Arsi Negele
| Engineer's QA Punch List - Electrical Work Items | |||||
| Location: | ARSI NEGELE HEALTH CENTER | Date of Visit: | 15-Apr-15 | ||
| Must be completed immediately for substantial completion | |||||
| Already completed | |||||
| white | Must be completed within warranty period | ||||
| NOTE: | Uninstalled parts may need connections in ceilings and must be finished before start of warranty period due to safety reason. Any new installation and new material supplies need 1 year warranty after handing over. | ||||
| Detailed Punch List Items: | Clean-Up | ||||
| Location/Room | Punch List Comments | Rating | Comments | ||
| I)OPD Block | |||||
| 1 | Emergency | 1.1 | Fluorescent tubes of installed Type 4.1 light fixtures are frequently burning, there voltage fluctuation in the town. The voltage reading is ~180V instead of 220, and this will even reduce at night as many loads are expected to run. | Install UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes. | |
| II)Delivery Block | |||||
| 1 | Min Opn, Deliv, Post Natal, Labor | 1.1 | Fluorescent tubes of installed Type 4.1 light fixtures are frequently burning, there voltage fluctuation in the town. The voltage reading is ~180V instead of 220, and this will even reduce at night as many loads are expected to run. | Install UPS for these 4.1 lights + (3x1.5) mm sq electric power cable from UPS to light points, multi-core copper conductor, PVC/PVC, colorcoded, in PVC conduit diameter 32 mm with conduit supports. Include new 100A battery. Install new, 11 watt CFL light bulbs instead of the fluorescent tubes. | |
| III) Administration Block | |||||
| 1 | Administration Offices | 1.1 | Telephone outlet works only in Head office, the Tele outlet in HR office does not work. Correct. | ||
| IV) General Site Work | |||||
| 1 | Site Work | 1.1 | One of the three phases of the EEPCO power supply has failed, the HC is to inform to EEPCO | ||
| 1.2 | Stand alone solar powered compound lights are not installed. Install. | ||||
| 1.3 | Label for neutral cable of main feeder to MSB and bus bars remaining | ||||
| Attachments: |
| Comments and observations are provided in this report for the use of the Client. Nothing in this report should be taken by the Contractor as a directive to modify the plans, specifications or completed work unless appropriate documentation is provided by the Client. | |
| Bizuayehu Tessema | |
| ---End of Report--- |