CLIN_-_003_RFI-00011-WaterSupplyLines.pdf

PDF 268 KB Posted

Attached to
Completion of Five Health Centers Renovation near Awassa Project in the communities of Arsi Negele, Batu, Durame, Gimbichu, and Waka
Solicitation number
SOL-663-15-000028
Issued by

About this file

CLIN_-_003_RFI-00011-WaterSupplyLines

View the file

Other files

File Type Posted
CLIN_-_005_RFI_00002-ElecCondClr.pdf PDF
Attachment_7.5_-_CLIN-005_Waka_BOQ.pdf PDF
Attachment_1.4_-_CLIN-004_Gimbichu_Design_Drawings.pdf PDF
Attachment_1.1_-_CLIN-001_Arsi_Negelle_Design_Drawings.pdf PDF
CLIN_-_003_RFI_00021-PitLatSink.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_001_RFI_00002_fixing_PVCCeiling.pdf PDF
CLIN_-_003_RFI_00016-ExtPVLight.pdf PDF
Attachment_3.1-_CLIN-002_Batu_General_Punch_List.xlsx XLSX spreadsheet
Attachment_3.2_-_CLIN-002_Batu_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_4.1_-_CLIN-003_Durame_General_Punch_List.xlsx XLSX spreadsheet
Attachment_7.4_-_CLIN-004_Gimbichu_BOQ.pdf PDF
Attachment_1.4.a_-_CLIN-004_Gimbichu_Soak_Away_Pit_Drawing_Details.pdf PDF
CLIN_-_003_RFI_00001-Various.pdf PDF
CLIN_-_004_RFI_00021_-FlexibleConduits.pdf PDF
CLIN_-_005_RFI_00023-ExtPVLight.pdf PDF
Attachment_6.2_-_CLIN-005_Waka_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_7.3_-_CLIN-003_Durame_BOQ.pdf PDF
CLIN_-_003_RFI_00090-AntirustElectrode.pdf PDF
Attachment_1.5_-_CLIN-005_Waka_Design_Drawings.pdf PDF
CLIN_-_005_RFI_00003_Various2.pdf PDF
CLIN_-_002_RFI_00023-ExtPVLight.pdf PDF
SOL-663-15-000028.pdf PDF
Attachment_2.2_-_CLIN-001_Arsi_Negele_Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_5.2_-CLIN-004_Gimbichu__Electrical_Punch_List.xlsx XLSX spreadsheet
Attachment_1.3_-_CLIN-003_Durame_Design_Drawings.pdf PDF
CLIN_-_005_RFI_00014_SiteElectrical.pdf PDF
CLIN_-_004_RFI-00009_Various.pdf PDF
Attachment_7.2_-_CLIN-002_Batu_BOQ.pdf PDF
CLIN_-_003_RFI_00009-SanitaryManholes.pdf PDF
Attachment_4.2_-_CLIN-003_Durame_Electrical_Punch_List.xlsx XLSX spreadsheet
CLIN_-_002_RFI__00020_ElectricManhole-HoldingTank.pdf PDF
CLIN_-_002_RFI_00007_WtrSuppLinesDelivBlock.pdf PDF
CLIN_-_004_RFI_00011_-_EpoxyFlrFin.pdf PDF
Attachment_7.1_-_CLIN-001_Arsi_Negele_BOQ.pdf PDF
CLIN_-_001_RFI_00007-GalvStlWaterSvcPiping.pdf PDF
Attachment_1.2_-_CLIN-002_Batu_Design_Drawings.pdf PDF
CLIN_-_001_RFI-00011-PumpPowerSupply.pdf PDF
CLIN_-_004_RFI_00008-ElecCondClr.pdf PDF
Attachment_1.0_-_Final_Spec_Health_Centers_Renovation.pdf PDF
CLIN_-_003_RFI_00006-IDStair.pdf PDF
CLIN_-_004_RFI_00026-PitLatrineFFL.pdf PDF
CLIN_-_004_RFI_00005_Various.pdf PDF
CLIN_-_002_RFI_00022_-_FlexibleConduits.pdf PDF
CLIN_-_004_RFI_00022-ExtPVLight.pdf PDF
Attachment_6.1_-_CLIN-005_Waka_General_Punch_List.xlsx XLSX spreadsheet
CLIN_-_001_RFI_00008-WallCerTile.pdf PDF
CLIN_-_004_RFI_00029-WaterSupplyLines.pdf PDF
CLIN_-_003_RFI_00019-PitLatHPL.pdf PDF
CLIN_-_003_RFI_00008_GalvStlWaterSvcPiping.pdf PDF
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USAID/EHIP

New Health Center Construction Task Order 8, Combined RFI Log

Durame Site 202 Batu Site 251 Gimbichu Site 208 Arsi Negele Site 277 Waka Site 213 Meki Site 290

RFI No. Date Rec'd Item No. Question TT Response Response Date Follow-up

Durame 00011

16-May-14 1 On the Site Utilities Plan (SN - OO 1), water supply lines and sewer lines pass behind Delivery, Admin and OPD blocks. However, the space behind these blocks (between the blocks and existing retaining wall) is narrow and impossible to maintain the minimum 3 m horizontal distance between the water lines and sewer lines as stated in SN - 000 (please refer to attached pictures). Please note that the existing manholes are to remain and to be repaired as required as stated in Note 5 (SN - OO 1).

Please clarify.

PROPOSED SOLUTION:

Proposed solution is to use surface mounted GS pipes where it is impossible to maintain the 3 m horizontal spacing.

Solution is acceptable. Water supply lines can be galvanized steel, surface mounted attached with galvanized steel brackets every 1M.

19-May-14

P:\01298\127-01298-11002\Construction\RFIs\TO#8 - Combined RFI's\RFI Log TO#8 COMBINED

Inkntluional Rdilo'f & D(;vdnpmr!lf

TK International Bulding NO.2 5th floor Addis Ababa, TRANSMITTAL

No. 00033

PROJECT: TO-14-00003(TO#8)Durame Renovation DATE: Friday, May 16,2014

TO: USAID/ET REF: Request for Information US Embassy Addis Ababa, ATTN: Roger Sydney

WE ARE SENDING: SUBMITTED FOR: ACTION TAKEN:

D Shop Drawings D Approval D Approved as Submitted

D Letter D YourUse D Approved as Noted

D Prints D As Requested D Retumed After Loan

D Change Order li'J Review and Comment D Resubmit

D Plans liit Submit

D Samnles SENTVIA: D Retumed

D Specifications IIi'J Attached D Retumed for Corrections

~. Other: ReQuest for lnforrnation D Senarate Cover Via: Mail D Due Date:

ITEM PACKAGE REV. COPIES DATE DESCRIPTION STATUS

RFI 5/1612014 Water Supply Lines OPN

Remarks:

CC: IRD Document Control

P.O. Box 6005 www.ird.org Tel.: +251·016·630023

International Relicf & Development

TK International Building No.2

5th floor

Addis Ababa

TITLE: Water Supply Lines

PROJECT: TO-14-00003(TO#8) Durame Renovation

TO: USAID/ET

Addis Ababa

ATTN: Roger Sydney

QUESTION:

REQUEST FOR INFORMATION

No. 00011

DATE: Friday, May 16,2014

Contraet No.: TO#8

US Embassy

On the Site Utilities Plan (SN - OO 1), water supply lines and sewer lines pass behind Delivery, Admin and OPD blocks. However, the space behind these blocks (between the blocks and existing retaining wall) is narrow and impossible to maintain the minimum 3 m horizontal distance between the water lines and sewer lines as stated in SN - 000 (please refer to attached pictures). Please note that the existing manholes are to remain and to be repaired as required as stated in Note 5 (SN - OO 1). Please clarify.

Note: IRD has not assessed the full impaet of this issue in terms of additional eost and extension of time. IRD reserve s the right to submit a c1aim as provided in Contraet Seetion I.

PROPOSED SOLUTION:

Proposed solution is to use surface mounted GS pipes where it is impossible to maintain the 3 m horizontal spacmg.

Requested By: International Reliefand Development

Signed: ~~ a;nesEdil1ger

P.O. Box 6005 www.ird.org Tel.: +251-0116-630023

TO#8