Attachment_1_to_amendment_0016.doc
DOC document 109 KB Posted
- Attached to
- USS COLUMBUS (SSN 762) Engineering Overhaul (EOH) Federal contract opportunity
- Solicitation number
- N0002415R4300
About this file
Attachment 1 to amendment 16
View the file
Other files for this federal contract opportunity
Show all 50
USS COLUMBUS (SSN 762) Engineering Overhaul (EOH) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USS MONTPELIER (SSN 765) IDD
Solicitation No. N00024-15-R-4300, Amendment 0016
Government Clarifying information
General:
1. All growth repair work and associated efforts (i.e. required tooling, radiological controls, etc.) associated with performance of SWLINs assigned to CLINs 0004, 0005 and 0006 shall be performed by the contractor, and charged against the authorized level of effort for the associated CLIN.
2.
Proposal will include anticipated material costs required to support the work of all CLINs of the RFP. Undefined growth, new work and AIT support service requirements identified during execution of CPFF/LOE CLINS may result in unforeseen material costs or lead times that could have an adverse impact on cost and/or schedule. Material costs identified during execution that exceed $250,000, or result in lead times that adversely impact execution schedules, will be adjudicated via separate contract action as appropriate.
3.
Proposal will be based on implementation of existing NAVSEA S9002-AK-CCM-010/6010 and will not include implementation of new fire prevention and response requirements in NAVSEA Technical Publication S0570-AC-CCM-010/8010, Industrial Ship Safety Manual for Fire Prevention and Response (8010).
4.
CCRP components specified in the AWP may be requisitioned from the Navy Stock System. Proposal assumes the condition of all CCRP and AERP assets obtained will be suitable for use and will be available on time to support the integrated schedule.
5.
Proposal will include an early start period of approximately three weeks where the ship is nested pier side at NAVSTA Norfolk or SUBASE New London to allow the Shipyard to perform work in accordance with the IDD integrated schedule. The ship will offload weapons, combustibles, and the maximum allowable amount of normal fuel oil prior to docking. The Shipyard will assume LMA duties upon docking in the Shipyard and will retain responsibility for LMA duties through availability completion.
6.
Proposal will not include any consideration for services that may be required during the nesting period. Proposal assumes the Government will provide these services.
7.
Proposal will not include any contingency for anticipated added expenses associated with government responsible third party performance of growth and/or new work.
8.
Proposal will not include any cost to provide funding to other Government activities by the contractor.
9.
Subcontracted effort may be used to perform portions of the work of the CPFF/LOE CLINs. The subcontracted effort utilized to perform work under these CLINs will count towards fulfillment of the total level of effort specified.
10.
In the event that an AIT schedule or actual work accomplished by an AIT extends beyond the shipyards proposed dates, any impacts will be adjudicated via separate contract action as appropriate.
11.
Proposal will be based on Ship’s Force maintaining control/ownership of all operating systems onboard the vessel for the duration of the availability.
12.
Any and all material removed from or added to the ship without the shipyard present shall be weighed by Ships Force and reported to the shipyard.
13.
Proposal (price/schedule) assumes that reports will be answered by government to support the availability schedule.
14.
NAVSEA 0989-062-4000 Naval Nuclear Quality Control Manual for Shipyard, Revision 8 will be implemented based on the following:
a) The extent of the scope of ANSI Z540-1 accreditation is limited to: All ship’s installed calibrated equipment (this includes but is not limited to pressure gauges, transducers, temperature indicators, switches and flowmeters), all General Purpose Test Equipment (GPTE) which belongs to the crew and all Calibration Standards used for the calibration of the aforementioned shipboard and GPTE equipment.
b) The conditions approved in NAVSEA Letter 08T/95-01776 dated 28 November 1995 will remain in effect.
15.
Proposal will not include removal of high chlorides prior to application of paint. Any as found conditions requiring removal of chlorides related to CLIN 0003 will be adjudicated via separate contract action as appropriate.
16.
Proposal will be based on valves selected as test boundaries will hold sufficiently to complete test.
17.
Repair and/or resetting of studs on hull valves related to CLIN 0003 will be adjudicated via separate contract action as appropriate. Proposal assumes studs have (K) markings; verifying unmarked studs will be adjudicated via separate contract action as appropriate.
18.
The contractor will evaluate all work items for repairs outside or beyond the scope of the maintenance standard, and will notify the Government of any potential delay to schedule. Required repairs outside or beyond the scope of the maintenance standard that will result in delay to schedule will be adjudicated via separate contract action as appropriate.
19.
Proposal assumes GFE, identified in this attachment, will be provided on a mutually agreed delivery date.
Nuclear SWLINs:
1. SWLIN Number: 014B01 – CLIN 0001 / 0003
System: Reactor Plant - General Pre-Avail Test
Title: Assist Ship’s Force
a) PATS - Pre availability testing will be performed at NOB, Norfolk or SUBASE New London.
b) POTS - Post availability testing, if performed at the contractor’s yard, will be charged to SWLIN 861L06.
2. SWLIN Number: 040B02 – CLIN 0003
System: Temp Utilities and Service
Title: Ship’s Force Training
a) Propose LOE man-days associated with paragraph JA.0080.0000 in the planning phase and LOE man-days associated with paragraph JA.0020.0000 in the accomplishment phase.
b) Additional man-days beyond the LOE of each paragraph will be adjudicated via separate contract action as appropriate.
3. SWLIN Number: 080B01 – CLIN 0003
System: Reactor Plant Temporary Services
Title: Maintenance a) Proposal will not include prime standard alignment equipment. Additional cost associated with the prime standard alignment equipment will be considered growth and will be adjudicated via separate contract action as appropriate.
b) Proposal will not include inlet and outlet temp flush rig for AUX SW. Additional cost associated with the inlet and outlet temp flush rig for AUX SW will be adjudicated via separate contract action as appropriate.
c) Proposal will include TRLW RC bilge suction costs based on water contamination levels.
d) Proposal assumes installation of the temporary salinity indication system (D189579) include two salinity cells, 1 installed and 1 spare. Additional salinity cells will be adjudicated via separate contract action as appropriate.
e) Proposal for Temporary reactor air (TRA) includes setting up and maintaining the freeze seal equipment. Cost associated with additional closure devices will be adjudicated via separate contract action as appropriate. Interference removal such as lagging, hangers, or paint to install and maintain freeze seals will be contained in SWLIN 080B03.
f) Proposal assumes TRA design requirements are the same as VCS. Any deviation from the original TRA design will be adjudicated via separate contract action as appropriate.
g) Proposal assumes an existing CPW tank is available for use. Cost associated with manufacturing a CPW tank will be adjudicated via separate contract action as appropriate.
4. SWLIN Number: 080B02 –CLIN 0003
System: Reactor Plant Establish Plant Conditions
Title: Maintenance
a) Proposal assumes the existing ship's steam generating system is radiologically cleared and all connections made to the ship's system will be performed without contamination controls. Additional cost associated with contamination controls will be adjudicated via separate contract action as appropriate.
b) Proposal will be based on discharging off-hull through the escape trunk, in lieu of the aft bilge collection (ABC) tank. If discharging off-hull cannot be achieved through the escape trunk, additional requirements will be adjudicated via separate contract action as appropriate.
c) Proposal includes 1 spare Tygon tubing assembly for E4.0020.0000 poly bottle pump down. Additional cost associated with Tygon tubing assemblies will be adjudicated via separate contract action as appropriate.
d) Proposal includes removal and reinstallation of hanger HGR-SG-H-214, if required. Additional hanger work will be adjudicated via separate contract action as appropriate.
5.
SWLIN Number: 080B03 – CLIN 0003
System: Reactor Plant Lagging and Painting
Title: Maintenance a) Proposal assumes all paint material will be considered growth and will be adjudicated via separate contract action as appropriate.
6.
SWLIN Number: 831B02 – CLIN 0003
System: COOLANT PURIFICATION
Title: Maintenance a) Proposal will be based on installation and monitoring of 4 freeze seals on the CP system as a result of unsatisfactory seat leak test of the boundary valves. Should more freeze seals be required, additional requirements will be adjudicated via separate contract action as appropriate.
b) Proposal will be based on performance of a phase I risk assessment for each TWD/TGI to be issued and an estimated performance of 11 phase II risk assessments for high level contamination work, performance of SPS lifts, and mock-up/training work package execution shipboard. Should additional phase I or phase II risk assessments be required, they will be adjudicated via separate contract action as appropriate.
c) Proposal will be based on resin/media discharge and replacement process knowledge of high level interference removal required for in-hull DMD and resin/media load equipment installation (fill line closure lagging, deck grating for media load funnel installation, lagging for valve cap removal/containment installation, etc.). Additional interferences identified at the final planning meeting will be adjudicated via separate contract action as appropriate.
7.
SWLIN Number: 831D33 – CLIN 0003
System: Coolant Purification Title: Maintenance
a) Proposal will be based on valve operating/indicating parts (e.g. stem adapter, indicator dial, etc.) being in place, undamaged and without fixed contamination which requires replacement. If as found conditions are different, additional requirements will be adjudicated via separate contract action as appropriate.
8.
SWLIN Number: 860L06 – CLIN 0003
System: Plant Conditions and Testing
a) Proposal will be based on requiring 2 BFPL assemblies and 1 spare assembly. If additional BFPL assemblies are needed, the additional requirements will be adjudicated via separate contract action as appropriate.
b) Proposal assumes liquid control system (warning) requirements will be limited to the liquid level alarms currently used on poly-bottles. If additional controls are required beyond those on the poly-bottles, the additional requirements will be adjudicated via separate contract action as appropriate.
9.
SWLIN Number: 860L09 – CLIN 0003 System: Services (Prorated)
Title: Service (Prorated)
a) Proposal will include the use of NON-RCRA hazardous hotguard temporary shielding (tungsten impregnated silicone). Proposal does not include the material costs for lead wool temporary shielding. Additional material costs for lead wool temporary shielding or other material if required, additional requirements will be adjudicated via separate contract action as appropriate.
b) Proposal will not include procurement of tungsten powder. Tungsten powder if required will be adjudicated via separate contract action as appropriate.
10.
SWLIN Number: 861L06 – CLIN 0003
System: Project Management Prorated
Title: Project Management (Prorated)
a) Proposal will not include travel for items such as ship checks. Travel costs will be adjudicated via separate contract action as appropriate.
Non-Nuclear SWLINs:
1. SWLIN Number: 002Y01 System: General Requirements
Title: Configuration Control
a) Proposal will be based on using material process specifications and standards in accordance with the VIRGINIA Master Index of Reference Documents (MIRD). Contractor will continue to evaluate later revisions of these specifications for use on this contract on a case by case basis in accordance with current Standard Practice.
2. SWLIN Number: 033A01 – CLIN 0003 System: Ship Handling and Worksite Preparations Title: Prepare Ship for Availability
a) Proposal will be based on one (1) defueling and one (1) evolution for fueling the NFO tank or new fuel oil. New fuel or additional evolutions will be adjudicated via separate contract action as appropriate.
3.
SWLIN Number: 034A01 – CLIN 0003
System: Ship Handling and Worksite Preparations
Title: Docking and Undocking, Berthing and Mooring Services
a) Proposal is based on contractor determined number of days in dock; additional days in dock will be considered the contractor’s responsibility unless adjudicated via separate contract action as appropriate.
4.
SWLIN Number: 035A01- CLIN 0003
System: Ship Handling and Worksite Preparations
Title: Temporary Ship Systems a) Paragraph KV. 0040.0020 – Proposal will be based on contractor providing T1 line connection in lieu of Navy Marine Corps Internet (NMCI) connects.
b) Paragraph KV. 0100.0020 – Proposal will not include providing fluids and gases for forces afloat. If required, additional requirements will be adjudicated via separate contract action as appropriate.
5.
SWLIN Number: 037A01 – CLIN 0003
System: Ship Handling and Worksite Preparations
Title: Temporary Access Openings
a) Proposal will be based on performing hull cuts #6, 15, 33 and 37. Proposal is based on performing one hull circularity check in way of hull cut #37. Any additional circularity checks and emergent work requiring an access cut will be adjudicated via separate contract action as appropriate.
6.
SWLIN Number: 044A01 – CLIN 0003
System: Ship Support
Title: Protection and Preventive Maintenance
a) Proposal assumes samples for PCB being taken on gaskets, oil and sealant associated with the Reduction Gears being negative. Any additional controls will be adjudicated via separate contract action as appropriate.
7.
SWLIN Number: 054A01 – CLIN 0003
System: Production Services and Support
Title: Lagging – Piping and Machinery
a) Proposal assumes all prior damaged lagging and insulation repair/replacement to be included in the 30 man-day LOE from paragraph GS.0020.0000.
b) Proposal will not include costs for the removal of asbestos lagging or insulation. Removal of such will be adjudicated via separate contract action as appropriate.
8.
SWLIN Number: 083A01 – CLIN 0003
System: Trials and Certification
Title: Sea Trials
a) Proposal will not include costs for an escort vehicle. The fleet will provide.
b) Proposal will not include cost for temporary ballasting. Any re-ballasting required will be adjudicated via separate contract action as appropriate.
9.
SWLIN Number: 091I01 – CLIN 0003
System: Special Services
Title: Hazardous Waste and Other Pollutants
a) Proposal will not include cost for the handling of Ship’s Force hazardous waste and other pollutants. Handling of Ship’s Force hazardous waste will be adjudicated via separate contract action as appropriate.
10.
SWLIN Number: 430A01 – CLIN 0004
System: Sonar; Hydrophones and Transducers
a) Paragraph 28.2780.2283 – Proposal will be based on bolted interference removal only.
b) Assume defective cables identified on the STAG report will be provided as CFM.
Government Approved GFE1:
| SWILN |
| Requested GFE |
| 033A01 |
| SF Living Barge |
| 442A01 |
| Handling Gear for UHF Sensor/ HDR Mast |
| 442A01 |
| Shipping Container for HDR Mast And Antenna |
| 404A01 |
| Shipping Crate for Hoist Cylinder |
| 404A01 |
| Shipping Crate for BRD-7 |
| 203A01 |
| Propeller Specific Handling Gear |
| 203A01 |
| Shaft Removal Equipment |
| 083A01 |
| SEIE Suits |
| 425A01 |
| WSQ-9 Transducer Assembly Fixture |
| 076A01 |
| AURES and Associated Loading and Handling Gear |
| 831B02 |
| DMD -All In-Hull Containments and Temp Assemblies On NSFPY-S6G 1&2 |
| 203A01 |
| Government Will Recondition Retaining Ring to URO 28 Category "A" Condition |
| 307A01 |
| Positive Pressurization Unit for SSMG |
| 408A01 |
| Replacement Radar Pedestal |
| 849B01 |
| Module Test Stand |
| 083A01 |
| Escort Vehicle |
| 426A01 |
| Flushing Fixture and Fittings |
| 440A01 |
| Antenna Base Assemblies |
Government Approved DMD GFE1 (available if needed2):
| SWILN |
| GFE |
| 831B02 |
| Off Hull Building/ Basin Work Enclosure Mating Unit |
Glove Bags
Test Equipment
Canopy Cutting Machine
High Integrity Container (HIC)
Tower
Notes:
1. The Government will supply GFE items on a mutually agreed to delivery date.
2. Contractor is required to request the above DMD GFE if needed.
ATTACHMENT (1)