REQUEST FOR CLARIFICATION
Name of Offeror: Electric Boat Corporation Date: December 23, 2014
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 4
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 826D08 Title: DHR Pump Removal
Section/Paragraph No.:
Question:
Request clarification regarding note 1 of the SWLIN which indicates “Accomplish if DHR System is used…”
DO NOT WRITE BELOW THIS LINE ---- (SPACE BELOW FOR GOV'T USE ONLY)
Answer:
Performance of ShipAlt, if not already accomplished based on FCR-03 report, would only be accomplished if pump has been unshipped in order to be used (system operation) or if the pump needed to be removed for some other purpose (interference).
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 11
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 860L04 Title: RP Prepare RC
Section/Paragraph No.: KM.0020.0000
Question:
Request clarification regarding shielding requirements in this SWLIN vs those in SWLIN 860L09.
History shows shielding captured in 860L04 only.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 78
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 823B01 Title: NUCLEAR STEAM
GENERATOR
Section/Paragraph No.: 27.0129.1300
Question:
SWLIN states “Inspect steam generator secondary side internals (when steam generator is opened for other purposes).” and refers to RMR 6-M-R-2.
Since there are no requirements within the AWP to open the Steam Generators for any other purpose, can it be assumed that this work will not be required and therefore not be part of the bid estimate?
The Government concurs.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 79
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 827B01 Title: CHARGING
SYSTEM
Section/Paragraph No.: 50.0780.1303
Question:
SWLIN states “Inspect inside the storage tanks and replace the manhole gaskets.” and refers to
RMR 8-M-C-5.
Is there any history with regard to the extent to rework required as a result of the 8-M-C-5 inspections?
Yes, but minor. Past history shows that there is difficulty in the manufacturing of new gaskets for covers, and cleanliness issues occasionally arise during inspection of piping internal to tank.
Work inside the tank is rare after technical disposition.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 80
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 836B01 Title: REACTOR PLANT
FRESH WATER
COOLING
Section/Paragraph No.: 48.0180.0663 & 48.0180.0684
Question:
48.0180.0663 & 48.0180.0684 require both the FA and SY to inspect and clean the heat exchangers in accordance with 15-M-Q-1R.
1. Will this work be performed jointly by FA and SY?
2. Will the FA issue a REC form for this work in accordance with NAVSEA 0989-037-2000 and NAVSEA 0924-LP-062-0010 and issue a RPWAR in accordance with NAVSEA 0989- 037-2000, or will the SY be responsible for issuing the REC and the RPWAR?
SY should plan on generating work control documents.
Assignments in AWP will remain as is. SY will perform clean and inspect along with maintaining work controls.
Name of Offeror: Electric Boat Corporation Date: January 7, 2015
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 116
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 201A02 Title: REDUCTION GEAR
(SOUND
ISOLATION
COUPLING
ASSEMBLY)
Section/Paragraph No.: 28.0180.410A
Question:
Is it the Government’s intention to clear DFS 762-1010-2010 by replacing the sound isolation fwd & aft hubs and the matching fwd and aft sound isolation coupling sleeves along with associated hardware? Replacement will require a hull cut, as defined in the DFS. If so, please define material availability and add the required parts to schedule A of the solicitation.
SY should assume material is LLTM and should procure under CLIN 0007.
Name of Offeror: Electric Boat Corporation Date: January 16, 2014
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 134
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 131A01 Title: MAINTENANCE
Section/Paragraph No.: 27.0305.1302
Question:
1. Will the tapped holes and sealing surface for CD-4 and CD-35 hull connections be inspected during these availabilities?
2. What document will be used for the inspection criteria to inspect the tapped holes and sealing surface for CD-4 and CD-35 hull connections?
1. Yes
2. URO MRC 003.
Name of Offeror: Electric Boat Corporation Date: January 16, 2014
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 135
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 087L01 Title: GENERAL
REQUIREMENTS
RP I&C
EQUIPMENT
Section/Paragraph No.: BT.0140.000
Question:
The Subject SWLIN invokes NAVSEA 0989-0310-4000 for inspection and repair for all Reactor Plant Instrumentation and Control Equipment. This manual provides several levels of inspection requirements based on equipment’s Effective Time in Service (ETIS) and other criteria. Since both ships have received upgrades to Type II I &C, as well as other Field Changes, EB considers the ETIS category to be “SHORT”, requiring only Limited Internal Inspection defined as no disassembly, as required by G/I 21.4.2.
EB requests NAVSEA concurrence regarding the level of inspection identified above. This effects the following CPFF SWLINs:
848B01, 849B01, 847B01, 843B01
The Government concurs. With respect to G/I 21.4.1 of NAVSEA 0989-0310-4000, there are no instances based on NAVSEA08 knowledge of this equipment in which NAVSEA08 intends to direct a different specific category be utilized.
| EBC BQ 4 11 78 79 answers |
| EBC BQ 116 answer |
| EBC BQ 135 answer |