HII Bidder's Question 41 Response

View the file

Other files

File Type Posted
amendment_20.doc DOC document
amendment_0019_USS_COLUMBUS_revised.pdf PDF
CJA_41069.20_SSN_765_and_762_Redacted.pdf PDF
SEA07B_Approved_Clarifying_6_4_15_Attachment_2.pdf PDF
amendment_18.pdf PDF
Amendment_18_Attachment_3.pdf PDF
Amendment_17.pdf PDF
Attachment_1_to_amendment_0016.doc DOC document
Amendment_16.doc DOC document
amendment_0015.doc DOC document
amendment_0014.pdf PDF
Final_amendment_13.pdf PDF
Final_amendment_12.doc DOC document
HII-NNS_762_BQ_12_answer.pdf PDF
EBC_BQ_125_revised_clarification_5FEB2015.pdf PDF
HII-NNS_RFP_Bidders'_Question__5_020515.docx DOCX document
EBC_INDUSTRY_DAY_BIDDERS_QUESTIONS.pdf PDF
EBC_pending_answers_4_11_78_79_116_134_135.pdf PDF
Final_amendment.doc DOC document
HII_BQ_149_01_02_03_14_18_24_28_44_55_answers.pdf PDF
HII-NNS_RFP_Bidders'_final_RFP_questions.docx DOCX document
N00024-15-R-4300-0010.doc DOC document
Final_HII-NNS_Final_Questions.pdf PDF
EB_questions_27 _51 _52 _54 _57 _59 _67 _83 _82 _121 _126 _130 _131 _132 _133 _136 _137 _138 _139 _140 _and_141.pdf PDF
HII_questions_47 _48 _49 _51 _56 _6 _8 _13 _14 _25 _39 _50.pdf PDF
amendment_09.doc DOC document
N00024-15-R-4300-0008.doc DOC document
HII-NNS_RFP_bidders_questions_legal_response_sent_to_Marina.docx DOCX document
amendment_0007_approved.doc DOC document
20150123_HII-NNS_answers.pdf PDF
EBBQ_96-110_114_115_answers.pdf PDF
EBBQ_15-16-22-23-28-31-32-40-81.pdf PDF
amendment_0006_posting.pdf PDF
NNSBQ_answers_146-6-8-20-33-34-35-40-43-50-22JAN2015.pdf PDF
2015Jan14-EBC_BQ_answers_1_14_26_41_47_49_53_56_58_64_post_01222015.pdf PDF
amendment_05_post_01222015.pdf PDF
HII-NNS_RFP_Bidders'_Question__18_011515_Response_011615.pdf PDF
EBC_BQ_113__Final_011615.pdf PDF
Final_amendment_0004_FBO.pdf PDF
HII-NNS_RFP_Bidders'_Question__16_011515_Response_011615.pdf PDF
20150115-USS_MONTPELIER_IDD_Q7 8_revision.pdf PDF
EB__74_-__Corp_cost_est__765_IDD.xlsx XLSX spreadsheet
EBC_BQ_125_shift_to_CLIN_5-11_response_011615.docx DOCX document
2015Jan12-EBC_BQ_answers.pdf PDF
EB__74_Corp_Cost_est_762_EOH.xlsx XLSX spreadsheet
EBC_BQ_74.docx DOCX document
2015JAN14_HII-NNS_Answers.pdf PDF
HII-NNS_RFP_Bidders'_Question__34_011515_response_011615.pdf PDF
Bidders_question_112_FinalRev_011615.pdf PDF
Pre-Proposal_Conf_final_slides_01132015.pptx PPTX presentation
Show 40 more

Latest 50 of 70 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR CLARIFICATION

(NO QUESTIONS WILL BE ACCEPTED AFTER) 16 January 2015

NAME OF OFFEROR: NEWPORT NEWS SHIPBUILDING DATE: 15-Jan-15

NAVSEA SOLICITATION NUMBER: N00024-15-R-4300 QUESTION# 41 (RFP)

SHIPS: USS MONTPELIER SSN 765/USS COLUMBUS SSN 762

SPECIFICATION NO: RFP PARAGRAPH NO.:

TITLE: PAGE NO.:

QUESTION:

The ALLOTMENT OF FUNDS, which is incorporated in full text in Section H, refers to FAR 52.232-20, Limitation of Cost, and FAR 52.232-22, Limitation of Funds. Given these references, does the Navy intend adding these clauses?

DO NOT WRITE BELOW THIS LINE--- (SPACE BELOW FOR GOV'T USE ONLY)

ANSWER:

FAR Clauses 52.232-20 and 52.232-22 will be added to Section I of Solicitation N00024-15-R-4300.

These clauses are applicable to cost reimbursement contract line item numbers (CLINs) only.