About this file

CLIN_-_003_RFI_00019-PitLatHPL

View the file

Other files

File Type Posted
CLIN_-_005_RFI_00002-ElecCondClr.pdf PDF
Attachment_7.5_-_CLIN-005_Waka_BOQ.pdf PDF
Attachment_1.4_-_CLIN-004_Gimbichu_Design_Drawings.pdf PDF
Attachment_1.1_-_CLIN-001_Arsi_Negelle_Design_Drawings.pdf PDF
CLIN_-_003_RFI_00021-PitLatSink.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_001_RFI_00002_fixing_PVCCeiling.pdf PDF
CLIN_-_003_RFI_00016-ExtPVLight.pdf PDF
Attachment_3.1-_CLIN-002_Batu_General_Punch_List.xlsx XLSX spreadsheet
Attachment_3.2_-_CLIN-002_Batu_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_4.1_-_CLIN-003_Durame_General_Punch_List.xlsx XLSX spreadsheet
Attachment_7.4_-_CLIN-004_Gimbichu_BOQ.pdf PDF
Attachment_1.4.a_-_CLIN-004_Gimbichu_Soak_Away_Pit_Drawing_Details.pdf PDF
CLIN_-_003_RFI_00001-Various.pdf PDF
CLIN_-_004_RFI_00021_-FlexibleConduits.pdf PDF
CLIN_-_005_RFI_00023-ExtPVLight.pdf PDF
Attachment_6.2_-_CLIN-005_Waka_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_7.3_-_CLIN-003_Durame_BOQ.pdf PDF
CLIN_-_003_RFI_00090-AntirustElectrode.pdf PDF
Attachment_1.5_-_CLIN-005_Waka_Design_Drawings.pdf PDF
CLIN_-_003_RFI-00011-WaterSupplyLines.pdf PDF
CLIN_-_005_RFI_00003_Various2.pdf PDF
CLIN_-_002_RFI_00023-ExtPVLight.pdf PDF
SOL-663-15-000028.pdf PDF
Attachment_2.2_-_CLIN-001_Arsi_Negele_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_5.2_-CLIN-004_Gimbichu__Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_1.3_-_CLIN-003_Durame_Design_Drawings.pdf PDF
CLIN_-_005_RFI_00014_SiteElectrical.pdf PDF
CLIN_-_004_RFI-00009_Various.pdf PDF
Attachment_7.2_-_CLIN-002_Batu_BOQ.pdf PDF
CLIN_-_003_RFI_00009-SanitaryManholes.pdf PDF
Attachment_4.2_-_CLIN-003_Durame_Electrical_Punch_List.xlsx XLSX spreadsheet
CLIN_-_002_RFI__00020_ElectricManhole-HoldingTank.pdf PDF
CLIN_-_002_RFI_00007_WtrSuppLinesDelivBlock.pdf PDF
CLIN_-_004_RFI_00011_-_EpoxyFlrFin.pdf PDF
Attachment_7.1_-_CLIN-001_Arsi_Negele_BOQ.pdf PDF
CLIN_-_001_RFI_00007-GalvStlWaterSvcPiping.pdf PDF
Attachment_1.2_-_CLIN-002_Batu_Design_Drawings.pdf PDF
CLIN_-_001_RFI-00011-PumpPowerSupply.pdf PDF
CLIN_-_004_RFI_00008-ElecCondClr.pdf PDF
Attachment_1.0_-_Final_Spec_Health_Centers_Renovation.pdf PDF
CLIN_-_003_RFI_00006-IDStair.pdf PDF
CLIN_-_004_RFI_00026-PitLatrineFFL.pdf PDF
CLIN_-_004_RFI_00005_Various.pdf PDF
CLIN_-_002_RFI_00022_-_FlexibleConduits.pdf PDF
CLIN_-_004_RFI_00022-ExtPVLight.pdf PDF
Attachment_6.1_-_CLIN-005_Waka_General_Punch_List.xlsx XLSX spreadsheet
CLIN_-_001_RFI_00008-WallCerTile.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_003_RFI_00008_GalvStlWaterSvcPiping.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USAID/EHIP

New Health Center Construction Task Order 8, Combined RFI Log

Durame Site 202 Batu Site 251 Gimbichu Site 208 Arsi Negele Site 277 Waka Site 213 Meki Site 290

RFI No. Date Rec'd Item No. Question TT Response Response Date Follow-up

Waka 00027 Durame 00019

Gimbichu 00027

27-Oct-14 1 AR-035 calls for the use of HPL partition walls at Pit Latrine. The length of the partition walls shown is to be 2m. However, the only available size in the local market is 1.83m in length. We request your approval to construct a narrow HCB wall at the front inner side of the block with mortar and reinforcements with methodology approved for TO#4, TO#6 and TO#7 sites.

Proposal is acceptable.

28-Oct-14

\\GLSS402FS1\Project\01298\127-01298-11002\Construction\RFIs\TO#8 - Combined RFI's\RFI Log TO#8 COMBINED.xlsx