2015Jan12-EBC_BQ_answers.pdf
PDF 918 KB Posted
- Attached to
- USS COLUMBUS (SSN 762) Engineering Overhaul (EOH) Federal contract opportunity
- Solicitation number
- N0002415R4300
About this file
Responses to EBC Bidder's Questions
View the file
Other files for this federal contract opportunity
Show all 50
USS COLUMBUS (SSN 762) Engineering Overhaul (EOH) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL DYNAMICS
Electric Boat
REQUEST FOR CLARIFICATION
Name of Offeror: Electric Boat Corporation Date: December 23, 2014
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 3
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 022A01 Title: Pre-Availability Planning
Section/Paragraph No.: Note 11
Question:
Pre-Installation Check-Out (PICO) testing is normally held 30-60 days prior to the start of availability. Will the PICO testing be held at SUBASE Groton or a different location?
DO NOT WRITE BELOW THIS LINE ---- (SPACE BELOW FOR GOV'T USE ONLY)
Answer:
Testing will be held at a different location.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 5
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 028B01 Title: RP General Inspection
Section/Paragraph No.: ZL.0020.000
Question:
SWLIN identifies DOP testing to be performed however DOP is a carcinogen and its use has been discontinued. Request SWLIN be modified to identify PAO in lieu of DOP.
DOP testing is an acronym used to describe the testing of High Efficiency Filters. This acronym was derived from Di-Octyl Phthalate, which has been identified as a carcinogen. Poly Alfa Olefin (PAO) is the currently authorized chemical to be used to verify effectiveness of High Efficiency Filters.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 6
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 860L09 Title: Services
Section/Paragraph No.: KC.0060.0000
Question:
Request Dosimetry Services for the availability be reassigned to the SY as the availability will be at the SY vs. at the SUBASE.
Concur
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 7
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 014B01 Title: PATS and POTS
Section/Paragraph No.: LL.0020.0000
Question:
As nuclear test gear and support (radiological/technical) for POTs testing will be accomplished prior to availability start, will the Government change the assignment from SY to local NRMD?
Due to the geographical separation of the shipyard and the vessel, provisioning controlled test equipment is considered cost prohibitive. The provisioning of test equipment to support SF POTs should be provided by their local FMA/NRMD/FMB as requested by SF.
The SY should provide the engineer to support SF in preparing for and accomplishing the POTs.
LL.0180.0000 should not require SY to provide equipment, delete “and a list of test equipment shipyard is to provide” and LL.0300.0000 should be reassigned to NRMD/FMA
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 8
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 083B01 Title: RP Gen Care & Protection
Section/Paragraph No.: ST.0020.0000
Question:
Request SWLIN assignment be modified to include FA as a responsible party since most of the protective gear is typically installed by FA.
Do not agree. Installation of protective coverings on ship’s equipment has historically been SY assigned for Major Availabilities, and requires significantly more durable and wider applicability than is possible by Ships Force.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 9
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 860L09 Title: Services
Section/Paragraph No.: DF.0020.0000
Question:
Request that the verbiage be modified to delete (NRMD for EB). NRMD does not represent forces afloat nor EB for the purposes of developing an agreement between the performing yard and the ship for the availability.
Concur
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 10
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 028B01 Title: RP General Inspections
Section/Paragraph No.: FB.0060.0000
Question:
Request clarification regarding assignment of Q COSAL responsibilities as replenishment of missing/consumed stock and or repair is not a normal S/Y responsibility.
If either availability is executed at HII-NNS, assignment will be for NRMD Norfolk.
If either availability is executed at EB, assignment will be for NSSF New London.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 12
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 032A01 Title: Weigh Materials
Section/Paragraph No.: SN.0060.0000
Question:
SF is assigned to provide a report of all material that will not be reloaded to the boat.
Will the SF report be sufficient to account for weight changes from stowed equipment before and after availability execution or will the SY be required to weigh all SF gear being removed prior to availability start?
The post DMP trim dive on SSN 761 resulted in the need to add 17LTs of cargo lead to compensate for off/on-loan provisioning disparity that wasn’t reported by Ship’s Force.
The shipyard should, as a minimum, train and require SF to weigh all off-loaded and on-loaded provisioning and provide services and oversight to ensure this is being done. This effort should begin following the pre-availability trim dive and continue through the post availability trim dive.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 13
Ship(s): SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 505A01 Title: Plumbing
Section/Paragraph No.: 44.0020.U008
Question:
AWP requires accomplishment of URO MRC 008 for PL-49/50, which requires removal and significant disassembly of PL-49/50. History has shown that without significant repair, restoration or replacement of PL-49/50 it won’t pass required retest even if disassembly occurred after only a short period of being in service. Will the Government make a CCRP asset available in lieu of restoration?
The Government's intent is to defer the URO MRC 008 inspection of PL-049/050 to EOH-01 (DFS 765-0026-2014 refers). Because of this action the restoration will not be required and the CCRP replacement will not be provided. DFS 756-0026-2014 has been extended to the EOH. URO MRC 008 for PL-49/50 has been removed from the AWP (Change 009).
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 17
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 131A01 Title: Maintenance
Section/Paragraph No.: 27.0137.U001
Question:
Are the SHT tiles removed to accomplish URO MRC 001, NDT Surveillance of Selected Hull Welds, included in the 500 tiles listed in Section 27.0165.U003, Note 1?
The 500 tile estimate listed in URO MRC 003 does not include the tile removal necessary for the accomplishment of URO MRC 001.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 18
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 131A01 Title: Maintenance
Section/Paragraph No.: 27.0142.U005
Question:
Are the SHT tiles removed to accomplish URO MRC 005, Ultrasonic Monitoring Inspection of Hull Welds with Known Discontinuities, included in the 500 tiles listed in Section 27.0165.U003, Note 1?
The 500 tile estimate listed in URO MRC 003 does not include the tile removal necessary for the accomplishment of URO MRC 005.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 19
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 131A01 Title: Maintenance
Section/Paragraph No.: 27.0305.2100
Question:
The scope/purpose of this line item is unclear. This line item references SMS 1110-081-020 which is the same SMS called out by 27.0305.1302. Is there a departure requiring repair of specific tapped holes in the subject hull insert(s)?
There are no active departures at this time.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 20
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 131A01 Title: Preservation
Section/Paragraph No.: 82.0100.2809
Question:
This line item requires clean and repair/restore of the preservation associated with exterior pressure hull, including the exterior of trunks and hatches in accordance with ATTACHMENT 7 of SMS 6310-081-015. ATTACHMENT 7 requires assignment of a preservation coating grade in order to determine the level of surface preparation and preservation work needed. The exterior surface of the hull does not use the same coating rating as internal tanks or recesses. How will the contractor assess the condition of the paint on the exterior of trunks and hatches to determine if a full abrasive blast and preservation is required?
Attachment 7 of MS 6310-081-015 provides the specific requirements for preserving the exterior/underwater hull of the submarine. Hatch exteriors and exteriors of trunks can be treated the same as exterior/underwater hull area. Paragraph 1.c.3.e.2 of attachment 7 provides the requirements for touchup vs. full blast and represerve.
See below:
1.c.(3)(e){2} For exterior underwater hull areas, preservation system failure up to 30 percent of the total area may be repaired by touchup painting. If the amount of touchup painting will cover an area greater than 30 percent of the total surface area being worked and the failure of the preservation system is scattered throughout the area so that touchup painting will not be cost effective, the area should have the coating completely removed and the area repainted. Surfaces covered by damping or acoustic tiles are not included when determining percentage of failure in a tank or free flood area. If the tiles are removed, the exposed areas are included. Free flood areas and enclosed spaces are not included when determining percentage of failure of exterior hull areas.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 21
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 131A01 Title: Maintenance
Section/Paragraph No.: ShipALT Interface
Question:
ShipALT SSN4635(K), Low Cost Conformal Array, is documented under the ShipALT Interface section of SWLIN 131A01. On previous availabilities, SSN 768 and SSN 769, ShipALT SSN4635(K) had no interference with the Pressure Hull. Is there a modification to the ShipALT that affects SWLIN 131A01?
There has not been an adjustment to the SHIPALT that includes new interferences for SWLIN 131A01. This is included in the interfacing systems due to penetrations through the pressure hull for the EHFs and other structural interfaces. The executing activities shall review SHIPALT 4635(K) and the ship's configuration for each availability to determine the necessary interferences to be removed/remedied.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 24
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 132A01 Title: External Tapped Holes
Section/Paragraph No.: 27.0305.1302
Question:
This line item tasks the Shipyard to clear DFS SSN-762-0010-2014. The DFS has no details regarding the quantity or location of stripped holes in the MBT 4A/4B vent valve insert. The amount of weld repair required may impact the type of interference removal (SHT, vent valve components, etc.) to support clearing this DFS. The contractor requests details on the extent of damage (number of stripped holes, location(s) around the bolt pattern, etc.) identified in DFS SSN- 762-0010-2014.
Main Ballast Tank (MBT) 4A and 4B bolt holes are located on or near aft pressure hull frame flange. The MBT vent valve cover bolt holes are stripped degrading the ability to install MBT covers. There are a total of 8 bolt holes per valve or 16 total bolt holes.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 25
Ship(s): SSN 762 EOH and SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 176A01 Title: Tank Inspections
Section/Paragraph No.: 80.0010.1381
Question:
The subject line item does not provide any configuration items (maintenance standard, URO MRC EGL number, DFS, NAVSEA Letter, etc.) to work to for this inspection. The contractor requests clarification on the required location(s) for this inspection, the applicable accept/reject criteria and the reporting requirements.
GCMA 80.0010.1381 requires inspection of the void between tank tops and the canning plates above the tank tops. The intent of this requirement is to inspect any areas entered during the availability that are not generally available to inspect. The accept/reject criteria is any sign of cracks/corrosion/damage to a canning plate over a tank that would allow water to enter the void space and collect on the tank top. Completion of this requirement will ensure that water cannot collect on tank tops leading to corrosion.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 29
Ship(s): SSN 762 EOH and SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 111A01 Title: A&I3309
Section/Paragraph No.:
Question:
The contractor requests that the government confirm whether A&I 3309 (Install Removable Sail Plates) is accomplished on SSN 762 and SSN 765. Records available to the contractor show that this A&I were completed on both SSN 762 and SSN 765?
Subject A&I was completed on both units.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 30
Ship(s): SSN 762 EOH and SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 131A01 Title: URO MRC 001 Item 11
Section/Paragraph No.: 27.0137.U001
Question:
The contractor requests that the government provide the list of the remaining 50% of URO MRC 001 Item 11 penetration welds that were not inspected during the last accomplishment of URO MRC 001 for both SSN 762 and SSN 765. Depending on the location(s), gaining access to some of the required penetration welds may require substantial interference removal or access to areas not already being opened. When will SUBMEPP provide the information assigned in the AWP?
SUBMEPP provides the completions for URO MRC 001 Item 11. It's up to the executing activity to determine the ship's configuration for remaining penetration welds to be inspected by URO MRC 001 Item 11.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 31
Ship(s): SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 131A01 Title: Deferred Work
Section/Paragraph No.: 88.0004.2009
Question:
DFS 765-1023-2013 was changed from permanent to temporary due to a NAVSEA 05 write-up (attached in eDFS) requesting a “full set of hull structural measurements” at the IDD availability.
The NAVSEA 05 write-up states that these measurements are required to assess the OOF condition before the DFS can be accepted as permanent. Is the contractor responsible for evaluating the data in order to clear the departure? Or is the contractor only responsible to provide the data to NAVSEA 05 for their own analysis?
The inspecting activity should collect the data and perform analysis to determine OOF and resulting impact to hull structure. The data package and analysis report should be forwarded to NAVSEA for concurrence.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 34
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 505A01 Title: UT Inspect Sanitary System Suction and Discharge Piping
Section/Paragraph No.: 70.0000.1505
Question:
The AWP requires the SY to UT inspect sanitary system suction and discharge piping and identify deficiencies at the Final Planning Meeting. When will the ship be made available and what are the dates and place for accomplishment of this inspection?
Typically, these inspections are performed between A-13 to A-7 time frame. Dates and places are TBD.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 35
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 111A01 Title: SUPERSTRUCTURE
& FAIRWATER
MAINT
Section/Paragraph No.: 74.0080.1300
Question:
Should we assume a replacement of all cathodic protection anodes in the fairwater? If not, please provide percentage.
SY should propose labor and material costs based on historical data to form their basis of estimate.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 36
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 156I01 Title: BALLAST
Section/Paragraph No.: 80.1000.4400
Question:
This specification on previous Submarine availabilities provided a man-day Level of Effort to accomplish re-ballasting (i.e. SSN 708 IDD - 200 man-days and SSN 769 DMP -350 man-days) Will the Government modify this specification to make it a level of effort?
The LOEs cited in individual SWLINS are established as basic controls for utilization of overall LOE hours to specific SWLINs based Baseline AWPs. The government does not intend on providing a specific LOE for SWLIN 156I01, as it is part of the overall Cost Plus Fix Fee CLIN 0010 effort to be executed by the contractor, and sufficient detail cannot be provided at this point in planning process. Contractors should base their estimates on historical data or an engineered estimate.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 37
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 429A01 Title: SONAR, UTILITY
MAINT
Section/Paragraph No.: 28.6181.0323
Question:
Is it the intent of this requirement to conduct the CSTP429-2-3018 prior to the start of any industrial activity (i.e., removal phase) to establish a baseline of the TSMS performance, to identify deficiencies, and provide protective covering devices for the TSMS system, and then to reconduct the CSTP429-2-3018 post-industrial activity (installation phase) to certify the TSMS performance?
Or Is it the intent of this requirement to remove and install the TSMS during this availability, utilizing the CSTP429-2-3018 to baseline and re-certify the TSMS?
The intent is NOT to remove and reinstall the TSMS during the availability as described above in "option 2". The intent is more in line with "option 1" above with clarification below:
Clarification: The intent of this MR is to conduct the applicable test (based on hull configuration), for a complete inspection and repair of the TSMS components. This is to be accomplished during the ongoing availability, mainly due to the TSMS system being located throughout the ship and being disturbed as interference to other work being accomplished. This gives the execution activity a way to certify the TSMS system under one line item, instead of conducting the same test for each and every time the system is disturbed. Work on the TSMS system should be coordinated with other ongoing work and testing of the system should be completed when work in the area is completed.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 38
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 307A01 Title: SHIP'S SERVICE
MOTOR
GENERATOR SETS
Section/Paragraph No.: 35.0900.22NU
Question:
Does SF have a positive pressurization unit (PPU) installed or available?
Yes, but SY typically provides source of air.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 39
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 426A01 Title: SONAR, ACTIVE
MAINT
Section/Paragraph No.: 28.5411.2200
Question:
The SY is tasked to replace the Thin Line Towed Array pendant cable and slip ring. On previous availabilities FTSCLANT has performed inspection and repair work on various components of the TLTA with EBC assistance. EBC recommends that they accomplish this work and provide all replacement material. Does the government concur?
The government disagrees with the proposed reassignment to STSC/FTSC. Historically STSC/FTSC provides technical support to the shipyard or conducts Engineering Changes/Technical Changes as an
AIT.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 42
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 006Y01 Title: MATERIAL
MANAGEMENT
Section/Paragraph No.: GM.0020.0000
Question:
Several components in the AWP are identified as "must be replaced vice restored" per the Corporate Component Repair Program (CCRP) but also have a Maintenance Standard invoked which requires the completion of a Material Condition Feedback (MCF) form for the existing item that is replaced.
Is it the Government's intention for SY to disassemble and inspect existing components in order to complete the Material Condition Feedback (MCF) form? To what extent should the existing component be inspected, if at all, for the purpose of completing the MCF form? An example is TD- 154 (SWILN 508A01, paragraph 44.2820.2100).
No, SY should send existing items to local Designated Overhaul Point (DOP) (i.e. NNSY, PNSY). The local DOP will be responsible for disassembly, inspection and performance of URO-008/009 on CCRP valves and actuator off-loads.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 43
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 111A01 Title: SUPERSTRUCTURE
& FAIRWATER
MAINT
Section/Paragraph No.: 27.0076.U003
Question:
Paragraph 27.0076.U003 states to accomplish URO MRC 003 and to remove portions of plating, as necessary, to obtain access for inspection, repair and preservation. Is it also the Government's intention for the Sail to be depopulated of masts, antennas, cables, cable guards, insulation, etc.
during the accomplishment URO MRC 003 or to inspect just the accessible areas?
Yes, the intention is total depopulation.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 44
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 131A01 Title: PRESSURE HULL
MAINT
Section/Paragraph No.: 27.0140.U004
Question:
How many SHT tiles should the SY plan on removing in order to facilitate the UT sampling of the hull welds? Typically 3 tiles need to be removed IWO each site.
SY should propose SHT tile interference removal based on historical data. The SHT tiles removed as interference are not included in the SHT tile replacement estimate level of effort.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 45
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 518A01 Title: STEERING &
DIVING
HYDRAULICS
MAINT
Section/Paragraph No.: 50.0120.0620
Question:
The SY has been tasked to inspect, clean, repair and re-preserve the vent and supply tank only if enter for other reasons. The SY knows of no known work that would require entering the tank. Can the SY assume that this tank will not be entered?
Agree with assumption. This GCMA should be deleted. If New/Supplemental Work is identified that requires the hydraulic vent and supply tank to be opened this requirement will have to be included with that change.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 46
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 534A01 Title: RESCUE, SALVAGE &
SURVIVAL MAINT
Section/Paragraph No.: 84.0020.1801
Question:
Perform oil sample analysis on the AFT and/or FWD Escape Trunk Upper Hatch Hydraulic System fluid to determine cleanliness in accordance with NSTM Chapter 556 is assigned to SF and SY.
Report results of analysis with recommendations at the Final Planning Meeting.
Is there any SY action for this paragraph?
This pre-availability inspection/test is SF/FMA capable. Reassign to SF/FMA.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 48
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 540A01 Title: NORMAL &
EMERGENCY
BALLAST TK
BLOW
Section/Paragraph No.: 43.0025.1013
Question:
Removing instrument valve test caps to take samples are a REC exception for Ship's Force so assigning to Ship's Force would reduce cost. If not assigned to ship's force request permission to use Portable Hygrometer GE Panametrics PM880 in lieu of Stephens Analytical Model 600-DDL (reference MRC 7BDB). Model 600-DDL appears to be no longer available and technical specification could not be found for comparison to other meters. Response should also include SWLIN 513A01 paragraph No. 43.0020.1013 (page 2 of 3) for consistency.
Agree. Assign to SF.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 50
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 404A01 Title: ELECTRONIC
WARFARE
SUPPORT
Section/Paragraph No.: 29.0122.2100
Question:
Note1 requires that "project order funding" be provided to CDNSWC PHILA (CODE 962DL). This paragraph is assigned SY. Will a government agency provide this "project order funding" and will they be added to the assignment of this paragraph?
TYCOM will directly fund the organizations where “project funding” is required.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 55
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 071A01 Title: INTEGRATED
AVAIL TEST PLAN
Section/Paragraph No.: YM.0080.5174
Question:
Access to Vital Equipment
a. SWLIN 071A01 Section YM.0080.5174 states "SSN688 Class mandatory TP No. 080-5174, Access to Vital Equipment (URO 029) is now accomplished in SWLIN 905A01" with Assignment SY.
b. SWLIN 905A01 Section 80.3040.U029 states "Accomplish URO MRC 029, Confirm Adequacy of Access to Vital Equipment" with Assignment SF.
As Government response to HII question #101 was to reassign the work to SF, will a similar reassignment to SF using URO-MRC 029 be made for the SSN762 EOH?
TYCOM agrees.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 60
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 708F02 Title: TORPEDO
TUBES/TORPEDOS
ORDALT
ACCOMPLISHMENT
Section/Paragraph No.: 94.0101.8000
Question:
Kitted material defined in section 12.1.1 of ORDALT 18000 is listed as provided by NUWC for 4 tubes (1 kit per ship). EBC requests clarification that this material is considered GFE without cost to the bidder and is readily available, not considered long lead material, for installation.
Material is GFE and is not LLTM.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 61
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 708F03 Title: TORPEDO
TUBES/TORPEDOS
ORDALT
ACCOMPLISHMENT
Section/Paragraph No.: 94.0101.8009
Question:
Kitted material defined in section 12.2 of ORDALT 18009 is listed as provided by NUWC for 1 tube (4 kits per ship). EBC requests clarification that this material is considered GFE without cost to the bidder and is readily available, not considered long lead material, for installation.
Material is GFE and is not LLTM.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 62
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 442A01 Title: RADIO, ULTRA
HIGH FREQUENCY
(UHF) MAINT
Section/Paragraph No.: 28.6675.2100
Who will provide handling gear for sensor/mast to support the depopulation of the sail?
Contractor shall specify GFM requirements in accordance with CDRL A002.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 63
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 176A01 Title: BUILT IN TANKS
MAINT
Section/Paragraph No.: 74.0080.1303
Question:
Based on the Governments answer to HII question #130 please confirm that SY should assume that 30% of the cathodic protection anodes will need replacement?
Please refer to the amended response for HII-NNS question #130.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 65
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 607A01 Title: INSULATION
(HULL, BULKHD,
DECK MAING)
Section/Paragraph No.: 80.1520.1302
Question:
Can we assume replacement of 100 tiles (exterior vibration dampening tiles) as done on past availabilities? Can we assume replacement of 140 tiles (interior vibration dampening tiles inside tanks) as done on past availabilities?
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 66
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 607A01 Title: INSULATION
(HULL, BULKHD,
DECK MAING)
Section/Paragraph No.: 80.1620.1309
Can we assume replacement of 250 SF (TLT material) as done on past availabilities?
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 68
Ship(s): SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 840D27, 841B01, 843B01 & 847D42
Title: SHIPALTs and A&Is
Section/Paragraph No.: Various
Question:
Request the government provide copies of the following SHIPALTs and A&Is assigned to the Shipyard in the work package:
A&I Q2431 A&I Q2443
SHIPALT SSN4660F
SHIPALT SSN4708F
Each contractor’s respective SUPSHIP will provide the documentation.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 69
Ship(s): SSN 765 IDD and SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 022A01 Title: PATs and POTs
Section/Paragraph No.: Various
Question:
Will the shipyard get the prescribed time (in accordance with the BPMP) to conduct PATs and POTs (i.e. PATs and POTs should be completed in Work Discovery Periods in the A-13 to A-7 timeframe;
PICO should be completed in the A-3 to A-2 timeframe). Will this be funded separately as the SY must travel to wherever the ship will be and that is unknown at this time?
Yes, BPMP will not be part of any contract, but can be used as a guide for pre-planning.
This effort will be funded separately if an Advanced Planning contract is not awarded at the time PATs and POTs are executed.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 70
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 307A01 Title: SSMG
MAINTENANCE
Section/Paragraph No.: 58.0340.0613
Please provide the maintenance standard the work is to be accomplished with.
The maintenance standard to be used to accomplish this work is 3140- 081-081. The SSN 688 Class Maintenance Plan has been updated to reflect this maintenance standard.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 71
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 176A01 Title:
Section/Paragraph No.: 50.0850.1302
Question:
Typically AWPs which have SWLIN 176A01 SLI 50.0850.1302 have a note which states;
For level of effort purposes:
a. Estimate to include 10 mandays as a contingency for manhole"
Will this note be added to the revised AWP?
The contingency cited in individual SWLINS are established as basic controls for utilization of overall man-days to specific SWLINs based on Baseline AWPs. The government does not intend on providing a specific contingency for SWLIN 176A01, as it is part of the overall Cost Plus Fix Fee CLIN 0004 or 0010 effort to be executed by the contractor, and sufficient detail cannot be provided at this point in planning process.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 72
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 176A01 Title:
Section/Paragraph No.: 50.0850.1325
Question:
Typically AWPs which have SWLIN 176A01 SLI 50.0850.1325 have a note which states;
For level of effort purposes:
a. Estimate to include 100 mandays as a contingency to cover necessary repairs.
The contingency cited in individual SWLINS are established as basic controls for utilization of overall man-days to specific SWLINs based Baseline AWPs. The government does not intend on providing a specific contingency for SWLIN 176A01, as it is part of the overall Cost Plus Fix Fee CLIN 0004 or 0010 effort to be executed by the contractor, and sufficient detail cannot be provided at this point in planning process.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 73
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 605A01 Title:
Section/Paragraph No.: 82.0025.0666
Question:
Typically AWPs which have SWLIN 605A01 SLI 82.0025.0666 have a note which states;
Funding limitation of 200 man-days is not to be exceeded without prior approval by Type Commander
The government does not intend to revise the AWP. The contractor should follow the basic SWLIN 605A01 Note 2 on page 1 of 3.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 75
Ship(s): SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 828B01 Title:
Section/Paragraph No.:
Question:
The USS MONTPELIER AWP, SWLIN 828B01, includes a requirement to replace PS-1 per NAVSEA Letter Ser 08M/C13-04028. NAVSEA response to Newport News Bidders Question 11 identifies that the USS MONTPELIER AWP does not currently include PS-1 replacement. Has the AWP been revised?
For proposal purposes, assume PS-1 replacement will not be accomplished on SSN 765. Any AWP revision will be by separate correspondence.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 76
Ship(s): SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 087L01 Title:
Section/Paragraph No.:
For the USS MONTPELIER IDD, SWLIN 087L01 is not specified in either the FFP or CPFF table?
This SWLIN only provides General Requirements for 800 series SWLINs and does not delineate any SY work.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 77
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: Title:
Section/Paragraph No.:
Question:
On page 48 of the RFP, Liquidated Damages in accordance with FAR 52.211-11 are specified.
However, FAR 52.211-11 was removed from the invoked clauses in the official version of the RFP.
Will the Government delete reference to Liquidated Damages on page 48 of the RFP?
No the Government will not delete the reference to Liquidated Damages on page 48 of the RFP.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 84
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: Title:
Section/Paragraph No.:
Question:
EBC recommends the following Recommend the following SWLINs be moved from FFP to CPFF
CLINS:
i. 036I01
ii. 041A01
iii. 044A01
iv. 045A01
v. 054A01
vi. 073A01
These SWLINs clearly defined reasonable fixed priced efforts, some of which provide Level of Effort limitations; as such the government intends to keep these SWLINS as FFP.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 85
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: Title:
Section/Paragraph No.:
Question:
The CLIN 0003/0009 SWLINs as specified in the RFP are comprised primarily of service and support type tasks, normally associated with and tied to work being conducted in the end use SWLINs which are predominantly specified in CLIN 0004/0010 in the RFP. If emergent work causes an increase to CLIN 0004/0010 in accordance with Note D and Note I of the RFP, will there be a corresponding adjustment to the associated service and support cost in CLIN 0003/0009?
The SWLINs identified in CLINs 0003 and 0009 are considered duration related not necessarily associated with touch labor hours; as such are considered more representative of FFP pricing. Any change in the period of performance due to new or growth work should fully bear all associated costs as has been the past practice of the contractor’s change proposals.
Name of Offeror: Electric Boat Corporation Date: December 30, 2014
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 86
Ship(s): SSN 762 EOH and SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 178A01 Title: PLATFORMS, WALKING FLATS, NON-
STRUCTURAL
BLKHDS
Section/Paragraph No.: 80.0000.2200
Question:
Should the contractor plan on removing the nucleonics room door during the SSN762 EOH and SSN765 IDD availability?
There are no known deficiencies with the nucleonic door at this time. Contractor should evaluate whether there is any work in the AWP that might require the door be removed.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 87
Ship(s): SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: VARIOUS Title: DFS765-1015-2013
Section/Paragraph No.: 131A01 para 88.0003.2009 132A01 para 88.0003.2009 170A01 para 88.0001.2009 518A02 para 88.0001.2009
Question:
In order to clear this DFS, a complete URO MRC 003 inspection, full blast and complete preservation is required. Is it the Government’s intention to clear the DFS or evaluate the subject areas and request this DFS be extended to a future EOH availability?
Evaluate and resubmit for extension to EOH.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 88
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: VARIOUS Title: ALTERATIONS
Section/Paragraph No.: VARIOUS
Please provide the below missing alteration documents required to support proposals:
Documentation will be provided by each contractor's respective
SUPSHIP.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 89
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 513C24(762)/513C25(765) Title: ShipAlt SSN4402D
Section/Paragraph No.: 92.0100.4101
Question:
92.0100.4101 Accomplish ShipAlt SSN4402(D), Standardize AHP Dew Point Monitor.
This line item tasks the Shipyard to Accomplish ShipAlt SSN 4402 (D) Rev. 1. This ShipAlt had been Contracted previously for SSN 719 and 768 to Electric Boat. Both installations encountered numerous problems and were subsequently canceled (Specification Item Number 719.076 and 769.069) by the customer due to design issues with Rev. 1 of the ShipAlt.
Is it the intent of the Government that a Revised ShipAlt will be provided and the 762 and 765 AWP be updated?
No.
Name of Offeror: Electric Boat
Corporation Date: December 30, 2014
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 90
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: VARIOUS Title: CPFF/FFP
DISCREPANCIES
Section/Paragraph No.: VARIOUS
Question:
In Section C of the RFP, there are numerous differences in the SSN 765 IDD and the SSN 762 EOH contract type designation for SWLINs. Electric Boat requests that the RFP be modified for consistency as recommended in the table below:
SWLIN Description
SWLIN.TYPE
SWLIN.TYPE Recommendation 014B01 Reactor Plant - PATs FFP CPFF Change SSN 765 to CPFF
032A01 Ship Handling and Worksite Prep - Weight Control CPFF FFP/CPFF Delete FFP Designation from SSN 762
037A01 Ship Handling and Worksite Prep - Temp Access Openings CPFF FFP Change SSN 762 to CPFF
040B02 Temp Utilities and Services - Ships Force Training Not Listed CPFF Change SSN 765 to CPFF
066A01 Inspection and Quality Control - AERP Comp. Test FFP CPFF Change SSN 765 to CPFF
083A01 Trials and Cert - Sea Trials CPFF FFP Change SSN 762 to CPFF 087B02 Reactor Plant - Maintenance CPFF FFP/CPFF Delete FFP Designation from SSN 762 087L01 Reactor Plant - General Req'ts Not Listed FFP Change SSN 765 and SSN 762 to CPFF 509A01 Potable Water CPFF FFP Change SSN 762 to CPFF 558A01 Aux Fresh Wtr Cooling FFP CPFF Change SSN 765 to CPFF 612P25 Furnishings - SA 4762KP CPFF Not Listed Change SSN 762 to CPFF 837B01 Primary Shield Wtr CPFF FFP Change SSN 762 to CPFF 848E12 St Gen Wtr Level Controls - SA4702 FFP CPFF Change SSN 765 to CPFF 854B01 Radiation Shielding - Primary CPFF FFP Change SSN 762 to CPFF 860L01 Reactor Plant - Engr Common Serv FFP CPFF Change SSN 765 to CPFF 860L02 Reactor Plant - QA Common Serv FFP CPFF Change SSN 765 to CPFF 860L09 Reactor Plant - Services FFP CPFF Change SSN 765 to CPFF 861L01 Reactor Plant - Supv Engr Serv FFP CPFF Change SSN 765 to CPFF 861L02 Reactor Plant - Supv QA Serv FFP CPFF Change SSN 765 to CPFF 861L03 Reactor Plant - Supv Rad Control Serv FFP CPFF Change SSN 765 to CPFF
903I01 Gen Req'ts - Engr and Planning Serv FFP FFP/CPFF Delete CPFF Designation from SSN 762
The government concurs with the overall recommendation and the following specific changes:
014B01 - Make both FFP 032A01 - Delete "FFP/" on 762 EOH 037A01- make both CPFF 040B02- make both FFP (LOE specified) 066A01 - make both FFP 083A01 - make both FFP 087B02 Delete "FFP/" on 762 EOH 087L01 - Delete from 762 (no work) 509A01 - make both FFP (LOE specified) 558A01 - Remain as written. 762 EOH includes A&I N3531 whereas 765 doesn't.
612P25 - Delete from 765. This is an AIT Install, support services are under CLIN 0005.
837B01 - make both FFP 848E12 - make both CPFF 854B01 - make both FFP 860L01 - make both FFP 860L02 - make both CPFF 860L09 - make both CPFF 861L01 - make both FFP 861L02 - make both FFP 861L03 - make both FFP 903I01 - delete/CPFF from 762
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 91
Ship(s): SSN 765 IDD and 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 036I01 Title: CPFF/FFP
Section/Paragraph No.: VARIOUS
Question:
For both SSN 765 IDD and SSN 762 EOH, SWLIN 036I01, Ship Handling and Worksite Preparations - Temporary Production Utilities, is designated as a FFP effort. Per NAVSEA response to Industry day questions, Item 29, each Shipyard shall provide a proposal for how 8010 manual requirements will be implemented in the Shipyard for these availabilities. Because the 8010 implementation procedures will not be agreed upon before the proposal submittal, will the government change the designation for SWLIN 036I01 from FFP to CPFF?
This SWLIN will remain FFP. It is recognized by the government that the 8010 is not invoked in its entirety at private nuclear capable yards, and is under review by separate contractual actions. The requirements of SWLIN 036I01 provide discrete fire protection requirements, using 8010 only as a reference for clarification. The government recognizes the contractor may take exception to providing any additional services above and beyond those provided during the conduct of the most recent CNO Major Availability completed in 2014.
Name of Offeror: Electric Boat Corporation Date: January 3, 2015
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 93
Ship(s): SSN 762 EOH and SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 308A01 & 309A01 Title: AC/DC POWER
DISTRIBUTION
SWITCHBOARDS
Section/Paragraph No.: 60.0080.7CCT
Question:
Historically MRC 7CCT is performed by SF/PMT. Electric Boat requests that MRC 7CCT assignment be transferred to SF/PMT.
MRC 7CCT needs to be accomplished by the shipyard as post-repair test prior to energizing the switchgear. For minor availabilities, 7CCT is performed by SF/PMT only as a pre-availability test.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 94
Ship(s): SSN 762 EOH and SSN 765 IDD
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: Various Title: VARIOUS
Section/Paragraph No.:
Question:
Request for clarification of the SWLIN sections listed below. These sections are assigned to the SY.
Is it the Governments intent for Electric Boat to provide the funding stipulated for these efforts? If so, what are the funding amounts/limits for those line items without defined funding requirements?
Boat SWLIN Line Item Value if provided
762/765
404A01 29.0122.2100
NOTE 1
Provide project order funding directly to and ship AN/BRD-7 mast assembly in conjunction with Section 29.0162.2100 to CDNSWC PHILA (Code 962DL) for fairing replacement, cycle testing and return.
762/765
404A01 29.0162.2100
NOTE 1
Provide project order funding directly to and ship AN/BRD-7 hoist cylinder assembly in conjunction with Section 29.0122.2100 to CDNSWC PHILA (Code 962DL) for restoration, testing and return.
415A01 27.0000.0501
Provide project order funding ($5,500 (Type 8), $7,700 (Type 18)) directly to NUWCDIVNPT Northeast Periscope Regional Repair Center.
415A01 31.0160.2100
04. Within 7 days of receipt of estimates from NUWCDIVNPT Northeast Periscope Regional Repair Center, provide project order funding (Funding POC, NUWCDIVNPT, Code 3402, 1-800- 669-6892, X2-8412) for repair, grooming preservation, acceptance testing at NUWCDIVNPT, and final on-board certification testing.
415A01 31.0180.2100
Provide project order funding directly to and ship PERISCOPE #1 and #2 fairing assemblies (including fairings and closure cap) to CDNSWC PHILA (Code 9633) for PERISCOPE #2 fairing.
replacement, cycle testing and return. Funding includes PERISCOPE #1 and #2 fairing hoist cylinder restoration. Accomplish in conjunction with Section 31.0180.2100.
426A01
28.5281.2200
NOTE 4
Provide project order funding for restoration of OK-276 unit 1, at the NUWCDIVNPT, TAHE Depot.
762/765 430A01 28.2780.4101
Provide $34,775 for replacement of defective AASP ShipAlt 4074D items to NUWCDIVNPT, Code 1531.
440A01 29.0600.2100
NOTE 1
Provide project order funding directly to and ship Multi-Purpose mast (including fairing and closure cap) in conjunction with Section
29.0660.2100 to CDNSWC PHILA (Code 962DL) for fairing replacement, cycle testing, antenna testing and return.
440A01 29.0660.2100
NOTE 1
Provide project order funding directly to and ship Multi-Purpose hoist cylinder in conjunction with Section 29.0600.2100 to CDNSWC PHILA (Code 962DL) for restoration, testing and return.
TYCOM will be responsible to provide all project order funding to the Navy Labs. Contractor will identify points of contact and the amount of funding required.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 95
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 111A01 Title: PRESERVATION
Section/Paragraph No.: 27.0076.2809
Question:
The AWP specifies SY shall conduct sail interior preservation in accordance with Attachment 7 of SMS 6310-081-015, Rev 1, Chg 2. The level of surface preparation and re-preservation specified in Attachment 7 is dependent on as-arrived coating condition, but would normally be planned as a low percentage of touch-up. The AWP also specifies full URO MRC 003 inspection (as authorized by line item 27.0076.U003) in order to reset periodicity, which is normally associated with preservation in accordance with Attachment 8 of SMS 6310-081-015, Rev 1, Chg 2. For planning and estimating purposes, should the Contractor assume touch-up preservation in accordance with Attachment 7, as specified, or full blast and paint for the fairwater interior surface?
Full blast and paint. An AWP change is required to specify full blast and paint.
Note: The government’s assessment is based on the poor interior sail conditions observed on post DMP vessels.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 97
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 132A01 Title: PRESERVATION
Section/Paragraph No.: 82.0058.2819
Question:
Please confirm that the Contractor shall plan for conducting a full blast and paint of the RBP Recess area in accordance with Attachment 14 of SMS 6310-081-015.
Only touchup should be required. Recommend adding NOTE: 1 to GCMA “Accomplish if RBP Recess has not previously received high solids coatings.”
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 101
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 176A01 Title: PRESERVATION
Section/Paragraph No.: 50.0710.2809
Question:
The AWP specifies SY shall conduct potable water tank preservation in accordance with Attachment 7 of SMS 6310-081-015, Rev 1, Chg 2. The level of surface preparation and re-preservation specified in Attachment 7 is dependent on as-arrived coating condition, but would normally be planned as a low percentage of touch-up. The AWP also specifies full URO MRC 003 inspection (as authorized by line item 50.0710.U003) in order to reset periodicity, which is normally associated with preservation in accordance with Attachment 8 of SMS 6310-081-015, Rev 1, Chg 2. For planning and estimating purposes, should the Contractor assume touch-up preservation in accordance with Attachment 7, as specified, or full blast and paint for the potable water tank surfaces?
Full blast and paint. An AWP change is required to change to the GCMA invoking Attachment 8.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 102
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 176A01 Title: PRESERVATION
Section/Paragraph No.: 50.0720.2809
Question:
The AWP specifies SY shall conduct reserve feedwater tank preservation in accordance with Attachment 7 of SMS 6310-081-015, Rev 1, Chg 2. The level of surface preparation and re-preservation specified in Attachment 7 is dependent on as-arrived coating condition, but would normally be planned as a low percentage of touch-up. The AWP also specifies full URO MRC 003 inspection (as authorized by line item 50.0720.U003) in order to reset periodicity, which is normally associated with preservation in accordance with Attachment 8 of SMS 6310-081-015, Rev 1, Chg 2.
For planning and estimating purposes, should the Contractor assume touch-up preservation in accordance with Attachment 7, as specified, or full blast and paint for the reserve feedwater tank surfaces?
Full blast and paint. An AWP change is required to change to the GCMA invoking Attachment 8.
NAVSEA Contract No.: N00024-15-R-4300 Question No.: 105
Ship(s): SSN 762 EOH
Solicitation Related: N/A
Section Letter: Page No.:
AWP Related Yes
SWLIN No.: 176A01 Title: PRESERVATION
Section/Paragraph No.: 50.0790.2809
Question:
The AWP specifies SY shall conduct impulse tank preservation in accordance with Attachment 7 of SMS 6310-081-015, Rev 1, Chg 2. The level of surface preparation and re-preservation specified in Attachment 7 is dependent on as-arrived coating condition, but would normally be planned as a low percentage of touch-up. The AWP also specifies full URO MRC 003 inspection (as authorized by line item 50.0790.U003) in order to reset periodicity, which is normally associated with preservation in accordance with Attachment 8 of SMS 6310-081-015, Rev 1, Chg 2.