Attachment_4.2_-_CLIN-003_Durame_Electrical_Punch_List.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
Completion of Five Health Centers Renovation near Awassa Project in the communities of Arsi Negele, Batu, Durame, Gimbichu, and Waka
Solicitation number
SOL-663-15-000028
Issued by

About this file

Attachment_4.2_-_CLIN-003_Durame_Electrical_Punch_List

View the file

Other files

File Type Posted
CLIN_-_005_RFI_00002-ElecCondClr.pdf PDF
Attachment_7.5_-_CLIN-005_Waka_BOQ.pdf PDF
Attachment_1.4_-_CLIN-004_Gimbichu_Design_Drawings.pdf PDF
Attachment_1.1_-_CLIN-001_Arsi_Negelle_Design_Drawings.pdf PDF
CLIN_-_003_RFI_00021-PitLatSink.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_001_RFI_00002_fixing_PVCCeiling.pdf PDF
CLIN_-_003_RFI_00016-ExtPVLight.pdf PDF
Attachment_3.1-_CLIN-002_Batu_General_Punch_List.xlsx XLSX spreadsheet
Attachment_3.2_-_CLIN-002_Batu_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_4.1_-_CLIN-003_Durame_General_Punch_List.xlsx XLSX spreadsheet
Attachment_7.4_-_CLIN-004_Gimbichu_BOQ.pdf PDF
Attachment_1.4.a_-_CLIN-004_Gimbichu_Soak_Away_Pit_Drawing_Details.pdf PDF
CLIN_-_003_RFI_00001-Various.pdf PDF
CLIN_-_004_RFI_00021_-FlexibleConduits.pdf PDF
CLIN_-_005_RFI_00023-ExtPVLight.pdf PDF
Attachment_6.2_-_CLIN-005_Waka_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_7.3_-_CLIN-003_Durame_BOQ.pdf PDF
CLIN_-_003_RFI_00090-AntirustElectrode.pdf PDF
Attachment_1.5_-_CLIN-005_Waka_Design_Drawings.pdf PDF
CLIN_-_003_RFI-00011-WaterSupplyLines.pdf PDF
CLIN_-_005_RFI_00003_Various2.pdf PDF
CLIN_-_002_RFI_00023-ExtPVLight.pdf PDF
SOL-663-15-000028.pdf PDF
Attachment_2.2_-_CLIN-001_Arsi_Negele_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_5.2_-CLIN-004_Gimbichu__Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_1.3_-_CLIN-003_Durame_Design_Drawings.pdf PDF
CLIN_-_005_RFI_00014_SiteElectrical.pdf PDF
CLIN_-_004_RFI-00009_Various.pdf PDF
Attachment_7.2_-_CLIN-002_Batu_BOQ.pdf PDF
CLIN_-_003_RFI_00009-SanitaryManholes.pdf PDF
CLIN_-_002_RFI__00020_ElectricManhole-HoldingTank.pdf PDF
CLIN_-_002_RFI_00007_WtrSuppLinesDelivBlock.pdf PDF
CLIN_-_004_RFI_00011_-_EpoxyFlrFin.pdf PDF
Attachment_7.1_-_CLIN-001_Arsi_Negele_BOQ.pdf PDF
CLIN_-_001_RFI_00007-GalvStlWaterSvcPiping.pdf PDF
Attachment_1.2_-_CLIN-002_Batu_Design_Drawings.pdf PDF
CLIN_-_001_RFI-00011-PumpPowerSupply.pdf PDF
CLIN_-_004_RFI_00008-ElecCondClr.pdf PDF
Attachment_1.0_-_Final_Spec_Health_Centers_Renovation.pdf PDF
CLIN_-_003_RFI_00006-IDStair.pdf PDF
CLIN_-_004_RFI_00026-PitLatrineFFL.pdf PDF
CLIN_-_004_RFI_00005_Various.pdf PDF
CLIN_-_002_RFI_00022_-_FlexibleConduits.pdf PDF
CLIN_-_004_RFI_00022-ExtPVLight.pdf PDF
Attachment_6.1_-_CLIN-005_Waka_General_Punch_List.xlsx XLSX spreadsheet
CLIN_-_001_RFI_00008-WallCerTile.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_003_RFI_00019-PitLatHPL.pdf PDF
CLIN_-_003_RFI_00008_GalvStlWaterSvcPiping.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Durame

Engineer's QA Punch List - Electrical Work Items
Location:DURAME HEALTH CENTERDate of Visit:16-Apr-15
Must be completed immediately for substantial completion
Already completed
whiteMust be completed within warranty period
NOTE:Uninstalled parts may need connections in ceilings and must be finished before start of warranty period due to safety reason. Any new installation and new material supplies need 1 year warranty after handing over.
Detailed Punch List Items:Clean-Up
Location/RoomPunch List CommentsRatingComments
I)Delivery
1Toilet1.1Water heater socket does not have switch
1.2Water heater does not have power plug
1.3Light switch should be water proof
2Post Natal2.1Type 4.1 Emergency light is not workingInstall UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes.
2.2Socket detached from wall
3Delivery3.1Type 4.1 Emergency light is not working, and move it to the middle of the light fixturesInstall UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes.
4Scrub4.1Water Heater socket does not have switch, Water heater needs plug
5Sluice5.1Water Heater socket does not have switch, water heater needs plug
6Sterilization6.11 socket outlet is not installed
7Ceiling7.1There is no access panel to the ceiling entrance
8Corridor8.1LPP-D:

The load distribution is not per schedule, the electrical installation is not done per drawings, drawings are not labeled to the LPP, spare circuit breakers are not installed, wires color is against code - black is used as neutral and blue is used as phase, labeling to feeder cable is not done, there are many loose connections specially to the bus bar-to-wire connections

9Outdoor, Front and Back side9.1Conduits are unfinished to Type 2 light fixtures
10Labor10.1Type 4.1 Emergency light is not working, and move it to the middle of the light fixturesInstall UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes.
II)Admin Block
1Mother to Mother store1.1Light fixture is not installed
2Mother to Mother2.1Color of wires at switch is against code, yellow is used as return line
3EPI3.1Sockets detached from wall
4Toilet4.1Water heater socket needs switch, heater needs plug
4.2Toilet/shower switch is not water proof
5Finance Office5.1Tele outlet is not installed
6Head Office6.1Tele outlet is not installed
7Verandah7.1Conduiting is unfinished to lighting points
7.2Main Tele Terminal Box is not installed
7.3Light fixture detached from ceiling
7.4LPP-B:

The load distribution is not per schedule, the electrical installation is not done per drawings, drawings are not labeled, spare circuit breakers are not installed, wires color is against code - black is used as neutral and blue is used as phase, labeling to feeder cable is not done, there are many loose connections specially to the bus bar-to-wire connections, One circuit breaker is burnt

8Ceiling8.1Conduit supports are required, conduits lying on ceiling
8.2Junction boxes do not have any support
8.3Insulation tape is used for wire connection insulation, use only cap connector
8.4Existing installation should be removed after renovation is completed
8.5Conduit runs are not organized into parallel network, parallel to the building structure
8.6Connection is done with no junction box
8.7Glands of junction boxes are not used, the junction boxes are left open
III)OPD Block
1Laboratory1.1Light fixtures are supported by screw to the plastic ceiling tile, make screw to wooden trusses or support by wires to trusses
1.2Light Switch is damaged
1.3Water heater socket and switch are not installed
2Emergency2.1Sockets detached from wall
2.2Light fixtures are installed very closer to each other
2.3Move Type 4 fixture to Pharmacy room and install type 4.1 fixture of pharmacy hereInstall UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes.
3Pharmacy3.1Move type 4.1 fixture to Emergency room and install one of type 4s of emergency here
4Toilet4.1Mirror socket is not installed
5Verandah5.1Outdoor sockets are not installed
5.2MSB:

Drawings are not labeled, spare circuit breakers are not installed, wires color is against code - black is used as neutral and blue is used as phase, labeling to feeder cable is not done, there are many loose connections specially to the bus bar-to-wire connections

5.3 LPP-A:

The load distribution is not per schedule, the electrical installation is not done per drawings, drawings are not labeled, spare circuit breakers are not installed, wires color is against code - black is used as neutral and blue is used as phase, labeling to feeder cable is not done, there are many loose connections specially to the bus bar-to-wire connections, wires are short to re-arrange per schedule(need wire extension and cap insulation connector)

5.4Extend the feeder cables UPVC pipe at back side of OPD block to the block's ceiling
5.5Conduits are unfinished to light fixtures
5.61 light fixture is not working
6Ceiling6.1No support for conduits, conduits lying on ceiling
6.2Conduits are not organized into parallel network
6.3Junction boxes do not have any support
6.4Glands of junction boxes are not used, the junction boxes are left open
IV)Infectious Disease Block
1Infectious Disease1.2Internal board cover is broken
1.3Feeder cable to LPP-E from MSB failed megger test
1.4LPP-E

Drawings are not labeled, Main circuit breaker is not labeled, wire color is against code, there are loose connections in bus bar-to-wire connection, electrical installation is not done per drawing

V)Drug Store Block
1Verandah1.1LPP-C:

The load distribution is not per schedule, the electrical installation is not done per drawings, drawings are not labeled, spare circuit breakers are not installed, wires color is against code - black is used as neutral and blue is used as phase, labeling to feeder cable is not done, there are many loose connections specially to the bus bar-to-wire connections

1.2Conduits are unfinished to light fixtures in verandah
1.3Verandah switch is not weather proof
VI)Pit Latrine Block
1Pit Latrine1.1Light fixtures are not installed
1.2Light switches are not installed
VII) General Site Work
1Site Work1.1Rain water enters Electrical manhole, manhole height shall be raised
1.2Rain water enters to conduit - elbow joint near earth manhole
1.3There is Junction box in earth manhole, the cap connectors inside are small in size
1.4Insulation of main feeder from J-box in earth manhole to MSB is damaged
1.5Main feeder conduit from earth manhole to MSB should be raised to 20 cm above FFL
1.6Drive down earth electrode until 10 cm remains
1.7Warning tape is not used to site UG cables
1.8The feeder cable from MSB to LPP-E failed megger test
1.9Spare circuit breakers are not installed in all distribution boards
1.10Electrical works are not per drawings in all blocks and load distribution are not per schedules in all distribution boards
1.11Stand alone solar compound lights are not installed
1.12Labeling are not done in LPPs
1.13EEPCO power is not upgraded to the HC
1.14Testing should be done to all blocks' electrical works after amendment is completed
Attachments:
Comments and observations are provided in this report for the use of the Client. Nothing in this report should be taken by the Contractor as a directive to modify the plans, specifications or completed work unless appropriate documentation is provided by the Client.
Bizuayehu Tessema
---End of Report---