About this file

CLIN_-_003_RFI_00021-PitLatSink

View the file

Other files

File Type Posted
CLIN_-_005_RFI_00002-ElecCondClr.pdf PDF
Attachment_7.5_-_CLIN-005_Waka_BOQ.pdf PDF
Attachment_1.4_-_CLIN-004_Gimbichu_Design_Drawings.pdf PDF
Attachment_1.1_-_CLIN-001_Arsi_Negelle_Design_Drawings.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_001_RFI_00002_fixing_PVCCeiling.pdf PDF
CLIN_-_003_RFI_00016-ExtPVLight.pdf PDF
Attachment_3.1-_CLIN-002_Batu_General_Punch_List.xlsx XLSX spreadsheet
Attachment_3.2_-_CLIN-002_Batu_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_4.1_-_CLIN-003_Durame_General_Punch_List.xlsx XLSX spreadsheet
Attachment_7.4_-_CLIN-004_Gimbichu_BOQ.pdf PDF
Attachment_1.4.a_-_CLIN-004_Gimbichu_Soak_Away_Pit_Drawing_Details.pdf PDF
CLIN_-_003_RFI_00001-Various.pdf PDF
CLIN_-_004_RFI_00021_-FlexibleConduits.pdf PDF
CLIN_-_005_RFI_00023-ExtPVLight.pdf PDF
Attachment_6.2_-_CLIN-005_Waka_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_7.3_-_CLIN-003_Durame_BOQ.pdf PDF
CLIN_-_003_RFI_00090-AntirustElectrode.pdf PDF
Attachment_1.5_-_CLIN-005_Waka_Design_Drawings.pdf PDF
CLIN_-_003_RFI-00011-WaterSupplyLines.pdf PDF
CLIN_-_005_RFI_00003_Various2.pdf PDF
CLIN_-_002_RFI_00023-ExtPVLight.pdf PDF
SOL-663-15-000028.pdf PDF
Attachment_2.2_-_CLIN-001_Arsi_Negele_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_5.2_-CLIN-004_Gimbichu__Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_1.3_-_CLIN-003_Durame_Design_Drawings.pdf PDF
CLIN_-_005_RFI_00014_SiteElectrical.pdf PDF
CLIN_-_004_RFI-00009_Various.pdf PDF
Attachment_7.2_-_CLIN-002_Batu_BOQ.pdf PDF
CLIN_-_003_RFI_00009-SanitaryManholes.pdf PDF
Attachment_4.2_-_CLIN-003_Durame_Electrical_Punch_List.xlsx XLSX spreadsheet
CLIN_-_002_RFI__00020_ElectricManhole-HoldingTank.pdf PDF
CLIN_-_002_RFI_00007_WtrSuppLinesDelivBlock.pdf PDF
CLIN_-_004_RFI_00011_-_EpoxyFlrFin.pdf PDF
Attachment_7.1_-_CLIN-001_Arsi_Negele_BOQ.pdf PDF
CLIN_-_001_RFI_00007-GalvStlWaterSvcPiping.pdf PDF
Attachment_1.2_-_CLIN-002_Batu_Design_Drawings.pdf PDF
CLIN_-_001_RFI-00011-PumpPowerSupply.pdf PDF
CLIN_-_004_RFI_00008-ElecCondClr.pdf PDF
Attachment_1.0_-_Final_Spec_Health_Centers_Renovation.pdf PDF
CLIN_-_003_RFI_00006-IDStair.pdf PDF
CLIN_-_004_RFI_00026-PitLatrineFFL.pdf PDF
CLIN_-_004_RFI_00005_Various.pdf PDF
CLIN_-_002_RFI_00022_-_FlexibleConduits.pdf PDF
CLIN_-_004_RFI_00022-ExtPVLight.pdf PDF
Attachment_6.1_-_CLIN-005_Waka_General_Punch_List.xlsx XLSX spreadsheet
CLIN_-_001_RFI_00008-WallCerTile.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_003_RFI_00019-PitLatHPL.pdf PDF
CLIN_-_003_RFI_00008_GalvStlWaterSvcPiping.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USAID/EHIP

New Health Center Construction Task Order 8, Combined RFI Log

Durame Site 202 Batu Site 251 Gimbichu Site 208 Arsi Negele Site 277 Waka Site 213 Meki Site 290

RFI No. Date Rec'd Item No. Question TT Response Response Date Follow-up

Durame 00021 Waka 00028

Gimbichu 00028

3-Nov-14 1 The Pit Latrine Details calls for the installation of two fiber-glass sinks with stainless steel frame and door at Pit latrine. We request your approval to use typical vitreous china HWBs with full pedestals

Fiberglass sink and steel frame were designed for enhanced durability.

Construct per design.

5-Nov-14

\\GLSS402FS1\Project\01298\127-01298-11002\Construction\RFIs\TO#8 - Combined RFI's\RFI Log TO#8 COMBINED.xlsx

File details come from the government source that posted it. Updated .