elevations used by the contractor to install all lines has not been fulfilled.

• MH-14 on the design drawing does not exist in the field constructed network. How will greywater be handled from the new handwash basins installed in the OPD Pharmacy and OPD Dressing Room?

• Several MHs have roof downspouts located directly above or immediately adjacent to the MHs. Relocate these downspouts. MH-6, MH-19 and MH-10 do not have covers. Install new covers.

Most sanitary MHs currently have 1 cm gaps between the covers and the wall tops. Significant stormwater infiltration will occur. Construct watertight seals at all MHs with 6 cm edge as per SN-001.
1.10Drinking water line and control valve adjacent to MH-19 and OPD Block is buried in an exposed trench with no valve box or cover. Install as per design drawings.
1.11Haul away from site multiple piles of excavated material and construction debris.
2) Indoor Items
2.1Final gypsum wall plaster work across all Blocks containes cracks. Repair.
3) Delivery Block
1Outdoor items
1.1Access ramp to Delivery Block entrance must include handrails, handrail anchors, and concrete pavers as per design drawings.
2Indoor Items
2.1Delivery, Scrub and Sluice Rooms are poorly painted with many places of exposed green under layer. Repaint to a consistent, professional finish as per design specifications. Repair several cracks in gypsum plaster.
2.2Numerous LTZ window frames across the Block include 1 cm - 2 cm gaps between the metal frame, terrazzo sill and HCB wall edges. Numerous LTZ frames also have no locks or locks that do not properly anchor. Glazing putty adjustments are required in many LTZ frames across the Block.
3Postnatal Toilet
3.1Incorrect location for electrical socket and light positions. Switch. Complete wall and tile finishes including plastering, painting, grouting of all tiles.
3.2Correctly anchor cistern water line to waste pan and wall. Correct cistern leaks.
3.3Electric system does not work in room.
3.4Door doesn't close and lock.
3.5Toilet fixtures: grab bars must be installed.
3.6Install shucko plug on new water heater.
4Scrub Room
4.1Properly anchor sink floor peddles to floor.
4.2Install shucko plug on new water heater.
5Sluice Room
5.1Wall skirting is unfinished.
6Delivery Room
6.1Install missing hardware on LTZ window frames.
4) Administration Block
1Indoor Items1.1Doors on Mother to Mother, ANC, Store and Family Planning do not close/lock properly.
1.2None of the equipment for the new data and phone lines is installed in Head Office and Finance Rooms as per EL-003. These rooms are fully occupied.
2ANC Toilet2.1Replace and repair broken ceramic tiles. Clean and paint walls. Install new grab bars as per design drawings.
5) OPD Block
1Outdoor items1.1MH-6 outside Sample Room must be repaired including a correct vent connection, new 160 mm outlet line, relocation of gutter downpipe away from the surface cover of MH-6.
1.2Install smooth transition finish between MH-4 cover and OPD/Delivery access ramp surface.
1.3Handicapped access ramp at ground termination is directly adjacent to MH-7 cover and anchor. Installed ramp railing will restrict patient ramp access to a very restricted opening that crosses MH-7 cover. Adjust Waiting Area access steps as per AR-007 to create space for patient access to ramp.
2OPD Toilet2.1The room has rough tile and windows completed. Most of the work identified in the design drawings must be completed.
3OPD Sample Room3.1The room has rough tile and windows completed. Most of the work identified in the design drawings, including sample window, must be completed.
4Laboratory4.1Walls must be repainted to correct design finish. Finish install of hot water tank electrical. Door does not work.
6) Pit Latrine
1Pit Latrine
1.1Concrete columns, beams and slabs are constructed with HCB walls. All plate-plate connections between truss, purlin and ring beam connections are very poorly aligned and do not comply with ST-080 details. Adjustable plate connections from water tower structure anchor plates have been incorrectly used for all pit latrine anchor plates. Replace. All j-bolts should be galvanized. Currently not galvanized.
1.2Install GS vents and flyscreens as per AR-035, AR-036 and AR-038.
1.3Install all internal pit latrine elements as per AR-035, AR-036 and AR-037.
1.4Install rubber washers on all EGA panel J-bolt connections as per design requirements to prevent leaking.
1.5Install epoxy flooring and ceramic thresholds as per design specifications and AR-036.
1.6Install PVC gutters and downspouts as per AR-035, AR-036 and AR-038.
1.7Electrical wiring and color coding is incorrect. Correct.
1.8Complete construction of pit latrine soakaway pit and also correct sub-base finishing of main waste disposal pit as per AR-036 and SN-010.
7) Infectious Disease Clinic
1Infectious Disease Clinic
1.1The Waiting Area has been painted. Terrazzo tile sills are installed. Access railings must be installed as per RFI 00006, April 10, 2014.
1.2Doors must be finished, door hardware must be installed.
1.3All plumbing and associated new SSW must be adjusted as per design requirements.
8) Water Tower
1Water Tower
1.1Only the original, incorrect water tower pad is currently constructed. Construct all aspects of the tower and water systems.
9) Electrical Items:
1Electrical Items:
1.1See Tetra Tech electrical QA report for listing of electrical issues identified during this QA site visit
10) Additional Comments:
10.1Conduct performance leak test of rennovated water piping network for the site as per design specifications section 02600 and 15991.
Attachments:
Comments and observations are provided in this report for the use of the Client. Nothing in this report should be taken by the Contractor as a directive to modify the plans, specifications or completed work unless appropriate documentation is provided by the Client.
C. Farkos
---End of Report---